Methods for Introducing Pulsing to Cementing Operations
A method for bonding a well bore to a casing may include several steps. Casing may be introduced into the well bore and pulses of fluid may be directed from within the casing into the well bore. An annulus between an inner surface of the well bore and an outer surface of the casing may be filled with fluid. A method for reducing fluid or gas migration into a fluid in the annulus may include inducing pressure pulses in the fluid before the fluid has cured.
The present invention relates to cementing operations, and, more particularly, methods and apparatuses for providing more competent cement bonds during and after cementing operations in well bores.
Settable compositions such as cement slurries may be used in primary cementing operations in which pipe strings, such as casing and liners, are cemented in well bores. In performing primary cementing, a cement may be pumped through the casing into an annulus between the walls of a well bore and the casing disposed therein. The cement typically is pumped into this annulus until it reaches a predetermined height in the well bore to provide zonal isolation. The cement cures in the annulus, thereby forming an annular sheath of hardened cement (e.g. a cement sheath) that supports and positions the pipe string in the well bore and bonds the exterior surface of the pipe string to the walls of the well bore.
Fluid or gas influx into the annulus and cement therein during the cement curing or “gelling” stage is quite common. This fluid or gas influx can damage the cement bond between the well bore formation and the exterior surface of the casing. Moreover, the buildup of residues such as filter cake on or in the surface of the well bore also can prevent a complete bond between the cement and the well bore.
The present invention relates to cementing operations, and, more particularly, methods and apparatuses for providing more competent cement bonds during and after cementing operations in well bores.
A method for bonding a well bore to a casing therein, may comprise the steps of introducing the casing into the well bore, directing pulses of fluid from within the casing into the well bore, and filling an annulus between an inner surface of the well bore and an outer surface of the casing with the fluid. The step of directing pulses of fluid may performed while moving the casing further into the well bore. Additionally or alternatively, the method may further comprise the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce filter cake formed on the inner surface of the well bore. Additionally or alternatively, the method may further comprise the step of vibrating well fluid at a resonance frequency for the well fluid. Additionally or alternatively, the method may further comprise the step of vibrating the casing at a resonance frequency for the casing. Vibrating the casing at a resonance frequency may comprise the step of directing pulses of fluid into the well bore at a frequency and pressure selected to induce resonance vibrations in the casing. Additionally, or alternatively, the fluid may be a cement. If the fluid is a cement, the method may further comprise the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce the amount non-cement material on the casing, and the method may further comprise the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce filter cake formed on the inner surface of the well bore, such that the pulses have a dual-step profile.
A method for reducing fluid or gas migration into a fluid in an annulus formed between a surface of a well bore in a formation and a casing, may comprising the step of inducing pressure pulses in the fluid before the fluid has cured. The fluid may be a cement. The method may further comprise the step of selecting a frequency and amplitude for the pressure pulses such that the pressure pulses prevent shear damage of the fluid during curing. The step of inducing pressure pulses in fluid before the fluid has cured may comprise the step of inducing a low-amplitude pressure pulse. Additionally, or alternatively, the step of inducing pressure pulses in fluid before the fluid has cured may comprise the step of inducing a low-frequency pressure pulse. Alternatively, the step of inducing pressure pulses in fluid before the cement has cured may comprise the step of inducing a pressure pulse having a dual-step profile.
The features and advantages of the present invention will be readily apparent to those skilled in the art. While numerous changes may be made by those skilled in the art, such changes are within the spirit of the invention.
These drawings illustrate certain aspects of some of the embodiments of the present invention, and should not be used to limit or define the invention.
The present invention relates to cementing operations, and, more particularly, methods and apparatuses for providing more competent cement bonds during and after cementing operations in well bores.
These methods and apparatuses may result in less fluid influx during the pre and post gelling stage of a cement slurry or other fluid, resulting in significant savings in time and cost, and improved hydrocarbon recovery.
Typically, a cementing operation involves attaching float shoe 110 to an end of casing 102 and introducing casing 102 into well bore 101. Cement 103 may then flow down the interior of casing 102 and out through float shoe 110 into annulus 104. Alternatively, a reverse cementing operation may be used to place cement 103 in annulus 104. In either instance, as cement 103 enters annulus 104, it displaces material such as drilling fluid, filter cake, gas, or debris occupying annulus 104. Typically, as cement 103 enters annulus 104, some material occupying annulus 104 remains, particularly near the walls of well bore 101 and casing 102. In other words, a displacement efficiency of the material is typically significantly below 100% efficiency, which would correspond to the instance when cement 103 completely displaces the material occupying annulus 104. Low displacement efficiency results in undesirable channeling and pocketing, which causes the cement bond to be compromised.
The material may be more completely replaced by cement 103 when pulsing or oscillation is used during the introduction of cement 103 into annulus 104. A number of devices rely on fluid oscillation effects to create pulsating fluid flow. Generally, these devices connect to a source of fluid flow, provide a mechanism for oscillating the fluid flow between two different locations within the device and emit fluid pulses downstream of the source of fluid flow. These “fluidic oscillator” 112 devices require no moving parts to generate the oscillations and have been used in various applications for which pulsating fluid flow is desired, such as massaging showerheads, flow meters, and windshield-wiper-fluid-supply units. Specialized fluidic oscillator devices have been developed for the oilfield industry, such as, for example, the Pulsonix TF tool offered by Halliburton Energy Services, Inc. of Duncan, Okla.
In addition to providing for more complete displacement of materials in annulus 104, fluidic oscillator 112 may help mitigate fluid and/or gas migration during cement cure time. As shown in
Referring now to
Since each well will have different frequency variables, such as fluid, rate, and geometry, it may be particularly useful for fluidic oscillator 112 to have variable components. A fluctuating or variable fluidic oscillator 112 may be used to allow for alternating resonance of casing 102 and well bore fluids. A high frequency component, a low frequency component, or a combination of the two may enhance the effectiveness of the system. These components may be further combined with either high or low amplitude components, or both. To reach the various resonance ranges, variable rate or “dual-step profile” pumping may be used. Alternatively, two or more fluidic oscillators 112 could be used to alternate between two or more resonances.
As an alternative to alternating between multiple frequencies and/or amplitudes, a specific design may be used for a specific well bore fluid system. As more cement 103 is pumped, resonant frequency will change. Thus it may be desirable for fluidic oscillator 112 to change based on changes in the system. This may be a result of monitoring of instrumentation measuring the level of excitation. This may be done with a sensor such as a hydrophone, a pressure transducer, a flow device, an accelerometer, or any number of other devices known in the art. This monitoring may allow for fluidic oscillator 112 to maintain resonance.
Referring now to
Idealized pressure wave forms can be controlled to provide optimal pulsation and help prevent shear of cement 103 during dehydration. Examples of what the inventors envision as optimal pressure pulses are illustrated in
Yet another embodiment involves a low cost “tubing” size fluidic oscillator 112, as shown in
The concept of “pulsing” the top plug after catching cement is illustrated in
Pulsation or oscillation may be used to set more competent balanced plugs. Shown in
This disclosure covers two basic fluid energy principles: fluidic oscillation and pressure pulsing technology. These two principles can be used during or after the cementing job. This technology is adaptable for both primary cementing and setting of balanced plugs.
This technology potentially could reduce sustained casing pressure which is a major concern particularly offshore. Earlier methods do not consider the advantage of inducing fluid energies by fluidic oscillation or pressure pulsation methods. This methodology greatly enhances the chances for competent cement bonding.
Therefore, the present invention is well adapted to attain the ends and advantages mentioned as well as those that are inherent therein. The particular embodiments disclosed above are illustrative only, as the present invention may be modified and practiced in different but equivalent manners apparent to those skilled in the art having the benefit of the teachings herein. Furthermore, no limitations are intended to the details of construction or design herein shown, other than as described in the claims below. It is therefore evident that the particular illustrative embodiments disclosed above may be altered or modified and all such variations are considered within the scope and spirit of the present invention. In particular, every range of values (of the form, “from about a to about b,” or, equivalently, “from approximately a to b,” or, equivalently, “from approximately a-b”) disclosed herein is to be understood as referring to the power set (the set of all subsets) of the respective range of values, and set forth every range encompassed within the broader range of values. Also, the terms in the claims have their plain, ordinary meaning unless otherwise explicitly and clearly defined by the patentee.
Claims
1. A method for bonding a well bore to a casing therein, comprising the steps of:
- introducing the casing into the well bore;
- directing pulses of fluid from within the casing into the well bore; and
- filling an annulus between an inner surface of the well bore and an outer surface of the casing with the fluid.
2. The method of claim 1, wherein the fluid is a cement.
3. The method of claim 1, wherein the step of directing pulses of fluid is performed while moving the casing further into the well bore.
4. The method of claim 1, further comprising the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce filter cake formed on the inner surface of the well bore.
5. The method of claim 2, further comprising the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce the amount non-cement material on the casing.
6. The method of claim 5, further comprising the step of selecting a frequency and pressure level for the pulses of fluid so as to reduce filter cake formed on the inner surface of the well bore, such that the pulses have a dual-step profile.
7. The method of claim 1, further comprising the step of vibrating the casing at a resonance frequency for the casing.
8. The method of claim 7, wherein the step of vibrating the casing at a resonance frequency comprises the step of directing pulses of fluid into the well bore at a frequency and pressure selected to induce resonance vibrations in the casing.
9. The method of claim 1, further comprising the step of vibrating well fluid at a resonance frequency for the well fluid.
10. (canceled)
11. (canceled)
12. A method for reducing fluid or gas migration into a fluid in an annulus formed between a surface of a well bore in a formation and a casing, comprising the step of inducing pressure pulses in the fluid before the fluid has cured, further comprising the step of selecting a frequency and amplitude for the pressure pulses such that the pressure pulses prevent shear damage of the fluid during curing.
13. The method of claim 12, wherein the step of inducing pressure pulses in fluid before the fluid has cured comprises the step of inducing a low-amplitude pressure pulse.
14. The method of claim 12, wherein the step of inducing pressure pulses in fluid before the fluid has cured comprises the step of inducing a low-frequency pressure pulse.
15. A method for reducing fluid or gas migration into a fluid in an annulus formed between a surface of a well bore in a formation and a casing, comprising the step of inducing pressure pulses in the fluid before the fluid has cured, wherein the step of inducing pressure pulses in fluid before the cement has cured comprises the step of inducing a pressure pulse having a dual-step profile.
Type: Application
Filed: Dec 20, 2007
Publication Date: Jun 25, 2009
Inventors: Earl Webb (Duncan, OK), Henry Rogers (Duncan, OK), Roger Schultz (Ninnekah, OK)
Application Number: 11/961,458
International Classification: E21B 33/13 (20060101);