Patents by Inventor Joel Melvin Levin

Joel Melvin Levin has filed for patents to protect the following inventions. This listing includes patent applications that are pending as well as patents that have already been granted by the United States Patent and Trademark Office (USPTO).

  • Patent number: 11022005
    Abstract: A steam turbine power plant utilizing high temperature high efficiency industrial heat pumps (IHP) to preheat boiler feedwater is disclosed. The typical extraction steam feedwater preheater is replaced by a plurality of series connected heat pumps that produce boiler feedwater by preheating pressurized condensate from a feedwater pump attached to a condensate receiver. A stack economizer extracts waste heat from boiler flue gas to provide a closed loop of hot source water to the heat pumps. The Heat Rate of the power plant will be reduced by approximately 7%. By using leaving condenser water as source water for the lower temperature stage heat pumps, some of the liberated high temperature source water can be diverted to a new boiler combustion air preheater. The combination of feedwater preheating heat pumps plus a boiler combustion air preheater will reduce the Heat Rate of the power plant by approximately 12%.
    Type: Grant
    Filed: September 21, 2020
    Date of Patent: June 1, 2021
    Inventor: Joel Melvin Levin
  • Publication number: 20210025292
    Abstract: A steam turbine power plant utilizing high temperature high efficiency industrial heat pumps (IHP) to preheat boiler feedwater is disclosed. The typical extraction steam feedwater preheater is replaced by a plurality of series connected heat pumps that produce boiler feedwater by preheating pressurized condensate from a feedwater pump attached to a condensate receiver. A stack economizer extracts waste heat from boiler flue gas to provide a closed loop of hot source water to the heat pumps. The Heat Rate of the power plant will be reduced by approximately 7%. By using leaving condenser water as source water for the lower temperature stage heat pumps, some of the liberated high temperature source water can be diverted to a new boiler combustion air preheater. The combination of feedwater preheating heat pumps plus a boiler combustion air preheater will reduce the Heat Rate of the power plant by approximately 12%.
    Type: Application
    Filed: September 21, 2020
    Publication date: January 28, 2021
    Inventor: Joel Melvin Levin