Method and System for Pouring Consecutive Separating Sections of Concrete Structures
A device and method for pouring consecutive concrete sections. The inventive device and method preferably include a barrier used to separate adjacent concrete slabs. This barrier is preferably erected in such a way that it allows a construction crew to continuously pour concrete in successive sections of a concrete structure, which prior to the current invention, could not be poured continuously. Previously, concrete sections were poured in an alternating fashion in order to create an expansion joint between each section of concrete which also acts to break the bond between each concrete section. However, the current inventive method and device allows the crew to pour adjacent concrete sections while still creating a joint between each concrete section. Each concrete section barrier preferably includes an upright surface and dowel sleeves. Prior to pouring concrete into each designated gap dowel bars are inserted into each dowel sleeve.
This non-provisional patent application is a continuation-in-part of U.S. application Ser. No. 14/016,412, filed on Sep. 3, 2013, which is a continuation-in-part of U.S. application Ser. No. 13/787,487. The original application was filed on Mar. 6, 2013. All applications list the same inventors.
STATEMENT REGARDING FEDERALLY SPONSORED RESEARCH OR DEVELOPMENTNot applicable
MICROFICHE APPENDIXNot Applicable
BACKGROUND OF THE INVENTION1. Field of the Invention
This invention relates to the field of roadway construction. More specifically, the present invention comprises a device and method for separating sections of concrete fir multiple structures.
2. Description of the Related Art
Governing bodies, such as the department of transportation for states and other territories, have rules and regulations which must be followed when erecting structures associated with walking paths and roadways. These restrictions pertain to roads, sidewalks, retaining, gravity and barrier walls, junction and/or moment slabs and other structures that are constructed using concrete. Although these restrictions are enforced with public safety and structural integrity in mind, the regulations create inefficiencies during construction.
One of the main restrictions mandated by most governing bodies for construction of retaining walls, gravity walls, barrier walls, and junction slabs is that each structure must have concrete poured in separate sections of a specified length. The separate sections of concrete create joints along the length of the structure. These joints allow for expansion, contraction, bond breaks, and movement of each individual section of concrete, thereby decreasing the likelihood of cracking and other complications. In addition, sonic structures require an interlocking joint comprising a mortise and tenon wherein each concrete section is not bonded together.
In the case of junction and moment slabs, the expansion joint (also known as the “bond break” joint) is typically created using a piece of lumber with a relatively small thickness to create a temporary form. The current process used to create an array of junction and moment slabs requires the construction team to measure out each section of concrete to be poured. However, due to the requirement of an expansion joint, whereby each section must not be bonded together, the sections are poured in an alternating fashion. Typically, a first section is poured, then a space which is equal to the length of a section is left vacant. Next, concrete is poured adjacent to the open space for a section, and so on down the line of junction/moment slabs. Once the first sections of concrete slabs have dried and cured, the vacant sections can be filled with concrete (this is typically done the day after the first concrete sections are poured). Thus, the adjacent concrete sections are prevented from bonding together, and the required expansion joint is formed between each section of concrete. In addition, dowel bars are inserted at regular intervals along the length of each piece of lumber. The hole for each dowel bar must be measured and drilled prior to pouring concrete.
Therefore, what is needed is a device and method which allows a construction team to continuously pour isolated sections of concrete during the fabrication of an array of junction or moment slabs. The present invention achieves this objective, as well as others that are explained in the following description.
BRIEF DESCRIPTION OF THE INVENTIONThe present invention comprises a device and method for pouring consecutive concrete sections which are disjoint. The present invention includes the required bond breaks, which prevent the adjacent concrete slabs from bonding to each other. This joint is referred to throughout the following disclosure as an expansion joint or bond breaking joint, as it serves a dual purpose. The inventive device and method preferably include a barrier used to separate adjacent concrete slabs. This barrier is preferably erected in such a way that it allows a construction crew to continuously pour concrete in successive sections of a concrete structure, which prior to the current invention, could not be poured continuously. Previously, concrete sections were poured in an alternating fashion in order to create an expansion joint between each section of concrete. However, the current inventive method and device allows the crew to pour adjacent concrete sections while still creating an expansion joint between each concrete section.
Each concrete section barrier includes an upright surface and dowel sleeves. Prior to pouring concrete into each designated gap, which have been measured and sectioned off, dowel bars are inserted into each dowel sleeve. Then, each gap is filled with concrete in a manner that allows a crew to pour adjacent gaps. This is an improvement on the previous method, wherein alternating gaps are filled on a first day, and then the remaining gaps are filled on a second day.
The present invention provides a method and device for separating sections of concrete during construction of structures on or near a roadway.
In one embodiment of the present invention, concrete section barrier 10 is fabricated using a molded plastic. A molded plastic material is capable of expansion and contraction. In addition, corrosion of molded plastic is less likely than with a metallic material such as steel or aluminum. However, it should be noted that molded plastic may be the preferred embodiment, there may be other suitable materials used for concrete section barrier 10. Some examples of suitable materials for barrier 10 are a composite, ceramic, coated steels, or another plastic material.
The reader will note that
Prior to pouring concrete into first gap 20 and second gap 22, dowels 24 are preferably inserted into dowel sleeves 14. This is illustrated in
Those familiar with the art will realize that the configuration shown in
Those familiar with the art will realize that in addition to the previously mentioned applications, dowel sleeves 14 and dowels 24 act to maintain the alignment of junction/moment slabs 32. While translation along axis of the dowels/dowel sleeves is allowed, the dowels 24 and dowel sleeves 14 inhibit lateral (radially in reference to the dowels/sleeves) and vertical translation. Thus, each concrete slab 32 is capable of expanding and contracting in the axial direction.
The preceding description contains significant detail regarding the hovel aspects of the present invention. It should not be construed, however, as limiting the scope of the invention but rather as providing illustrations of the preferred embodiments of the invention. Thus, the scope of the invention should be fixed by the following claims, rather than by the examples given.
Claims
1. A method for pouring consecutive concrete slabs using concrete comprising:
- a. providing a concrete section barrier having: i. a surface; and ii. at least one dowel sleeve;
- b. providing at least two form walls;
- c. fixing said at least two form walls in a position to form a channel;
- d inserting said concrete section barrier such that said concrete section barrier is capable of separating said channel into at least two gaps;
- e. maintaining said concrete section barrier in an upright position;
- f. providing at least one dowel;
- g. inserting said at least one dowel into said at least one dowel sleeve of said concrete section barrier; and
- h. pouring said concrete in said at least two gaps consecutively.
2. The method of claim 1, wherein said at least one dowel sleeve is further comprised of:
- a. an extruded cylinder; and
- b. a dowel sleeve opening.
3. The method of claim 1, wherein said concrete barrier section is comprised of molded plastic.
4. The method of claim 1, wherein said concrete barrier section is comprised of ceramic.
5. The method of claim 1, wherein said concrete barrier section is comprised of a composite.
6. The method of claim 1, wherein said concrete barrier section is comprised of coated steel or any other rigid material.
7. The method of claim 1, wherein said form walls are fixed parallel to one another set apart a distance equal to the length of said concrete section barrier.
8. The method of claim 1, further comprising allowing said concrete to adhere to said at least one dowel in a first gap and said at least one dowel sleeve in a second gap, such that said concrete in said first gap and said concrete in said second gap are not fixed together.
9. The method of claim 8, wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete expanding.
10. The method of claim 9, wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete contracting.
11. A method for pouring consecutive concrete slabs using concrete comprising:
- a. providing at least one concrete section barrier having: i. a surface; and ii. a plurality of dowel sleeves;
- b. providing at least two form walls;
- c. fixing said at least two form walls in an upright position to form a channel;
- d. inserting said at least one concrete section barrier such that said at least one concrete section barrier is capable of separating said channel into a plurality of gaps;
- e. maintaining said at least one concrete section barrier in an upright position by providing a chamfer attached to said at least one concrete section barrier and said form wall;
- f. providing a plurality of dowels;
- g. inserting said plurality of dowels into said plurality of dowel sleeves of said at least one concrete section barrier; and
- h. pouring said concrete in said at least two gaps prior to allowing said concrete to set.
12. The method of claim 11, wherein said plurality of dowel sleeves are further comprised of:
- a. a plurality of extruded cylinders; and
- b. a plurality of dowel sleeve openings.
13. The method of claim 11 wherein said at east one concrete barrier section is comprised of a rigid material.
14. The method of claim 11, further comprising covering said at least one concrete barrier section with a portion of expansion paper such that said concrete bonds to said portion of expansion paper when said concrete sets.
15. The method of claim 11, wherein said at least one concrete barrier section further comprises a keyway having a mortise and a tenon.
16. The method of claim 15, further comprising allowing said concrete to adhere to said keyway at said mortise and said tenon, thereby creating a mortise and tenon joint after said concrete sets.
17. The method of claim 10, further comprising allowing said concrete to adhere to said at least one dowel in a first gap and said at least one dowel sleeve in a second gap, such that said concrete in said first gap and said concrete in said second gap are not fixed together.
18. The method of claim 16, wherein said at least one dowel is capable of translating within said at least one dowel sleeve upon said concrete movement.
19. A method for pouring consecutive concrete slabs, using concrete, comprising:
- a. providing a plurality of concrete section barriers having: i. a surface; and ii. a plurality of dowel sleeves;
- b. providing at least two form walls;
- c. fixing said at least two form walls in a position to form a channel;
- d. inserting said plurality of concrete section barriers such that said plurality of concrete section barriers are capable of separating said channel into a plurality of consecutive gaps;
- e. maintaining said plurality of concrete section barriers in an upright position by providing a plurality of chamfers attached to said plurality of concrete section barriers and said at least two form walls;
- f. providing a plurality of dowels;
- g. inserting said plurality of dowels into said plurality of dowel sleeves of said plurality of concrete section barriers; and
- h. pouring said concrete in said plurality of consecutive gaps prior to allowing said concrete to set.
20. The method of claim 19, wherein said step of pouring said concrete further comprises pouring said concrete simultaneously into said plurality of consecutive gaps.
Type: Application
Filed: Aug 28, 2014
Publication Date: Mar 3, 2016
Inventors: Christopher J. Collines (Miromar Lakes, FL), Dean Giardini (Miromar Lakes, FL)
Application Number: 14/471,826