BEAM-COLUMN CONNECTION STRUCTURE AND METHOD FOR FORMING THE SAME
The present invention relates to a beam-column connection structure and a method for connecting a beam and a column. The beam-column connection structure comprises a precast column, a precast steel reinforced concrete beam and a plurality of fasteners. The precast column has a plurality of tension bars horizontally arranged inside the precast column and has an engagement assembly. One side of the engagement assembly is connected with one end of each of the plurality of tension bars, and the other side of the engagement assembly has a plurality of second holes therein. One end of the precast steel reinforced concrete beam has a plurality of first holes corresponding to the plurality of second holes. The plurality of fasteners are inserted into the plurality of first holes and the plurality of second holes such that the precast steel reinforced concrete beam is fixed to the precast column.
Latest Patents:
The instant disclosure relates to a beam-column connection structure and a method for forming the same, in particular to a beam-column connection structure of a precast column and a precast steel reinforced concrete beam and a method for forming the same.
BACKGROUNDConventional methods of constructing reinforced concrete (RC) buildings require construction floor-by-floor from the bottom to the top, which is time consuming. One of such methods involves: pouring concrete into molds having rebar therein at the construction site for construction at the ground floor and waiting until the concrete reaches a predetermined compression strength, then removing the molds and starting the constructing work for the next floor (i.e., the 2nd floor), and so on. Further, such conventional method involves many processes, such as tying the reinforced steel, molding, grouting and so on, which requires a lot of workers on the construction site. Thus, the quality of the construction is dependent on the skill and experience of the workers and the weather, and is difficult to control.
To resolve the above problems, a precast construction method is provided. For example, precast columns and precast beams are first fabricated in the factory, and then transported to the construction site to be hoisted to particular locations. At the construction site, the precast columns and beams are assembled by the steps of: binding the rebar extending from the outer surfaces of the precast columns and the precast beams, assembling the molds around the joints of the precast columns and beams, and pouring concrete into the molds to complete the beam-column connection structure. However, the accuracy of such conventional beam-column connection structure highly depends on the skill and experience of the workers on site. Thus, it is still hard to control construction quality, and it is desirable to reduce the time required further and improve the strength of such beam-column connection. Using steel reinforced concrete (SRC) as load-bearing beams and columns may expedite the construction process. However, if SRC is comprehensively used in the load-bearing beams and columns, it will require a great amount of steel, resulting in high construction cost. Thus, a combination of precast columns and SRC in a construction is one of the preferred designs.
Given the above, it is desired to provide a beam-column connection structure with stronger structural strength and to provide a construction method that can rapidly assemble a precast column and a precast steel reinforced concrete beam.
SUMMARY OF THE INVENTIONAccording to one exemplary embodiment of the instant disclosure, a beam-column connection structure comprises a precast column, a precast steel reinforced concrete beam and a plurality of fasteners. The precast column comprises a plurality of tension bars horizontally embedded in the precast column and an engagement assembly, wherein one side of the engagement assembly is connected with a first end of the plurality of tension bars, and the other side of the engagement assembly has a plurality of second through holes. The precast steel reinforced concrete beam has a plurality of first through holes at an end of the precast steel reinforced concrete beam, wherein the plurality of first through holes corresponds to the plurality of second through holes. The plurality of fasteners are penetrated through the plurality of first and second through holes so that the precast steel reinforced concrete beam is fixed to the precast column.
According to another exemplary embodiment of the instant disclosure, a method for beam-column connection comprises: providing a precast column comprising a plurality of tension bars horizontally embedded in the precast column; providing an engagement assembly; connecting one side of the engagement assembly with a first end of the plurality of tension bars, wherein the other side of the engagement assembly has a plurality of second through holes; providing a precast steel reinforced concrete beam, an end of the precast steel reinforced concrete beam having a plurality of first through holes corresponding to the plurality of second through holes; and penetrating a plurality of fasteners through the plurality of first and second through holes so that the precast steel reinforced concrete beam is fixed to the precast column.
According to another exemplary embodiment of the instant disclosure, a method for beam-column connection comprises: providing a precast column comprising a plurality of first and second tension bars horizontally embedded in the precast column, wherein the plurality of second tension bars substantially perpendicularly intersect with the plurality of first tension bars; providing a first engagement assembly, wherein one side of the first engagement assembly connecting with a first end of the plurality of first tension bars, and the other side of the first engagement assembly having a plurality of second through holes; providing a second engagement assembly, wherein one side of the second engagement assembly connects with the first end of the plurality of second tension bars, and the other side of the second engagement assembly having a plurality of third through holes; providing a first and a second precast steel reinforced concrete beam, wherein an end of each the first and second precast steel reinforced concrete beams has a plurality of first through holes corresponding to the plurality of second through holes and the plurality of third through holes; and penetrating a plurality of fasteners through the plurality of first through holes and the plurality of second through holes and through the plurality of first through holes and the plurality of third through holes so that the first and second precast steel reinforced concrete beams are fixed to two adjacent sides of the precast column.
In order to further understand the instant disclosure, the following embodiments are provided along with illustrations to facilitate appreciation of the instant disclosure; however, the appended drawings are merely provided for reference and illustration and are not intended to be used for limiting the scope of the instant disclosure.
The invention will be described according to the appended drawings, in which:
In order to facilitate understanding of the technical features, technical contents, technical advantages and technical effects of the subject invention, a detailed description with accompanying drawings is provided below for explanation only. The drawings only serve an auxiliary purpose for understanding of the technical contents; the scope of the subject invention should not be interpreted merely based on the scale or the relative positions between the elements illustrated in the drawings.
The terminology used in the description of the present disclosure herein is for the purpose of describing particular embodiments only, and is not intended to be construed as a limitation of the invention. As used in the description of the invention and the appended claims, the singular articles “a” and “an” are intended to include the plural forms as well, unless the context clearly indicates otherwise. It will also be understood that the term “and/or” as used herein refers to and encompasses any and all possible combinations of one or more of the associated listed items. It will be further understood that the terms “includes,” “including,” “comprises,” and/or “comprising,” when used in this specification, specify the presence of stated features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and/or groups thereof.
In addition, the main rebar assembly 11 comprises a plurality of main rebar 111, 112, 113 inserted inside and fixedly coupled to the auxiliary spiral stirrups 122 and/or the main spiral stirrup 121 binding with thin metal wires or through welding. In the embodiment shown in
As illustrated in
As shown in
The outer surface of the engagement assembly 4 is provided with a protrusion 41 substantially perpendicularly extending from the outer surface of the engagement assembly 4. The protrusion 41 has a plurality of second through holes 411 for connecting one end of the precast steel reinforced concrete beam 2. In particular, the number and the distribution of the plurality of second through holes 411 of the protrusion 41 correspond to those of the plurality of first through holes 214 of the precast steel reinforced concrete beam 2 (see
Please refer to
As illustrated in
In a preferred embodiment, the structural body of the precast column 1 and the precast steel reinforced concrete beam 2 are manufactured in the precast factory according to the construction blueprints. After the concrete of the precast column 1 and the precast steel reinforced concrete beam 2 reaches a predetermined rigidity, the precast column 1 and the precast steel reinforced concrete beam 2 are transported to the construction site for assembly.
Please refer to
In step S2, at least one precast steel reinforced concrete beam 2 is provided with a plurality of first through holes 214 at one end of the precast steel reinforced concrete beam 2. A crane (not shown in figures) hoists the precast steel reinforced concrete beam 2 to a position adjacent to the precast column 1 for connecting the precast steel reinforced concrete beam 2 to a predetermined position of the precast column 1. In an alternative embodiment, a plurality of precast steel reinforced concrete beams 2 can be connected to different sides of the precast column 1 simultaneously or sequentially.
In step S3, the position of the precast steel reinforced concrete beam 2 is adjusted. After the plurality of through holes 214 of the precast steel reinforced concrete beam 2 are aligned with the plurality of second through holes 411 of the engagement assembly 4, a plurality of fasteners 3 are penetrated through the plurality of first through holes 214 of the precast steel reinforced concrete beam 2 and the plurality of second through holes 411 of the engagement assembly 4 so that the precast steel reinforced concrete beam 2 is fixed to the precast column 1. In addition, the fastener 3 comprises a bolt and corresponding nut. The threaded end of the bolts penetrates through the plurality of first through holes 214 of the precast steel reinforced concrete beam 2, and then penetrates through the plurality of second through holes 411 of the engagement assembly 4, so the threaded end is exposed outside the surface of the engagement assembly 4. In addition, the position of the spacer 42 is so designed that when the plurality of first through holes 214 of the precast steel reinforced concrete beam 2 are aligned with the plurality of second through holes 411 of the engagement assembly 4, the upper surface of the spacer 42 is attached to the lower surface of the bottom flange 212 of the steel beam 21 (see
In step S4, the precast steel reinforced concrete beam 2 is welded to the engagement assembly 4 to enhance the connection strength. The top flange 211 and the bottom flange 212 of the steel beam 21 of the precast steel reinforced concrete beam 2 are welded to the outer surface of the engagement assembly 4, and the web plate 213 of the steel beam 21 is welded to the protrusion 41 of the engagement assembly 4. After the precast steel reinforced concrete beam 2 is positioned, the spacer 43 is attached to the lower surface of the bottom flange 212 of the steel beam 21. In addition, the lower surface of the top flange 211 of the steel beam 21 is provided with a spacer 48 for limiting the flow range of the solder. Because the height H3 of the web plate 213 is greater than the height H2 of the protrusion 41, the web plate 213 can be welded to the outer periphery of the protrusion 41, such as along the top edge, outer edge and bottom edge of the protrusion 41 (see
In step S5, in the bare steel beam section 22 of the precast steel reinforced concrete beam 2, wrapping a plurality of first rebar 24 around the steel beam 21. In addition, at least one surface of two lateral surfaces of the bare steel beam section 22 of the precast steel reinforced concrete beam 2 is further provided with at least one third rebar 241 substantially perpendicularly intersecting with the first rebar 24 (see
In step S6, the bare steel beam section 22 of the precast steel reinforced concrete beam 2 is enclosed by concrete forms 29 and into which concrete is then poured. The concrete form 29 comprises an outer concrete form 291, an inner concrete form 292 and a bottom concrete form 293 disposed on the outer surface, inner surface and bottom surface of the bare steel beam section 22 of the precast steel reinforced concrete beam 2, respectively. In particular, there is a height difference between the top edge 2911 of the outer concrete form 291 and the top edge 2921 of the inner concrete form 292. In an embodiment of the instant disclosure, the top edge 2911 of the outer concrete form 291 is higher than the top edge 2921 of the inner concrete form 292. In an embodiment shown in
In step S7, a plate member 5 (i.e., the corrugated steel sheets serving as the bottom of the floorslab) is horizontally disposed and surrounded by the precast column 1 and the at least one precast steel reinforced concrete beam 2, and a plurality of second rebar 6 perpendicularly intersect with each other on the plate member 5. In an embodiment shown in
In step S8, concrete is poured onto the area not previously enveloped by concrete. When the precast steel reinforced concrete beam 2 is a semi-precast steel reinforced concrete beam (as shown in
The beam-column connection structure and the method of forming the same as provided in the above embodiments effectively speed up the connections between the precast columns and the precast beams so that the main structure of the building can be rapidly accomplished. Moreover, the tension bars embedded in the precast column not only enhance the structural strength of the precast beams coupled to both ends of each tension bar, but also effectively transmit the shear force resulting from earthquakes so as to prevent the beam-column connection structure from being damaged due to the unfavorable stress concentration phenomenon.
Specific components of an insertion system and related methods for insertion have been described. It should be apparent, however, to those skilled in the art that many more modifications besides those already described are possible without departing from the inventive concepts herein. The inventive subject matter, therefore, is not to be restricted except in the spirit of the present disclosure. Moreover, in interpreting the present disclosure, all terms should be interpreted in the broadest possible manner consistent with the context. In particular, the terms “comprises” and “comprising” should be interpreted as referring to elements, components, or steps in a non-exclusive manner, indicating that the referenced elements, components, or steps may be present, or utilized, or combined with other elements, components, or steps that are not expressly referenced.
Claims
1. A beam-column connection structure, comprising:
- a precast column comprising a plurality of tension bars horizontally embedded in the precast column and comprising an engagement assembly, wherein one side of the engagement assembly is connected with a first end of the plurality of tension bars, and the other side of the engagement assembly has a plurality of second through holes;
- a precast steel reinforced concrete beam having a plurality of first through holes at an end of the precast steel reinforced concrete beam, wherein the plurality of first through holes corresponds to the plurality of second through holes; and
- a plurality of fasteners penetrating through the plurality of first and second through holes so that the precast steel reinforced concrete beam is fixed to the precast column.
2. The beam-column connection structure according to claim 1, wherein the precast steel reinforced concrete beam comprises a steel beam therein, and a section of the steel beam is partially or completely enveloped by reinforced concrete and the end of the precast steel reinforced concrete beam is a bare steel beam section with a predetermined distance, the section being next to the bare steel beam section.
3. The beam-column connection structure according to claim 2, where the steel beam is enveloped by reinforced concrete, on the left side, right side and bottom, but not on the top.
4. The beam-column connection structure according to claim 2, wherein the steel beam of the precast steel reinforced concrete beam comprises:
- a top flange;
- a bottom flange substantially parallel to the top flange; and
- a web plate substantially perpendicularly connected to the top flange and the bottom flange with two ends thereof.
5. The beam-column connection structure according to claim 4, wherein the plurality of first through holes are linearly disposed on the web plate of the steel beam along the edge of the end of the precast steel reinforced concrete beam, and a plurality of shear studs are provided on an upper surface of the top flange.
6. The beam-column connection structure according to claim 1, wherein a surface of the other side of the engagement assembly is provided with a protrusion substantially perpendicularly extending from the surface, the protrusion having the plurality of second through holes therein.
7. The beam-column connection structure according to claim 6, wherein the protrusion is elongated, the plurality of second through holes are substantially linearly arranged along the protrusion, and the plurality of fasteners are high-tension bolts.
8. The beam-column connection structure according to claim 7, wherein the engagement member further comprises:
- a first engagement member, one side of the first engagement member connecting with the first end of a part of the plurality of tension bars at a first position, the other side of the first engagement member connecting with the engagement assembly; and
- a second engagement member, one side of the second engagement member connecting with the first end of the rest part of the plurality of tension bars at a second position, the other side of the second engagement member connecting with the engagement assembly,
- wherein the first position is higher than the second position.
9. The beam-column connection structure according to claim 1, wherein the precast column comprises a main rebar assembly and a stirrup assembly fixedly coupled to the main rebar assembly, wherein the stirrup assembly comprises a main spiral stirrup and a plurality of auxiliary spiral stirrups, wherein the plurality of auxiliary spiral stirrups partially overlap the main spiral stirrup, and a major part of the auxiliary spiral stirrups are disposed outside the main spiral stirrup.
10. The beam-column connection structure according to claim 9, wherein the main rebar assembly comprises:
- a set of inner main rebar, the main spiral stirrup surrounding and connecting to outer sides of the set of inner main rebar;
- a set of middle main rebar disposed between the main spiral stirrup and the plurality of the auxiliary spiral stirrups; and
- a set of outer main rebar disposed outside of the main spiral stirrup and inside of the plurality of the auxiliary spiral stirrups.
11. A method for forming a beam-column connection, comprising:
- providing a precast column comprising a plurality of tension bars horizontally embedded in the precast column;
- providing an engagement assembly;
- connecting one side of the engagement assembly with a first end of the plurality of tension bars, wherein the other side of the engagement assembly has a plurality of second through holes;
- providing a precast steel reinforced concrete beam, an end of the precast steel reinforced concrete beam having a plurality of first through holes corresponding to the plurality of second through holes; and
- penetrating a plurality of fasteners through the plurality of first and second through holes so that the precast steel reinforced concrete beam is fixed to the precast column.
12. The method according to claim 11, further comprising providing a first engagement member and a second engagement member; connecting inner sides of the first and second engagement members to the first end of the plurality of tension bars at a first position and a second position respectively; and connecting the outer sides of the first and second engagement members to the engagement assembly, wherein the first position is higher than the second position.
13. The method according to claim 12, further comprising welding inner sides of the first and second engagement members to the first end of the plurality of tension bars at a first position and a second position respectively, and welding the outer sides of the first and second engagement members to the engagement assembly.
14. The method according to claim 13, further comprising welding a bare steel beam section of the precast steel reinforced concrete beam to the engagement assembly.
15. The method according to claim 14, wherein providing a precast steel reinforced concrete beam comprises providing a steel beam and enveloping a section of the steel beam with reinforced concrete wherein the steel beam comprises a top flange, a web plate and a bottom flange, wherein the top flange is substantially parallel to the bottom flange, and the web plate is substantially perpendicularly connected to the top flange and the bottom flange with two ends thereof.
16. The method according to claim 15, further comprising providing a plurality of shear studs on an upper surface of the top flange, welding the top flange and the bottom flange to a surface of the engagement assembly, and welding the web plate to a protrusion substantially perpendicularly extending from the surface of the engagement assembly.
17. A method for beam-column connection, comprising:
- providing a precast column comprising a plurality of first and second tension bars horizontally embedded in the precast column, wherein the plurality of second tension bars substantially perpendicularly intersect with the plurality of first tension bars, wherein providing the precast column comprises:
- providing a first engagement assembly so that one side of the first engagement assembly connects with a first end of the plurality of first tension bars, and the other side of the first engagement assembly has a plurality of second through holes;
- providing a second engagement assembly so that one side of the second engagement assembly connects with a first end of the plurality of second tension bars, and the other side of the second engagement assembly has a plurality of third through holes;
- providing a first and a second precast steel reinforced concrete beam, wherein an end of each the first and second precast steel reinforced concrete beams has a plurality of first through holes corresponding to the plurality of second through holes and the plurality of third through holes; and
- penetrating a plurality of fasteners through the plurality of first through holes and the plurality of second through holes and through the plurality of first through holes and the plurality of third through holes so that the first and second precast steel reinforced concrete beams are fixed to two adjacent sides of the precast column.
18. The method according to claim 17, wherein providing a first and a second precast steel reinforced concrete beam comprises providing a steel beam therein, and partially or completely enveloping a section of the steel beam with reinforced concrete so that the end at each the first and second precast steel reinforced concrete beams is a bare steel beam section with a predetermined length, the section being next to the bare steel beam section.
19. The method according to claim 18, further comprising surrounding the bare steel beam section with a plurality of first rebar, molding and grouting the left side, right side and bottom side of the bare steel beam section.
20. The method according to claim 19, further comprising horizontally disposing a plate member surrounded by the precast column and the first and second precast steel reinforced concrete beams.
21. The method according to claim 20, further comprising disposing a plurality of second rebar on the plate member, wherein the plurality of second rebar is in a staggered arrangement; and grouting concrete on the plate member and a part of an upper surface of the first and second precast steel reinforced concrete beams.
22. The beam-column connection structure according to claim 1, wherein the side of the engagement assembly, which is connected with the first end of the plurality of tension bars, is opposite to the other side of the engagement assembly, which has a plurality of second through holes.
23. The beam-column connection structure according to claim 1, further comprising another engagement assembly spaced apart from the engagement assembly and connected with a second end of the plurality of tension bars, wherein the second end of the plurality of tension bars is opposite to the first end of the plurality of tension bars.
Type: Application
Filed: Jul 19, 2018
Publication Date: Jul 25, 2019
Applicant:
Inventors: Samuel YIN (Taipei City), Jui-Chen WANG (Taipei City)
Application Number: 16/039,716