Method of constructing multi-storey building balconies
A method of constructing balconies (20) to exterior walls (12) of buildings (10). A prefabricated balcony skeleton having a floor beam structure platform (22) and a three-side rail (26) is brought by crane (18) to the designed location of the first storey and supported by a post and wall plugs (34). The balcony skeleton of the second storey is supported by post, and so forth. The respective portion of the exterior wall (12) is then broken for completing the balcony floor.
The present invention relates to building methods, and more particularly to a method of constructing balconies to exterior building walls.
In the industry of building constructions there are generally known buildings (1) originally provided with balconies extending outdoors of the building line; (2) buildings without balconies; or (3) interior balconies.
Buildings of the second category are sometimes desired to be converted into the first category, namely with exterior balconies. If conventional methods are to be applied, this will demand the erection of scaffolding, casting concrete in suitable forms, etc., which of course is highly inconvenient, expensive and involves considerable nuisance to the tenants of the building in question.
Certain attempts have been made to remedy these disadvantages by employing industrialized building techniques—see for example DE19600255, EP0417127 and WO9324710. However, these methods were still complicated to practice and never gained commercial success.
It is therefore the object of the present invention to provide a quick, low-cost and effective method of constructing exterior balconies onto existing building exterior walls.
It is a further object of the invention that the balconies be of the pre-fabricated type, namely industrially manufactured in plants, and brought to the building site for immediate mounting to the building.
It is a still further object of the invention that the operations of breaking-through to and flooring the balcony can take place at any time later on, as convenient to the tenants.
SUMMERY OF THE INVENTIONThus, provided according to the present invention is a method of constructing multi-storey building balconies, comprising the steps of prefabricating a balcony skeleton having a floor beam structure platform, a three-side rail, attachment means for anchoring the balcony skeleton to an exterior building wall and a support member configured to be supported by a first tubular post extending from below, as well as to support a second tubular post extending upright above the platform; erecting the first tubular post from the ground in alignment with the support member; lifting a first balcony skeleton up to a first storey location against the building wall; supporting the balcony by the first tubular post; anchoring the skeleton to the building wall by the attaching means; mounting the second tubular post on the support member; lifting a second balcony up to a second storey location; supporting the balcony by the second tubular post; anchoring the balcony to the building wall by the attaching means; and so forth with respect to the remaining stories of the building; breaking openings in the building wall to attain access to the respective balconies and completing the floor of the balcony by any known method.
BRIEF DESCRIPTION OF THE DRAWINGSThese and additional features and advantages of the invention will become more clearly understood in the light of the ensuing description of preferred embodiments thereof, given by way of example only with reference to the accompanying drawings, wherein:
As shown in
Let us assume that a balcony is desired to be erected and applied to the wall 12 in front of window opening 14.
A prefabricated balcony skeleton generally denoted 20 is separately manufactured (see below) lifted by crane 18 in order to be installed at its appropriate location.
As can be seen, the pre-fabricated balcony 20 is of minimum weight, and actually comprises only a skeleton or framework of the balcony. Hence, there is provided only a floor platform structure denoted 22 (see
At the geometrical center of the platform 22 a support member 30 is connected, e.g. by welding at a junction of cross beams 24. The support member 30 is in the form of a tubular sleeve projecting to a certain extent from both sides of the platform 22, thereby enabling attaching thereto, in a telescopic manner, a first circular post 32(1) extending from below, and a second tubular support 32(2) extending above the platform 22 (see below).
Turning back to
Referring now to
In the following stage illustrated in
As shown in
This completes the application of the balcony to the first storey, and the same procedure will be applied to the balconies of the second, third and so forth stories.
While the embodiment described is the most simple and basic one, for illustration purposes only, it will be readily understood that many variations can be applied. One example is schematically shown in
An intermediate partition 140 would be necessary, and can be used for further stabilizing and better supporting the balcony 120 by applying additional anchoring facilities to the building wall (not shown).
The method provided according to the invention is thus flexible, versatile and provides a low-cost and effective solution to the problem of attaining more comfort and additional space to apartments.
Those skilled in the art will readily appreciate that numerous additional variations and modifications may be applied to the invention as heretofore exemplified without departing from the scope thereof as defined in and by the appended claims.
Claims
1. A method of constructing multi-storey building balconies, characterized by the steps of:
- (a) prefabricating a balcony skeleton (20) comprising— a floor beam structure platform (22); a three-side rail (26); attachment means (34) for anchoring the balcony skeleton to an exterior building wall (12); and a support member (30) located at about the center of the platform configured to be supported by a first tubular post extending from below, as well as to support a second tubular post extending upright above the platform;
- (b) erecting the first tubular post from the ground in alignment with the support member (30);
- (c) lifting a first balcony skeleton up to a first storey location against the building wall;
- (d) supporting the balcony skeleton by the first tubular post;
- (e) anchoring the balcony skeleton to the building wall by the attaching means (34);
- (f) mounting the second tubular post to the support member (30);
- (g) lifting a second balcony up to a second storey location;
- (h) supporting the second balcony by the second tubular post;
- (i) anchoring the second balcony to the building wall by the attaching means; and so forth with respect to the remaining stories of the building;
- (j) breaking openings in the building wall (12) to attain access to the respective balconies; and
- (k) completing the floor (38) of the balcony by any known method.
2. The method of claim 1 wherein the tubular posts (32) are telescopically received by the support member (30).
3. The method of claim 1 wherein the balcony is supported by two or more tubular posts (132).
Type: Application
Filed: Mar 30, 2003
Publication Date: Sep 21, 2006
Inventor: Moshe Keilaf (Givat Shmuel)
Application Number: 10/551,627
International Classification: E04B 1/00 (20060101); E04G 21/00 (20060101); E04G 23/00 (20060101);