EMERGENCY FREQUENCY LOAD SHEDDING SCHEME
A load shedding system and method for controlling imbalances in a power system includes a signal generator adapted to generate a signal representative of a local system, and a modifying circuit adapted to adjust set frequencies. The system also includes a processing circuit adapted to process data received from the signal generator and modifying circuit and set load shedding priorities for the local system based on the processed data.
Latest ELECTRIC POWER RESEARCH INSTITUTE, INC. Patents:
This application is a divisional application of U.S. patent application Ser. No. 12/131,986, filed Jun. 3, 2008, which is currently pending.
BACKGROUND OF THE INVENTIONThe present invention relates generally to a system and method for controlling imbalances between load and supply in power systems, and more particularly to a load shedding system and method for controlling imbalances in a power system.
In power systems of today, it is essential that a balance between the amount of power being used (“load”) and the amount of power being supplied (“supply”) be maintained to provide a secure and reliable power system, thereby preventing blackouts and power interruptions. Every imbalance between the supply and load causes a deviation of the frequency. More importantly, if the load exceeds the supply and the deficit is not counteracted, the deficit in supply can lead to system interruptions and even blackouts.
One way to control these imbalances is to use load shedding. Load shedding (i.e., opening a circuit breaker to reduce the load) has been used to mitigate imbalances between supply and load since the infancy of power systems, and has basically remained unchanged over the last 100 years. During the same period, the logic used to shed the load has also only changed slightly. Unfortunately, the power systems, expectations of the users, and their loads have changed drastically, thereby necessitating better ways to handle these imbalances.
Currently, there are basically two kinds of under frequency load shedding schemes: the first is based on pre-determined frequencies encountered during a frequency decline, and the second is based on the rate of decline of the frequency (i.e., first derivative of frequency with respect to time). Both schemes use different time delays (from zero delay to several seconds, in some cases).
The first scheme drops the load based on predefined frequencies, f1, f2, f3, . . . fn in the hope that the dropped load would be enough to reverse the frequency decline by narrowing the gap between the supply and the connected load. The predefined set points are based on previous studies, and they do not consider the actual state of the system when the disturbance occurs or any dynamic system conditions ensuing from the disturbance. Though this scheme is relatively good when there is a smaller disturbance coupled with a long time to respond, it is unable to differentiate between some “normal” system oscillations and actual system disturbances. Hence, it may not shed enough load to arrest a frequency decline associated with real disturbances. This could cause the disturbance to cascade and result in the system actually collapsing because the appropriate action (shed enough load) was not taken at the right time.
The second scheme for shedding load is based on the rate of change (first derivative) of the frequency decline (combined often with predefined frequencies). This scheme solves some of the concerns with the first scheme above by providing a means for a faster response to disturbances and a better method for differentiating disturbances from “normal” system oscillations. The rate of change of the frequency (df/dt) is used at some or all of the predefined frequencies.
Unfortunately, the last blackouts, including the 2003 North East Blackout, have shown that the above existing load shedding schemes are not sufficient to arrest frequency declines and can not save power systems from large disturbances. Accordingly, there is a need for a load shedding scheme that can sufficiently arrest frequency declines that result from large disturbances.
BRIEF SUMMARY OF THE INVENTIONThese and other shortcomings of the prior art are addressed by the present invention, which provides an emergency frequency load shedding sheme that preempts a frequency decline by shedding load based on the severity of a disturbance.
According to one aspect of the present invention, a load shedding system includes a signal generator adapted to generate a signal representative of a local system; a modifying circuit adapted to adjust set frequencies; and a processing circuit adapted to process data received from the signal generator and modifying circuit and set load shedding priorities for the local system based on the processed data.
According to one aspect of the present invention, a method of pre-empting a frequency decline includes the steps of continuously monitoring voltage or current of a local system over a set time interval; estimating a rate of change of frequency with time from voltage and current measurements taken during the time interval; and using the rate of change of frequency with time to determine a frequency load shedding point.
According to one aspect of the present invention, a method of pre-empting a frequency decline includes the steps of continuously monitoring voltage and current of a feeder; estimating a rate of change of frequency with time from voltage and current measurements taken during a set time interval; estimating a rate of change of power with frequency; using the rate of change of frequency to determine a frequency load shedding point; and using the rate of change of power with frequency to set load shedding priorities.
The subject matter that is regarded as the invention may be best understood by reference to the following description taken in conjunction with the accompanying drawing figures in which:
Referring to the drawings, an exemplary emergency frequency load shedding scheme or system according to the present invention is illustrated in
Referring to
As shown in
As shown, if the rate of frequency, df/dt is greater than or equal to −k, then KLS is set to zero and, hence, the load shedding will take place at the predetermined scheduled frequencies without any correction applied to them. However, if df/dt is smaller than −k (i.e., more negative), then KLS, will be non zero and the load shedding will take place at an earlier value of frequency than the predetermined scheduled frequency.
Referring to
As shown in
In use,
Monitoring is done on a continuous basis; hence, the change in frequencies forms two measurements separated by a sampling interval; thus, yielding an estimate of the rate of change of frequency with time. This is also known as the first derivative of frequency with time (df/dt). Similarly, the rate of change of P with respect to frequency, or the first derivative of power with frequency (dP/df) may be derived from consecutive P and f measurements.
The value of df/dt provides an indication of the severity of the disturbance. The more negative in magnitude df/dt is, the more severe the disturbances. A positive df/dt indicates that the frequency decay is recovering. In the case of dP/df, a zero (0) value implies that the load is independent of frequency. A less negative value implies less dependence of frequency. A positive dP/df would indicate an increase of the load with the frequency; however, it is unlikely that this would occur.
From the df/dt values, the system 10 determines a new frequency load shedding point. This is based on the next predetermined (set point) load shedding value. The current df/dt alters the value at which the next load shedding event will take place, with more severe disturbances represented when df/dt is more negative than KLS and resulting in shedding load at higher frequencies. When df/dt is less negative than KLS, then load shedding will take place at the predetermined load shedding frequency.
Similarly, dP/df is used to set the priority of the shedding of the different feeders based on the frequency dependency of the load they carry. This is determined by how negative the rate of change of power with frequency (dP/df) is for each feeder, with smaller values of dP/df having higher priority. This priority is then communicated as trip signals to different actual relays, and then to associated breakers.
The foregoing has described an emergency frequency load shedding scheme. While specific embodiments of the present invention have been described, it will be apparent to those skilled in the art that various modifications thereto can be made without departing from the spirit and scope of the invention. Accordingly, the foregoing description of the preferred embodiment of the invention and the best mode for practicing the invention are provided for the purpose of illustration only and not for the purpose of limitation.
Claims
1. A method of pre-empting a frequency decline, comprising the steps of:
- (a) continuously monitoring voltage of a local system over a set time interval;
- (b) estimating a rate of change of frequency with time from voltage measurements taken during the time interval; and
- (c) using the rate of change of frequency with time to determine a frequency load shedding point.
2. The method according to claim 1, further including the step of deriving a frequency signal indicative of the local system.
3. The method according to claim 1, further including the step of determining a magnitude of power carried by the local system.
4. The method according to claim 1, further including the step of determining a change of power with frequency.
5. The method according to claim 1, further including the step of setting load shedding priorities for the local system.
6. A method of pre-empting a frequency decline, comprising the steps of:
- (a) continuously monitoring voltage and current of a feeder;
- (b) estimating a rate of change of frequency with time from voltage and current measurements taken during a set time interval;
- (c) estimating a rate of change of power with frequency;
- (d) using the rate of change of frequency to determine a frequency load shedding point; and
- (e) using the rate of change of power with frequency to set load shedding priorities.
7. The method according to claim 6, further including the step of deriving a frequency signal indicative of the local system.
8. The method according to claim 6, further including the step of determining a magnitude of power carried by the local system.
9. The method according to claim 6, further including the step of comparing the rate of change of frequency with time to a load shedding constant.
10. The method according to claim 9, wherein if the rate of change of frequency with time is more negative than the load shedding constant, load shedding occurs at higher frequencies.
11. The method according to claim 9, wherein if the rate of change of frequency with time is less negative than the load shedding constant, load shedding occurs at predetermined frequencies.
12. The method according to claim 6, further including the step of communicating load shedding priorities to relays and breakers.
13. The method according to claim 6, wherein the more negative the rate of change of power with frequency is the higher the load shedding priority is for a feeder.
Type: Application
Filed: Oct 26, 2011
Publication Date: Feb 16, 2012
Applicant: ELECTRIC POWER RESEARCH INSTITUTE, INC. (Charlotte, NC)
Inventor: Nicholas C. Abi-Samra (Carlsbad, CA)
Application Number: 13/282,032
International Classification: G06F 1/28 (20060101);