Patents by Inventor Tin Cheung Wong

Tin Cheung Wong has filed for patents to protect the following inventions. This listing includes patent applications that are pending as well as patents that have already been granted by the United States Patent and Trademark Office (USPTO).

  • Patent number: 11560706
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building comprises multiple prefabricated room units (1). A bottom of a load-bearing structure of the prefabricated room unit (1) is provided with a semi-prefabricated connecting port (2). Reinforcing bars arranged at a top of the prefabricated room unit (1) of a next floor are inserted in the connecting port (2) and thus connected with reinforcing bars arranged therein, so that the prefabricated room units (1) of two adjacent floors are connected with each other through in-situ casting concrete in the connecting port (2). A cast-in-situ concrete interlayer (3) is arranged on a top plate (11) of the prefabricated room unit (1) of a next floor, for connecting adjacent prefabricated room units (1) of a same floor together.
    Type: Grant
    Filed: November 2, 2020
    Date of Patent: January 24, 2023
    Assignee: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Patent number: 11466445
    Abstract: The present invention discloses an integrated steel concrete building and its construction method. The building comprises a plurality of prefabricated room modules of steel, each including at least one column having a structure of hollow steel tube, which has an inner chamber inserted with penetrating rebars and poured with concrete. The penetrating rebars extend upwardly out of the column of the prefabricated room module into an inner chamber of a column of a prefabricated room module of an upper floor.
    Type: Grant
    Filed: August 31, 2020
    Date of Patent: October 11, 2022
    Assignee: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Patent number: 11254016
    Abstract: The present invention relates to a joint mechanism (100), a method for controlling the joint mechanism (100), a multi-arm device (200) including the joint mechanism (100), and a robot. The joint mechanism (100) comprises: a base (4) having a pivot shaft (41); a swinging arm (1) having a first end (11) mounted on the pivot shall (41); a first driving member (2) and a second driving member (3) mounted on the pivot shall (41) for interacting with the swinging arm (1) through magnetorheological fluid; and a first electromagnetic component (22) and a second electromagnetic component (32), configured to change phase state of the magnetorheological fluid. The first driving member (2) and the second driving member (3) can selectively drive tire swinging arm (1) to rotate along a first direction or a second direction.
    Type: Grant
    Filed: August 30, 2018
    Date of Patent: February 22, 2022
    Assignee: GUANGDONG O-MATIC INTELLIGENT ROBOT LIMITED
    Inventors: Wai Man Lee, Tin Cheung Wong
  • Publication number: 20210348379
    Abstract: The present invention discloses an integrated steel concrete building and its construction method. The building comprises a plurality of prefabricated room modules of steel, each including at least one column having a structure of hollow steel tube, which has an inner chamber inserted with penetrating rebars and poured with concrete. The penetrating rebars extend upwardly out of the column of the prefabricated room module into an inner chamber of a column of a prefabricated room module of an upper floor.
    Type: Application
    Filed: August 31, 2020
    Publication date: November 11, 2021
    Applicant: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung WONG, Rosana Wai Man WONG
  • Publication number: 20210187758
    Abstract: The present invention relates to a joint mechanism (100), a method for controlling the joint mechanism (100), a multi-arm device (200) including the joint mechanism (100), and a robot. The joint mechanism (100) comprises: a base (4) having a pivot shaft (41); a swinging arm (1) having a first end (11) mounted on the pivot shall (41); a first driving member (2) and a second driving member (3) mounted on the pivot shall (41) for interacting with the swinging arm (1) through magnetorheological fluid; and a first electromagnetic component (22) and a second electromagnetic component (32), configured to change phase state of the magnetorheological fluid. The first driving member (2) and the second driving member (3) can selectively drive tire swinging arm (1) to rotate along a first direction or a second direction.
    Type: Application
    Filed: August 30, 2018
    Publication date: June 24, 2021
    Inventors: Wai Man LEE, Tin Cheung WONG
  • Patent number: 10982427
    Abstract: Disclosed herewith a prefabricated bathroom and a construction method and an installation method thereof. The prefabricated bathroom includes a bottom unit (11), multiple wall units (12) and a top plate unit (13). One of the wall units (12) is a structural wall (14), which is provided with a recessed top region (141) reserved for later pouring, a middle full-prefabricated structural wall body (142), and a recessed bottom region (143) reserved for later pouring. Top exposed reserve bars (144) of the prefabricated bathroom of a floor are inserted into the recessed bottom region (143) of the prefabricated bathroom of a next floor, and connected with bottom exposed reserve bars (146) thereof, so that the prefabricated bathroom of said floor can be connected with that of said next floor through pouring concrete in the recessed top region (141) and the recessed bottom region (143).
    Type: Grant
    Filed: June 27, 2019
    Date of Patent: April 20, 2021
    Assignee: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Publication number: 20210047824
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building comprises multiple prefabricated room units (1). A bottom of a load-bearing structure of the prefabricated room unit (1) is provided with a semi-prefabricated connecting port (2). Reinforcing bars arranged at a top of the prefabricated room unit (1) of a next floor are inserted in the connecting port (2) and thus connected with reinforcing bars arranged therein, so that the prefabricated room units (1) of two adjacent floors are connected with each other through in-situ casting concrete in the connecting port (2). A cast-in-situ concrete interlayer (3) is arranged on a top plate (11) of the prefabricated room unit (1) of a next floor, for connecting adjacent prefabricated room units (1) of a same floor together.
    Type: Application
    Filed: November 2, 2020
    Publication date: February 18, 2021
    Applicant: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung WONG, Rosana Wai Man WONG
  • Patent number: 10858817
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building comprises multiple prefabricated room units (1). A bottom of a load-bearing structure of the prefabricated room unit (1) is provided with a semi-prefabricated connecting port (2). Reinforcing bars arranged at a top of the prefabricated room unit (1) of a next floor are inserted in the connecting port (2) and thus connected with reinforcing bars arranged therein, so that the prefabricated room units (1) of two adjacent floors are connected with each other through in-situ casting concrete in the connecting port (2). A cast-in-situ concrete interlayer (3) is arranged on a top plate (11) of the prefabricated room unit (1) of a next floor, for connecting adjacent prefabricated room units (1) of a same floor together.
    Type: Grant
    Filed: December 18, 2018
    Date of Patent: December 8, 2020
    Assignee: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Patent number: 10837187
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building includes multiple prefabricated room units, each provided with reserved, exposed reinforcing bars at its top. A bottom of a load-bearing structure of the prefabricated room unit is embedded with grouting couple shafts. Reinforcing bars of the load-bearing structure and of the prefabricated room unit of a next floor are inserted in inner grouting chambers of the grouting couple shafts to connect two prefabricated room units of adjacent floors together. A cast-in-situ concrete interlayer is arranged for connecting adjacent prefabricated room units of a same floor together. The on-site workload is reduced significantly, the construction period is shortened greatly, and the construction is convenient and rapid.
    Type: Grant
    Filed: January 8, 2019
    Date of Patent: November 17, 2020
    Assignee: YAU LEE WAH CONCRETE PRECAST PRODUCTS (SHENZHEN) COMPANY LIMITED
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Publication number: 20200199868
    Abstract: Disclosed herewith a prefabricated bathroom and a construction method and an installation method thereof. The prefabricated bathroom includes a bottom unit (11), multiple wall units (12) and a top plate unit (13). One of the wall units (12) is a structural wall (14), which is provided with a recessed top region (141) reserved for later pouring, a middle full-prefabricated structural wall body (142), and a recessed bottom region (143) reserved for later pouring. Top exposed reserve bars (144) of the prefabricated bathroom of a floor are inserted into the recessed bottom region (143) of the prefabricated bathroom of a next floor, and connected with bottom exposed reserve bars (146) thereof, so that the prefabricated bathroom of said floor can be connected with that of said next floor through pouring concrete in the recessed top region (141) and the recessed bottom region (143).
    Type: Application
    Filed: June 27, 2019
    Publication date: June 25, 2020
    Applicant: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Publication number: 20200190799
    Abstract: Disclosed herewith a prefabricated frame, including a column (1), a main beam (2), a secondary beam (3), and a floor (5). The main beam (2) and the secondary beam (3) are both prefabricated members, and provided with exposed reserve reinforcing bars. The floor (5) is a laminated plate having a prefabricated slab (51) at a lower portion thereof. The prefabricated slab (51), the main beam (2), and the secondary beam (3) are connected together through in-situ casting concrete on respective top portions thereof. The column (1) is a prefabricated column, which has exposed reserve reinforcing bars at a top thereof, and a to-be-cast structure at a bottom thereof for connection with a lower building structure, which has exposed reinforcing bars inserted into the to-be-cast structure. The connection between the column (1) and the lower building structure is achieved by casting in-situ concrete in the to-be-cast structure (12).
    Type: Application
    Filed: June 27, 2019
    Publication date: June 18, 2020
    Applicant: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Publication number: 20200095758
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building comprises multiple prefabricated room units (1). A bottom of a load-bearing structure of the prefabricated room unit (1) is provided with a semi-prefabricated connecting port (2). Reinforcing bars arranged at a top of the prefabricated room unit (1) of a next floor are inserted in the connecting port (2) and thus connected with reinforcing bars arranged therein, so that the prefabricated room units (1) of two adjacent floors are connected with each other through in-situ casting concrete in the connecting port (2). A cast-in-situ concrete interlayer (3) is arranged on a top plate (11) of the prefabricated room unit (1) of a next floor, for connecting adjacent prefabricated room units (1) of a same floor together.
    Type: Application
    Filed: December 18, 2018
    Publication date: March 26, 2020
    Applicant: Yau Lee Wah Construction Materials (Huizhou) Company Limited
    Inventors: Conrad Tin Cheung WONG, Rosana Wai Man WONG
  • Patent number: 10584478
    Abstract: Disclosed is a building frame structure having an edge beam and a construction method thereof. The frame structure includes: a main frame structure and a cantilever beam provided outside of the main frame structure, a beam supported by the cantilever beam, and an outer floor disposed between the main frame structure and the edge beam. The edge beam and the cantilever beam are preforms reserved with exposed reinforcing bars, respectively. The edge beam is provided thereon with a vertical sideboard and a temporary safety rail. The cantilever beam is a beam-shell structure provided with an inner recess. The outer floor is a laminated plate, a lower part of which is a preformed plate. The preformed plate, the edge beam, and the cantilever beam are connected to each other by concrete cast in situ at respective top portions thereof.
    Type: Grant
    Filed: August 14, 2018
    Date of Patent: March 10, 2020
    Assignee: Yau Lee Wah Concrete Precast Products (Shenzhen) Company Limited
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Publication number: 20200011076
    Abstract: Disclosed herewith a modular integrated building and a construction method thereof. The building includes multiple prefabricated room units, each provided with reserved, exposed reinforcing bars at its top. A bottom of a load-bearing structure of the prefabricated room unit is embedded with grouting couple shafts. Reinforcing bars of the load-bearing structure and of the prefabricated room unit of a next floor are inserted in inner grouting chambers of the grouting couple shafts to connect two prefabricated room units of adjacent floors together. A cast-in-situ concrete interlayer is arranged for connecting adjacent prefabricated room units of a same floor together. The on-site workload is reduced significantly, the construction period is shortened greatly, and the construction is convenient and rapid.
    Type: Application
    Filed: January 8, 2019
    Publication date: January 9, 2020
    Applicant: Yau Lee Wah Concrete Precast Products (Shenzhen) Company Limited
    Inventors: Conrad Tin Cheung WONG, Rosana Wai Man WONG
  • Publication number: 20190048575
    Abstract: Disclosed is a building frame structure having an edge beam and a construction method thereof. The frame structure includes: a main frame structure and a cantilever beam provided outside of the main frame structure, a beam supported by the cantilever beam, and an outer floor disposed between the main frame structure and the edge beam. The edge beam and the cantilever beam are preforms reserved with exposed reinforcing bars, respectively. The edge beam is provided thereon with a vertical sideboard and a temporary safety rail. The cantilever beam is a beam-shell structure provided with an inner recess. The outer floor is a laminated plate, a lower part of which is a preformed plate. The preformed plate, the edge beam, and the cantilever beam are connected to each other by concrete cast in situ at respective top portions thereof.
    Type: Application
    Filed: August 14, 2018
    Publication date: February 14, 2019
    Inventors: Conrad Tin Cheung Wong, Rosana Wai Man Wong
  • Patent number: 8608838
    Abstract: The invention provides an air purification system in form of tubing, by which particulates of various sizes in the air flow can be collected. The system includes an air inlet, an air outlet and a particulate removing unit located therebetween, the particulate removing unit including a tubing array of material having low dielectric constant, when an air flow passes through the system electrostatic effect is created between the air flow and the tubing material so as to remove the particulates entrained within the air flow. The invention also provides a method for removing particulates from air flow using the electrostatic effect created between the air flow and said material.
    Type: Grant
    Filed: January 14, 2011
    Date of Patent: December 17, 2013
    Assignee: Yau Lee Innovative Technology, Ltd.
    Inventors: Tin Cheung Wong, Yee Tak Leung
  • Publication number: 20130031722
    Abstract: An air-conditioning bed comprises a bed frame, a mattress placed on and supported by the bed frame, and a head panel located at one end of the bed frame. The mattress is associated with a first air-conditioning system for providing air after being conditioned to the region adjacent to the body of the user of the bed, forming an air-conditioned space. The head panel is associated with a second air-conditioning system for providing air after being conditioned to the region adjacent to the head of the user. The first and second air-conditioning systems include a thermoelectric module.
    Type: Application
    Filed: August 1, 2011
    Publication date: February 7, 2013
    Inventor: Tin Cheung Wong
  • Publication number: 20110271952
    Abstract: The invention relates to a system for reclaiming solar energy in buildings, comprising a fluid inlet header pipe, a fluid outlet header pipe and a plurality of heat collector panels connected to the two pipes at ends thereof respectively. Fluid with a lower temperature from the fluid inlet header pipe enters into the heat collector panels, where it is heated to a higher temperature by the solar energy stored therein, and then discharges from the system via the fluid outlet header pipe for energy reuse. The heat collector panels are mounted on the inner surface of the cladding panels of the building, so that the outer appearance of the building will not be negatively influenced by the system.
    Type: Application
    Filed: May 4, 2011
    Publication date: November 10, 2011
    Applicant: Yau Lee Innovative Technology Limited
    Inventors: Tin Cheung WONG, Chi Ming Antonio Chan, Wai Sin Lau
  • Publication number: 20110179950
    Abstract: The invention provides an air purification system in form of tubing, by which particulates of various sizes in the air flow can be collected. The system comprises an air inlet, an air outlet and a particulate removing unit located therebetween, the particulate removing unit including a tubing array of material having low dielectric constant, when an air flow passes through the system electrostatic effect is created between the air flow and the tubing material so as to remove the particulates entrained within the air flow. The invention also provides a method for removing particulates from air flow using the electrostatic effect created between the air flow and said material.
    Type: Application
    Filed: January 14, 2011
    Publication date: July 28, 2011
    Applicant: YAU LEE INNOVATIVE TECHNOLOGY LIMITED
    Inventors: Tin Cheung WONG, Yee Tak LEUNG
  • Patent number: 7058623
    Abstract: A computer automated method for identification, management and retrieval of engineering drawings in digital format where the central processing unit locates and identifies specific predefined textual and graphical information, relating to that drawing, in accordance with predefined algorithms. The textual information thus identified is then stored in accordance with predefined criteria to allow the engineering drawing to be identified and retrieved by reference to that textual information.
    Type: Grant
    Filed: February 8, 2001
    Date of Patent: June 6, 2006
    Assignee: VHSoft Technologies Company Limited
    Inventor: Tin Cheung Wong