Abstract: Disclosed is a construction method of a cellar for a building completed. The construction method includes fixing supporting structures to bottom concrete of the building; installing a press-in machine on the supporting structures; inserting posts for supporting the building into the foundation under the building by inserting hollow piles into the holes to then insert the piles into the underground using the press-in machine, stacking new piles on the inserted piles, and sequentially inserting the piles using the press-in machine; excavating a foundation under the bottom concrete of the building to prepare an underground space when the building is supported by the posts; and placing the concrete on the horizontal and vertical faces of the underground space prepared by the excavating the bottom concrete of the building.
Type:
Application
Filed:
December 15, 2011
Publication date:
June 21, 2012
Applicant:
Korea Engineering & Consultant Co., Ltd.