COMPOSITE CONCRETE ROOF FOR AN OUTER LNG CONTAINMENT TANK AND METHOD OF MAKING THE SAME
A method for constructing a composite concrete roof on an outer LNG containment tank is disclosed. The roof includes a roof assembly and a plurality of precast reinforced concrete roof elements. The roof assembly is mounted on a tank shell. At least some of the roof elements including a concrete body and embedded metal plates adapted to be welded to the roof assembly. The roof elements are welded to the roof assembly to provide additional strength and stiffness to the roof assembly. Preferably, no or minimal cast in place concrete structural joints are needed to join the roof elements to the roof assembly and or top of the shell. Ideally, the roof assembly includes a membrane and mounting beams connected to the membrane. The embedded plates of the roof assemblies are welded to the mounting beams on the roof assembly. The method may further include mounting or welding the roof elements to the roof assembly while workers access the interior of the shell to perform work therein. A tank having a composite concrete roof made according to the above method is also disclosed.
Latest Patents:
The present invention relates generally to the construction of LNG (liquefied natural gas) full containment tanks, and more particularly, to the construction of roofs for outer LNG containment tanks.
BACKGROUNDLarge storage tanks are typically designed with a so-called “roof”—a reinforced concrete dome centered continuously on top of and integrally connected to a tank shell. Tank roofs for LNG (liquefied natural gas) tanks may be large structures. The roof of large storage tanks need to be reinforced to handle the construction, operating and earthquake loads. One approach for creating such a roof is casting in place a roof on top of a steel support framing. However this approach for very large tanks is a time-consuming process, and may be very problematic at remote site locations.
Another method of constructing a roof is to erect a roof assembly including a metal structural and membrane plate to form a steel dome in a “low” position on the ground. Then the steel dome is raised to the top of the tank wall or shell to a “high” position using air pressure & cable guides. After the steel dome has been welded in position and is safe to allow casting in place activities, the tank roof is pressurized to aid in cast in place activities. The air pressure allows for more concrete to be placed on the roof. As curing time can be long, the air pressure source must be secure and the tank leak tight. Most of the large tanks require the concrete to be placed in multiple lifts to prevent overload and collapse of the steel frame. During the time that the tank needs to be pressurized, no work may proceed inside the tank.
Building with precast concrete elements is also a known approach in the construction of various structures when construction time at the site needs to be minimized, and when site conditions and location are problematic for casting in place. However, roofs are very specific structural elements due to their function and configuration. Large storage tank roofs are not easily constructed out of precast elements. Due to the large tensile forces that occur during tank operation, effective structural connections between separate precast concrete elements are difficult to construct. Typically, such connections between roof elements are made through casting in place structural connections between roof elements. However, such connections are time consuming and expensive to make.
SUMMARYA method for constructing a composite concrete roof on an outer LNG containment tank is disclosed. The roof includes a roof assembly and a plurality of precast concrete roof elements. The roof assembly is mounted on a tank shell. At least some of the roof elements including a concrete body and embedded metal plates adapted to be welded to the roof assembly. The roof elements are welded to the roof assembly to provide additional strength and stiffness to the roof assembly. Ideally, the roof assembly includes a membrane and mounting beams connected to the membrane. The metal plates are then welded to the mounting beams on the roof assembly. The method may further include mounting or welding the roof elements to the roof assembly while workers access the interior of the shell to perform work therein. A tank is also described which has a roof constructed as described above.
The roof elements can be quickly attached to the roof assembly mounted atop the tank shell to form the roof or dome. The addition of the roof elements to the roof assembly stiffens the dome as concentric courses of roof elements are welded to the roof assembly. The courses are welded to the roof assembly successively from the radial outermost course to radial innermost course until all the roof elements are applied. The roof elements can be safely placed on the dome without the need for pressurizing the tank interior and will allow work to proceed inside the tank even as the roof elements are being added.
These and other objects, features and advantages of the present invention will become better understood with regard to the following description, appended claims and accompanying drawings where:
In a first embodiment, a full containment LNG tank 18 is shown in
In this particular embodiment, outer tank 20 is primarily made of precast reinforced concrete elements which reduce fire risk relative to using a primarily steel outer container or tank. The construction of outer tank 20 involves assembling precast reinforced concrete elements for a foundation 24, including a base mat assembly 100 and an outer ring beam 200, an outer wall or shell 300 and a roof 400. As an example of order of magnitude, outer tank 20 in this embodiment has a diameter of approximately 80 meters, an overall height (to the top of the dome of roof 400) of about 50 meters, and a height to the top of shell 300 of about 40 meters. Those skilled in the art of LNG facilities construction will appreciate that much larger or smaller tanks can be built and still use the design considerations described herein. However, tanks having diameters of at least 25 meters are particularly well suited to the construction methods described herein which utilize precast reinforced concrete elements. These elements ideally can be welded together to form structural welds thereby minimizing the number of cast in place concrete structural joints which have to be made to form an outer containment tank.
Ideally, inner tank 22 can be assembled at the same time as roof 400 is being built to save time and money in the overall construction of inner tank 22 and outer tank 20. Note in
Inner tank 22 can be built in any of a number of ways which may require welding processes to connect individual plates. For example, the plates can be joined using shielded metal arc welding (SMAW) and submerged arc welding (SAW) for 9% nickel tanks of the size described above, i.e. having a diameter greater than 25 meters. In this particular example, inner tank 22 can be friction stir welded (FSW) by plate at a time erection method. A course of plates at a time can be welded with the bottom (thickest) first and then subsequent (thinner) courses welded there above. Scaffolding (not shown) can be used as each course is added. Alternatively, inner tank 22 can be constructed course down either by supporting the tank from the roof to allow insertion of the next course or by supporting on jack stands to allow insertion of the next course. For the last two methods, the scaffolding need be erected only one time. By way of example and not limitation, another alternative method is to use coil material shaped to the curvature required for the tank. Coil tank building occurs from the top course down either using jacking or by roof supported. Expanded pearlite insulation is typically used in the annulus formed between inner tank 22 and outer tank 22. Although not shown, an under bottom insulating layer, which can be made of foam glass, is applied on the top of base mat assembly 100 with inner tank 22 prior to inner tank 22 being placed there on.
Foundation 24, i.e., base mat assembly 100 and ring beam 200, is designed to support inner tank 22 and outer shell 300. Outer shell 300 rests upon and transfers loads directly to outer ring beam 200 preferably through welded connections. A particularly significant load is the torsional load applied to ring beam 200 from outer shell 300. Base mat assembly 100 is secured to and transfers loads to outer ring beam 200 as well through a cast in place joint 270, which is best seen in
Concrete ribs 130 and grooves 132 are also formed on the longitudinally and laterally extending edge surfaces of concrete body 114. Locating projections 106 and ribs 130 and receiving recesses 110 and grooves 132 allow a plurality of base mat elements 102 to be placed in interlocking juxtaposition as suggested in
Base mat assembly 100 is constructed by juxtaposing base mat elements 102 in both first and second generally perpendicular directions as seen in
Tensile members 150 are fed through tensile conduits 120, 122, 124 and 126 as base mat elements 102 are being juxtaposed to one another. After the mating surfaces on the base mat elements 102 are properly located relatively to one another, tensile members 150, i.e. cables, are post-tensioned and anchored by anchors 152 to clamp base mat elements 102 together. In this particular example, tensioning can be accomplished such as by using a Williams Strand Anchor System available from Williams Form Engineering of Belmont, Mich., USA. Those skilled in the art will appreciate that other tensioning systems can also be used to post-tension and anchor tensile members 150. After the tensioning is complete, anchors 152 are locked in place on tensile members 150 to maintain the tension in tensile members 150 with anchors 152 bearing upon base mat elements 102.
Liner plates 104 of each of base mat elements 102 are then welded together to form a part of a generally contiguous membrane 140 on the top of base mat assembly 100. As tensile conduits 120, 122, 124 and 126 are located above and below the central horizontal plane 144 of concrete body 114, the top and bottom surfaces of base mat elements 102 are held together and do not separate due to the post tensioning of tensile members 150 with anchors 152 clamping about base mat elements 102, preferably even under construction and operating loads applied to base mat assembly 100.
C. Mounting of Base Mat Elements on PilesBase mat elements 102 can be assembled on a graded, level surface if the underlying surface or soil is sufficiently stiff. However, if the soil does not provide adequate support, base mat elements 102 can be mounted on piles 160. The upper portion of a typical pile 160 is seen in
The corners and long sides of base mat elements 102 will be supported by six cooperating supporting flanges 166. Voids 174 are created by the intersection of the corners and along the sides of cooperating base mat elements 102. In the case where piles are used, base mat elements 102 can include reinforcing bar loops (not shown) which are embedded in concrete body 114 and extend laterally and longitudinally from concrete body 114. The loops will loop over vertically extending reinforcing bars 170. Concrete is cast in these voids 174 about the loops and reinforcing bars 170. Fitted liner plate 176 is anchored by J-hooks in the cast concrete so that liner plates 104 and 176 can be welded together to form generally continuous top membrane 140 on base mat assembly 100.
III. Outer Ring Beam 200Also formed within concrete body 220 are circumferentially extending lower and upper tensile conduits 232, 234. In this particular embodiment, there are four such tensile conduits 232, 234. Two of these tensile conduits 232 are generally arranged below and two conduits 234 are arranged above the horizontal center plane 236 of ring beam element 202. Also, two of the tension conduits 232, 234 are arranged beneath base plate 206 and two are located radially inwardly beneath liner plate 204 closer to the inner radial surface 224. These cooperating locations of tensile conduits 232, 234 allow tensioning members 250, i.e., cables, to pass through each of ring beam elements 202 and assist in counter balancing the bending, shearing and torsional loads applied to base plate 206 by outer shell 300. Also, tensile members 250 and anchors 252 cooperate to clamp about ring beam elements 202 to prevent the abutting ring beam elements 202 from displacing with respect to one another. In this particular example, high density polyethylene (HDPE) tubing is used to form the tensile conduits 232, 234 in concrete body 220. Of course, the tensile conduits could be made of other suitable materials such as steel or other structurally strong materials. Downwardly and upwardly opening steps 238 and 240 allow elements 202 to be vertically interlocking as well. Also, located within concrete body 220 is a plurality of reinforcing bars (not shown) which are conventional for adding tensile strength to cast concrete bodies. Extending radially inwardly are reinforcing bars or J-hooks 242 which are later to be included in cast concrete connection 270 which connects base mat assembly 100 with ring beam 200.
Ring beam elements 202 are juxtaposed with respect to one another with locating concrete ribs 226 of one ring beam element being held within locating recess 230 of the adjacent ring beam element. Similarly, cooperating steps 238 and 240 assist in vertical alignment between ring beam elements 202. Tensile members 250 are placed through tensile conduits 232 and 234 as the ring beam elements are being positioned adjacent one another. As seen in
After the individual ring beam elements 202 are aligned and clamped together using tensile members 250 and anchors 252, base plates 206 are welded together along their radially extending abutting edges to form an annular ring which strengthens outer ring beam 200. Finally, liner plates 204 on ring beam elements 202 are also welded together along their radially extending edges to form a continuous membrane 244 on the radial inner side of outer ring beam 200, as best seen in
Each of shell elements 302 includes a pair of tapered carbon steel side plates 304 and a carbon steel liner plate 306 forming a generally U-shaped steel cross-section. In this example, the liner plate 306 is about 10 mm thick and side plates 304 are about 25 mm thick. The width of side plates 304 is about 800 mm at their bottom and 400 mm at the top providing the tapered shape to shell element 302. A base plate 312 connects side plates 304 and liner plate 306 at the bottom of shell element 302. Numerous reinforcing bars 310 are welded to and extend from side plate 304 to the opposing side plate 304 and from base plate 312 to top end cap 314. Base plate 312 is about 50 mm in thickness in this example. A steel end cap plate 314, also about 50 mm thick, is welded to side plates 304 and steel liner plate 306 at the top of shell element 302. Concrete is cast in place in the U-shaped volume defined by side plates 304 and steel liner plate 306 and about reinforcing bars 310 and J-hooks 316 to form reinforced concrete body 318. Liner plate 306 acts as a vapor/gas barrier
B. Constructing Shell 300Shell 300 is constructed by arranging shell elements 302 vertically upon outer ring beam 200. Initially, base plates 312 are arranged radially slightly outside of their final position for welding with shell elements 312 being slightly radially spaced apart. Shell elements 302 are then moved radially inwardly until all base plates 312 and side plates 304 are brought into abutment at the proper radial position atop of base plates 206 of ring beam 202. Erection gear will be used to finally align and pull the side plates 304 closely together to begin welding.
As seen in
Shell elements 302 are splice welded to accommodate load transfer even under earthquake or missile impact. If additional strength is needed, shell elements 302 may be designed to be mechanically interlocking with one another as well as being joined by welds such as weld 320. Ideally, the welded connections between shell elements 302 will be comparable in strength to conventional cast in place connections formed between shells.
All of shell elements 302 are permanently welded together to form shell 300, with the exception of 2-4 special half shell elements 302′. Half shell elements 302′ are similar to shell elements 302 except they are only about half the height of regular shell elements 302. These special shell elements 302′ will be temporarily sealed with shell opening 350 to accommodate air raising of roof assembly 404, as suggested in
As an alternative to permanently closing construction opening 350, liner plates can be welded to close shell opening 350. Then reinforcing bars and steel rib stiffeners can be placed in a form and concrete can be cast in place to form a cast in place shell element similar to that used in the design of the precast shell elements 302. Shell 300 should have great strength when completed due to the welded connections 320 on the inner and outer edges of side plates 304 which cooperate to form a large number of radially extending stiffeners arranged around the circumferential periphery of outer tank 20.
C. Alternate Shell DesignLower shell element 302a includes a concrete body 316a to which a pair of circumferentially spaced apart side plates 304a, liner plate 320a, upper end cap plate 314a and lower base plate 312a are anchored or embedded (anchors and reinforcement bars not shown). Base plate 312a is welded by welds 324a to base plate 206 of ring beam 200. Upper end cap plate 314a has two downwardly depending sockets 362 formed therein.
Upper shell element 302b includes a concrete body 316b to which a pair of circumferentially spaced apart side plates 304b, liner plate 320b, upper end cap plate 314b and lower base plate 312b are anchored (anchors and reinforcement bars not shown). Two downwardly depending and circumferentially spaced apart alignment pipes 360 are welded to lower base plate 312b. As seen in
Referring in general now to
Once enough weld joints have been formed to safely support roof 400, the pressurization within shell 300 is removed. Personnel can then access the inside of the outer tank 20 to construct inner tank 22. Additional welding is done to complete the circumferential weld joint between the roof membrane 412 and shell membrane 340. Special extra strength roof elements 402′ are attached to shell 300 and roof frame 404 forming the radial outermost course of roof elements 402. Then typical roof elements 402 are attached to roof frame 404 with the radial outermost course of roof elements 402 being attached first. Then the successive next radial outermost course of roof elements is added until all the rings of roof elements 402 are in place forming roof 400.
A. Roof Assembly 404Roof assembly 404 is built on the ground in this particular preferred exemplary embodiment. Roof frame 406 comprises a plurality of radially and circumferentially extending wide flange beams 420, as best seen in
Referring now to
Half shell elements 302′ are removed to provide access from within shell 300. Referring now to
Roof elements 402 and 402′ are mounted to roof assembly 404 after roof assembly 404 has been affixed by weldments to shell 300.
Roof element frame 428 is used to construct precast reinforced concrete roof elements 402, as seen in
For the outermost concentric course of roof elements 402′ which secure to both roof assembly 404 and to shell 300, the design is slightly different from that of roof elements 402 disposed on the inner radial concentric courses. As shown in
Provided in concrete body 440′ are four access openings 472 (two seen in
The outer concentric ring or course of roof elements 402′ are located adjacent shell 300 and this outer ring of roof elements 402′ is first welded to roof assembly 404 and to shell 300. This outer ring of roof elements 402′ adds significant strength to roof 400. Subsequently, second through eighth courses of roof elements 402 are sequentially welded to roof assembly 404 starting from the radially outermost course and then each concentric course of roof elements is added until all rows of roof elements 402 are in place to form a complete roof 400 such as seen in
L-shaped brackets 432 of roof elements 402 are mounted atop and are welded to tubular mounting beams 414 creating welds such as the weld joint 436 seen in
While in the foregoing specification this invention has been described in relation to certain preferred embodiments thereof, and many details have been set forth for purpose of illustration, it will be apparent to those skilled in the art that the invention is susceptible to alteration and that certain other details described herein can vary considerably without departing from the basic principles of the invention. For example, any one or more of base mat assembly 100, ring beam 200, outer shell 300 or roof 400 could be constructed using conventional cast in place construction techniques while the other components are constructed using the precast elements as described herein. As another example of an alternative embodiment, the roof assembly could be directly built atop shell 300 such as by using a crane. In this instance, roof assembly 404 would not have to be airlifted and attached atop shell 300. However, ideally even in this embodiment, the shell elements 402 could be welded to the roof assembly concurrently with the construction of the inner tank 22 to save construction time on building outer tank 20 and inner tank 22.
While beam ring 200 described in the above particular exemplary embodiment was used in conjunction with a full containment LNG tank, a beam ring could certainly be used in other applications. For example, the ring beam could be used in cases where neither a liner plate or thick structural base plate is necessary. In this case, the ring beam need only comprise ring beam elements having precast reinforced concrete bodies with embedded tensile conduits which receive tensile members there through so that the tensile members may be tensioned and anchored by anchors to form the beam ring. Although not required, preferably the ring beam elements would be interlocking with one another.
Claims
1. A method for constructing a composite concrete roof on an outer LNG containment tank, the method comprising:
- mounting a roof assembly on a tank shell; providing a plurality of precast reinforced concrete roof elements, at least some of the roof elements including a concrete body and embedded metal plates adapted to be welded to the roof assembly;
- and mounting the roof elements to the roof assembly by welding the metal plates of the roof elements to the roof assembly to form structural welds there between and to enhance the stiffness of the roof.
2. The method of claim 1 wherein:
- the roof assembly includes longitudinally extending mounting beams; and the metal plates of roof elements are welded to the mounting beams.
3. The method of claim 1 wherein:
- the roof assembly includes a membrane and overlying mounting beams;
- and the metal plates of the roof elements are welded to the mounting beams.
4. The method of claim 1 wherein:
- the roof assembly includes a membrane and overlying mounting beams, the mounting beams extending circumferentially and radially over the membrane;
- and the metal plates of the roof elements are welded to the mounting beams.
5. The method of claim 1 further comprising the steps of:
- pressurizing the tank shell to air lift the roof assembly to the top of the tank shell and mounting the roof assembly to the top of the tank shell;
- opening an access opening in the tank shell to allow access within the shell; and
- concurrently welding the roof elements to the roof assembly as work is being performed within the shell.
6. The method of claim 1 wherein:
- the pressure within the shell is at atmospheric pressure so that workers may work within the shell of the tank as roof elements are being welded to the roof assembly.
7. The method of claim 1 further comprising:
- welding the roof elements to the roof assembly to form concentric courses of ring elements.
8. The method of claim 7 wherein:
- the radial outer most course of roof elements is first welded to the roof assembly before any of the other courses of roof elements.
9. The method of claim 7 wherein:
- the radial outer most course of roof elements is welded to the roof assembly first;
- and then the remaining courses of roof elements are successively added from the radial outermost course to the radial innermost course.
10. An outer LNG containment tank comprising:
- a tank shell and a composite concrete roof mounted to the top of the tank shell, the roof including a roof assembly and a plurality of roof elements welded to the roof assembly by structural welds.
11. The tank of claim 10 wherein:
- at least some of the roof elements including a concrete body and embedded metal plates which are welded to the roof assembly.
12. The tank of claim 11 wherein:
- the roof assembly includes longitudinally extending mounting beams; and the metal plates of roof elements are welded to the mounting beams.
13. The tank of claim 11 wherein:
- the roof assembly includes a membrane and overlying mounting beams;
- and the metal plates of the roof elements are welded to the mounting beams.
14. The tank of claim 11 wherein:
- the roof assembly includes a membrane and overlying mounting beams, the mounting beams extending circumferentially and radially over the membrane;
- and the metal plates of the roof elements are welded to the mounting beams.
15. The tank of claim 10 wherein:
- the roof elements are welded to the roof assembly to form concentric courses of ring elements.
15. The tank of claim 15 wherein:
- the radial outermost course of ring elements is welded to the roof assembly and to the tank shell.
Type: Application
Filed: Dec 23, 2008
Publication Date: Jun 24, 2010
Applicant:
Inventors: Lestle R. Shockley (San Ramon, CA), Vincent G. Borov (Martinez, CA)
Application Number: 12/342,495
International Classification: E04B 7/10 (20060101); E04B 7/00 (20060101);