Granular Power Ramping
Examples relate to flexible datacenters or other power loads tolerant of intermittent operation and configured to use power received behind-the-meter. A system may include a plurality of computing systems that receive behind-the-meter (“BTM”) power from a BTM power source. The system may include a first controller configured to control a first set of computing systems and a second controller configured to control a second set of computing systems of the plurality of computing systems. The system may also include a third controller communicatively coupled to the first controller and the second controller. The third controller is configured to provide instructions to the first controller and the second controller based on BTM power availability at the plurality of computing systems.
This specification relates to a system using intermittent behind-the-meter power.
BACKGROUND“Electrical grid” or “grid,” as used herein, refers to a Wide Area Synchronous Grid (also known as an Interconnection), and is a regional scale or greater electric power grid that that operates at a synchronized frequency and is electrically tied together during normal system conditions. An electrical grid delivers electricity from generation stations to consumers. An electrical grid includes: (i) generation stations that produce electrical power at large scales for delivery through the grid, (ii) high voltage transmission lines that carry that power from the generation stations to demand centers, and (iii) distribution networks carry that power to individual customers.
A generation segment 102 includes one or more generation stations that produce utility-scale electricity (typically >50 MW), such as a nuclear plant 102a, a coal plant 102b, a wind power station (i.e., wind farm) 102c, and/or a photovoltaic power station (i.e., a solar farm) 102d. Generation stations are differentiated from building-mounted and other decentralized or local wind or solar power applications because they supply power at the utility level and scale (>50 MW), rather than to a local user or users. The primary purpose of generation stations is to produce power for distribution through the grid, and in exchange for payment for the supplied electricity. Each of the generation stations 102a-d includes power generation equipment 102e-h, respectively, typically capable of supply utility-scale power (>50 MW). For example, the power generation equipment 102g at wind power station 102c includes wind turbines, and the power generation equipment 102h at photovoltaic power station 102d includes photovoltaic panels.
Each of the generation stations 102a-d may further includes station electrical equipment 102i-1 respectively. Station electrical equipment 102i-1 are each illustrated in
Each generation station 102a-d may produce AC or DC electrical current which is then typically stepped up to a higher AC voltage before leaving the respective generation station. For example, wind turbines may typically produce AC electrical energy at 600V to 700V, which may then be stepped up to 34.5 kV before leaving the generation station 102d. In some cases, the voltage may be stepped up multiple times and to a different voltage before exiting the generation station 102c. As another example, photovoltaic arrays may produce DC voltage at 600V to 900V, which is then inverted to AC voltage and may be stepped up to 34.5 kV before leaving the generation station 102d. In some cases, the voltage may be stepped up multiple times and to a different voltage before exiting the generation station 102d.
Upon exiting the generation segment 102, electrical power generated at generation stations 102a-d passes through a respective Point of Interconnection (“POI”) 103 between a generation station (e.g., 102a-d) and the rest of the grid. A respective POI 103 represents the point of connection between a generation station's (e.g. 102a-d) equipment and a transmission system (e.g., transmission segment 104) associated with electrical grid. In some cases, at the POI 103, generated power from generation stations 102a-d may be stepped up at transformer systems 103e-h to high voltage scales suitable for long-distance transmission along transmission lines 104a. Typically, the generate electrical energy leaving the POI 103 will be at 115 kV AC or above, but in some cases it may be as low as, for example, 69 kV for shorter distance transmissions along transmission lines 104a. Each of transformer systems 103e-h may be a single transformer or may be multiple transformers operating in parallel or series and may be co-located or located in geographically distinct locations. Each of the transformer systems 103e-h may include substations and other links between the generation stations 102a-d and the transmission lines 104a.
A key aspect of the POI 103 is that this is where generation-side metering occurs. One or more utility-scale generation-side meters 103a-d (e.g., settlement meters) are located at settlement metering points at the respective POI 103 for each generation station 102a-d. The utility-scale generation-side meters 103a-d measure power supplied from generation stations 102a-d into the transmission segment 104 for eventual distribution throughout the grid.
For electricity consumption, the price consumers pay for power distributed through electric power grids is typically composed of, among other costs, Generation, Administration, and Transmission & Distribution (“T&D”) costs. T&D costs represent a significant portion of the overall price paid by consumers for electricity. These costs include capital costs (land, equipment, substations, wire, etc.), costs associated with electrical transmission losses, and operation and maintenance costs.
For utility-scale electricity supply, operators of generation stations (e.g., 102a-d) are paid a variable market price for the amount of power the operator generates and provides to the grid, which is typically determined via a power purchase agreement (PPA) between the generation station operator and a grid operator. The amount of power the generation station operator generates and provides to the grid is measured by utility-scale generation-side meters (e.g., 103a-d) at settlement metering points. As illustrated in
After passing through the utility-scale generation-side meters in the POI 103, the power originally generated at the generation stations 102a-d is transmitted onto and along the transmission lines 104a in the transmission segment 104. Typically, the electrical energy is transmitted as AC at 115 kV+ or above, though it may be as low as 69 kV for short transmission distances. In some cases, the transmission segment 104 may include further power conversions to aid in efficiency or stability. For example, transmission segment 104 may include high-voltage DC (“HVDC”) portions (along with conversion equipment) to aid in frequency synchronization across portions of the transmission segment 104. As another example, transmission segment 104 may include transformers to step AC voltage up and then back down to aid in long distance transmission (e.g., 230 kV, 500 kV, 765 kV, etc.).
Power generated at the generation stations 104a-d is ultimately destined for use by consumers connected to the grid. Once the energy has been transmitted along the transmission segment 104, the voltage will be stepped down by transformer systems 105a-c in the step down segment 105 so that it can move into the distribution segment 106.
In the distribution segment 106, distribution networks 106a-c take power that has been stepped down from the transmission lines 104a and distribute it to local customers, such as local sub-grids (illustrated at 106a), industrial customers, including large EV charging networks (illustrated at 106b), and/or residential and retail customers, including individual EV charging stations (illustrated at 106c). Customer meters 106d, 106f measure the power used by each of the grid-connected customers in distribution networks 106a-c. Customer meters 106d are typically load meters that are unidirectional and measure power use. Some of the local customers in the distribution networks 106a-d may have local wind or solar power systems 106e owned by the customer. As discussed above, these local customer power systems 106e are decentralized and supply power directly to the customer(s). Customers with decentralized wind or solar power systems 106e may have customer meters 106f that are bidirectional or net-metering meters that can track when the local customer power systems 106e produce power in excess of the customer's use, thereby allowing the utility to provide a credit to the customer's monthly electricity bill. Customer meters 106d, 106f differ from utility-scale generation-side meters (e.g., settlement meters) in at least the following characteristics: design (electro-mechanical or electronic vs current transformer), scale (typically less than 1600 amps vs. typically greater than 50 MW; typically less than 600V vs. typically greater than 14 kV), primary function (use vs. supply metering), economic purpose (credit against use vs payment for power), and location (in a distribution network at point of use vs. at a settlement metering point at a Point of Interconnection between a generation station and a transmission line).
To maintain stability of the grid, the grid operator strives to maintain a balance between the amount of power entering the grid from generation stations (e.g., 102a-d) and the amount of grid power used by loads (e.g., customers in the distribution segment 106). In order to maintain grid stability and manage congestion, grid operators may take steps to reduce the supply of power arriving from generation stations (e.g., 102a-d) when necessary (e.g., curtailment). Particularly, grid operators may decrease the market price paid for generated power to dis-incentivize generation stations (e.g., 102a-d) from generating and supplying power to the grid. In some cases, the market price may even go negative such that generation station operators must pay for power they allow into the grid. In addition, some situations may arise where grid operators explicitly direct a generation station (e.g., 102a-d) to reduce or stop the amount of power the station is supplying to the grid.
Power market fluctuations, power system conditions (e.g., power factor fluctuation or generation station startup and testing), and operational directives resulting in reduced or discontinued generation all can have disparate effects on renewal energy generators and can occur multiple times in a day and last for indeterminate periods of time. Curtailment, in particular, is particularly problematic.
According to the National Renewable Energy Laboratory's Technical Report TP-6A20-60983 (March 2014):
-
- [C]urtailment [is] a reduction in the output of a generator from what it could otherwise produce given available resources (e.g., wind or sunlight), typically on an involuntary basis. Curtailments can result when operators or utilities command wind and solar generators to reduce output to minimize transmission congestion or otherwise manage the system or achieve the optimal mix of resources. Curtailment of wind and solar resources typically occurs because of transmission congestion or lack of transmission access, but it can also occur for reasons such as excess generation during low load periods that could cause baseload generators to reach minimum generation thresholds, because of voltage or interconnection issues, or to maintain frequency requirements, particularly for small, isolated grids. Curtailment is one among many tools to maintain system energy balance, which can also include grid capacity, hydropower and thermal generation, demand response, storage, and institutional changes. Deciding which method to use is primarily a matter of economics and operational practice.
- “Curtailment” today does not necessarily mean what it did in the early 2000s. Two separate changes in the electric sector have shaped curtailment practices since that time: the utility-scale deployment of wind power, which has no fuel cost, and the evolution of wholesale power markets. These simultaneous changes have led to new operational challenges but have also expanded the array of market-based tools for addressing them.
- Practices vary significantly by region and market design. In places with centrally-organized wholesale power markets and experience with wind power, manual wind energy curtailment processes are increasingly being replaced by transparent offer-based market mechanisms that base dispatch on economics. Market protocols that dispatch generation based on economics can also result in renewable energy plants generating less than what they could potentially produce with available wind or sunlight. This is often referred to by grid operators by other terms, such as “downward dispatch.” In places served primarily by vertically integrated utilities, power purchase agreements (PPAs) between the utility and the wind developer increasingly contain financial provisions for curtailment contingencies.
- . . .
- Some reductions in output are determined by how a wind operator values dispatch versus non-dispatch. Other curtailments of wind are determined by the grid operator in response to potential reliability events. Still other curtailments result from overdevelopment of wind power in transmission-constrained areas.
- Dispatch below maximum output (curtailment) can be more of an issue for wind and solar generators than it is for fossil generation units because of differences in their cost structures. The economics of wind and solar generation depend on the ability to generate electricity whenever there is sufficient sunlight or wind to power their facilities.
- Because wind and solar generators have substantial capital costs but no fuel costs (i.e., minimal variable costs), maximizing output improves their ability to recover capital costs. In contrast, fossil generators have higher variable costs, such as fuel costs. Avoiding these costs can, depending on the economics of a specific generator, to some degree reduce the financial impact of curtailment, especially if the generator's capital costs are included in a utility's rate base.
Curtailment may result in available energy being wasted because solar and wind operators have zero variable cost (which may not be true to the same extent for fossil generation units which can simply reduce the amount of fuel that is being used). With wind generation, in particular, it may also take some time for a wind farm to become fully operational following curtailment. As such, until the time that the wind farm is fully operational, the wind farm may not be operating with optimum efficiency and/or may not be able to provide power to the grid.
SUMMARYIn an example, a system includes a plurality of computing systems. The plurality of computing systems receives behind-the-meter (“BTM”) power from a BTM power source. The system also includes a first controller configured to control a first set of computing systems of the plurality of computing systems and a second controller configured to control a second set of computing systems of the plurality of computing systems. The system may also include a third controller communicatively coupled to the first controller and the second controller. The third controller is configured to provide instructions to the first controller and the second controller based on BTM power availability at the plurality of computing systems.
In another example, a method involves receiving behind-the-meter (“BTM”) power at a plurality of computing systems. The plurality of computing systems receives BTM power from a BTM power source. The method also involves controlling, by a first controller, a first set of computing systems of the plurality of computing systems. The first controller controls the first set of computing systems based on instructions from a third controller. The method also involves controlling, by a second controller, a second set of computing systems of the plurality of computing systems. The second controller controls the second set of computing systems based on instructions from the third controller. The third controller is configured to provide instructions to the first controller and the second controller based on BTM power availability at the plurality of computing systems.
In yet another example, a method involves determining, by a secondary controller, behind-the-meter (“BTM”) power availability at a plurality of computing systems. The plurality of computing systems receives BTM power from a BTM power source. The method also involves, based on determining the BTM power availability at the plurality of computing systems, providing, by the secondary controller, instructions to: (i) a first primary controller configured to control a first set of computing systems of the plurality of computing systems and (ii) a second primary controller configured to control a second set of computing systems of the plurality of computing systems.
In a further example, non-transitory computer-readable medium is described that is configured to store instructions, that when executed by a computing system, causes the computing system to perform functions consistent with the method steps described above.
Other aspects of the present invention will be apparent from the following description and claims.
Disclosed examples will now be described more fully hereinafter with reference to the accompanying drawings, in which some, but not all of the disclosed examples are shown. Different examples may be described and should not be construed as limited to the examples set forth herein.
As discussed above, the market price paid to generation stations for supplying power to the grid often fluctuates due to various factors, including the need to maintain grid stability and based on current demand and usage by connected loads in distribution networks. Due to these factors, situations can arise where generation stations are offered substantially lower prices to deter an over-supply of power to the grid. Although these situations typically exist temporarily, generation stations are sometimes forced to either sell power to the grid at the much lower prices or adjust operations to decrease the amount of power generated. Furthermore, some situations may even require generation stations to incur costs in order to offload power to the grid or to shut down generation temporarily.
The volatility in the market price offered for power supplied to the grid can be especially problematic for some types of generation stations. In particular, wind farms and some other types of renewable resource power producers may lack the ability to quickly adjust operations in response to changes in the market price offered for supplying power to the grid. As a result, power generation and management at some generation stations can be inefficient, which can frequently result in power being sold to the grid at low or negative prices. In some situations, a generation station may even opt to halt power generation temporarily to avoid such unfavorable pricing. As such, the time required to halt and to restart the power generation at a generation station can reduce the generation station's ability to take advantage of rising market prices for power supplied to the grid.
Example embodiments provided herein aim to assist generation stations in managing power generation operations and avoid unfavorable power pricing situations like those described above. In particular, example embodiments may involve providing a load that is positioned behind-the-meter (“BTM”) and enabling the load to utilize power received behind-the-meter at a generation station in a timely manner.
For purposes herein, a generation station is considered to be configured for the primary purpose of generating utility-scale power for supply to the electrical grid (e.g., a Wide Area Synchronous Grid or a North American Interconnect).
In one embodiment, equipment located behind-the-meter (“BTM equipment”) is equipment that is electrically connected to a generation station's power generation equipment behind (i.e., prior to) the generation station's POI with an electrical grid.
In one embodiment, behind-the-meter power (“BTM power”) is electrical power produced by a generation station's power generation equipment and utilized behind (i.e., prior to) the generation station's POI with an electrical grid.
In another embodiment, equipment may be considered behind-the-meter if it is electrically connected to a generation station that is subject to metering by a utility-scale generation-side meter (e.g., settlement meter), and the BTM equipment receives power from the generation station, but the power received by the BTM equipment from the generation station has not passed through the utility-scale generation-side meter. In one embodiment, the utility-scale generation-side meter for the generation station is located at the generation station's POI. In another embodiment, the utility-scale generation-side meter for the generation station is at a location other than the POI for the generation station—for example, a substation between the generation station and the generation station's POI.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station that is subject to metering by a utility-scale generation-side meter (e.g., settlement meter), and the BTM power is utilized before being metered at the utility-scale generation-side meter. In one embodiment, the utility-scale generation-side meter for the generation station is located at the generation station's POI. In another embodiment, the utility-scale generation-side meter for the generation station is at a location other than the POI for the generation station—for example, a substation between the generation station and the generation station's POI.
In another embodiment, equipment may be considered behind-the-meter if it is electrically connected to a generation station that supplies power to a grid, and the BTM equipment receives power from the generation station that is not subject to T&D charges, but power received from the grid that is supplied by the generation station is subject to T&D charges.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station that supplies power to a grid, and the BTM power is not subject to T&D charges before being used by electrical equipment, but power received from the grid that is supplied by the generation station is subject to T&D charges.
In another embodiment, equipment may be considered behind-the-meter if the BTM equipment receives power generated from the generation station and that received power is not routed through the electrical grid before being delivered to the BTM equipment.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station, and BTM equipment receives that generated power, and that generated power received by the BTM equipment is not routed through the electrical grid before being delivered to the BTM equipment.
For purposes herein, BTM equipment may also be referred to as a behind-the-meter load (“BTM load”) when the BTM equipment is actively consuming BTM power.
Beneficially, where BTM power is not subject to traditional T&D costs, a wind farm or other type of generation station can be connected to BTM loads which can allow the generation station to selectively avoid the adverse or less-than optimal cost structure occasionally associated with supplying power to the grid by shunting generated power to the BTM load.
An arrangement that positions and connects a BTM load to a generation station can offer several advantages. In such arrangements, the generation station may selectively choose whether to supply power to the grid or to the BTM load, or both. The operator of a BTM load may pay to utilize BTM power at a cost less than that charged through a consumer meter (e.g., 106d, 1060 located at a distribution network (e.g., 106a-c) receiving power from the grid. The operator of a BTM load may additionally or alternatively charge less than the market rate to consume excess power generated at the generation station during curtailment. As a result, the generation station may direct generated power based on the “best” price that the generation station can receive during a given time frame, and/or the lowest cost the generation station may incur from negative market pricing during curtailment. The “best” price may be the highest price that the generation station may receive for its generated power during a given duration, but can also differ within embodiments and may depend on various factors, such as a prior PPA. In one example, by having a behind-the-meter option available, a generation station may transition from supplying all generated power to the grid to supplying some or all generated power to one or more BTM loads when the market price paid for power by grid operators drops below a predefined threshold (e.g., the price that the operator of the BTM load is willing to pay the generation station for power). Thus, by having an alternative option for power consumption (i.e., one or more BTM loads), the generation station can selectively utilize the different options to maximize the price received for generated power. In addition, the generation station may also utilize a BTM load to avoid or reduce the economic impact in situations when supplying power to the grid would result in the generation station incurring a net cost.
Providing BTM power to a load can also benefit the BTM load operator. A BTM load may be able to receive and utilize BTM power received from the generation station at a cost that is lower than the cost for power from the grid (e.g., at a customer meter 106d, 106f). This is primarily due to avoidance in T&D costs and the market effects of curtailment. As indicated above, the generation station may be willing to divert generated power to the BTM load rather than supplying the grid due to changing market conditions, or during maintenance periods, or for other non-market conditions. Furthermore, in some situations, the BTM load may even be able to obtain and utilize BTM power from a generation station at no cost or even at negative pricing since the generation station may be receiving tax credits (e.g., Production Tax Credits) for produced wind or is slow to self-curtail.
Another example of cost-effective use of BTM power is when the generation station 202 is selling power to the grid at a negative price that is offset by a production tax credit. In certain circumstances, the value of the production tax credit may exceed the price the generation station 202 would have to pay to the grid power to offload generation's station 202 generated power. Advantageously, one or more flexible datacenters 220 may take the generated power behind-the-meter, thereby allowing the generation station 202 to produce and obtain the production tax credit, while selling less power to the grid at the negative price.
Another example of cost-effective behind-the-meter power is when the generation station 202 is selling power to the grid at a negative price because the grid is oversupplied and/or the generation station 202 is instructed to stand down and stop producing altogether. A grid operator may select and direct certain generation stations to go offline and stop supplying power to the grid. Advantageously, one or more flexible datacenters may be used to take power behind-the-meter, thereby allowing the generation station 202 to stop supplying power to the grid, but still stay online and make productive use of the power generated.
Another example of beneficial behind-the-meter power use is when the generation station 202 is producing power that is, with reference to the grid, unstable, out of phase, or at the wrong frequency, or the grid is already unstable, out of phase, or at the wrong frequency. A grid operator may select certain generation stations to go either offline and stop producing power, or to take corrective action with respect to the grid power stability, phase, or frequency. Advantageously, one or more flexible datacenters 220 may be used to selectively consume power behind-the-meter, thereby allowing the generation station 202 to stop providing power to the grid and/or provide corrective feedback to the grid.
Another example of beneficial behind-the-meter power use is that cost-effective behind-the-meter power availability may occur when the generation station 202 is starting up or testing. Individual equipment in the power generation equipment 210 may be routinely offline for installation, maintenance, and/or service and the individual units must be tested prior to coming online as part of overall power generation equipment 210. During such testing or maintenance time, one or more flexible datacenters may be intermittently powered by the one or more units of the power generation equipment 210 that are offline from the overall power generation equipment 210.
Another example of beneficial behind-the-meter power use is that datacenter control systems at the flexible datacenters 220 may quickly ramp up and ramp down power consumption by computing systems in the flexible datacenters 220 based on power availability from the generation station 202. For instance, if the grid requires additional power and signals the demand via a higher local price for power, the generation station 202 can supply the grid with power nearly instantly by having active flexible datacenters 220 quickly ramp down and turn off computing systems (or switch to a stored energy source), thereby reducing an active BTM load.
Another example of beneficial behind-the-meter power use is in new photovoltaic generation stations 202. For example, it is common to design and build new photovoltaic generation stations with a surplus of power capacity to account for degradation in efficiency of the photovoltaic panels over the life of the generation stations. Excess power availability at the generation station can occur when there is excess local power generation and/or low grid demand. In high incident sunlight situations, a photovoltaic generation station 202 may generate more power than the intended capacity of generation station 202. In such situations, a photovoltaic generation station 202 may have to take steps to protect its equipment from damage, which may include taking one or more photovoltaic panels offline or shunting their voltage to dummy loads or the ground. Advantageously, one or more flexible datacenters (e.g., the flexible datacenters 220) may take power behind-the-meter at the Generations Station 202, thereby allowing the generation station 202 to operate the power generation equipment 210 within operating ranges while the flexible datacenters 220 receive BTM power without transmission or distribution costs.
Thus, for at least the reasons described herein, arrangements that involves providing a BTM load as an alternative option for a generation station to direct its generated power to can serve as a mutually beneficial relationship in which both the generation station and the BTM load can economically benefit. The above-noted examples of beneficial use of BTM power are merely exemplary and are not intended to limit the scope of what one of ordinary skill in the art would recognize as benefits to unutilized BTM power capacity, BTM power pricing, or BTM power consumption.
Within example embodiments described herein, various types of utility-scale power producers may operate as generation stations 202 that are capable of supplying power to one or more loads behind-the-meter. For instance, renewable energy sources (e.g., wind, solar, hydroelectric, wave, water current, tidal), fossil fuel power generation sources (coal, natural gas), and other types of power producers (e.g., nuclear power) may be positioned in an arrangement that enables the intermittent supply of generated power behind-the-meter to one or more BTM loads. One of ordinary skill in the art will recognize that the generation station 202 may vary based on an application or design in accordance with one or more example embodiments.
In addition, the particular arrangement (e.g., connections) between the generation station and one or more BTM loads can vary within examples. In one embodiment, a generation station may be positioned in an arrangement wherein the generation station selectively supplies power to the grid and/or to one or more BTM loads. As such, power cost-analysis and other factors (e.g., predicted weather conditions, contractual obligations, etc.) may be used by the generation station, a BTM load control system, a remote master control system, or some other system or enterprise, to selectively output power to either the grid or to one or more BTM loads in a manner that maximizes revenue to the generation station. In such an arrangement, the generation station may also be able to supply both the grid and one or more BTM loads simultaneously. In some instances, the arrangement may be configured to allow dynamic manipulation of the percentage of the overall generated power that is supplied to each option at a given time. For example, in some time periods, the generation station may supply no power to the BTM load.
In addition, the type of loads that are positioned behind-the-meter can vary within example embodiments. In general, a load that is behind-the-meter may correspond to any type of load capable of receiving and utilizing power behind-the-meter from a generation station. Some examples of loads include, but are not limited to, datacenters and electric vehicle (EV) charging stations.
Preferred BTM loads are loads that can be subject to intermittent power supply because BTM power may be available intermittently. In some instances, the generation station may generate power intermittently. For example, wind power station 102c and/or photovoltaic power station 102d may only generate power when resource are available or favorable. Additionally or alternatively, BTM power availability at a generation station may only be available intermittently due to power market fluctuations, power system conditions (e.g., power factor fluctuation or generation station startup and testing), and/or operational directives from grid operators or generation station operators.
Some example embodiments of BTM loads described herein involve using one or more computing systems to serve as a BTM load at a generation station. In particular, the computing system or computing systems may receive power behind-the-meter from the generation station to perform various computational operations, such as processing or storing information, performing calculations, mining for cryptocurrencies, supporting blockchain ledgers, and/or executing applications, etc. Multiple computing systems positioned behind-the-meter may operate as part of a “flexible” datacenter that is configured to operate only intermittently and to receive and utilize BTM power to carry out various computational operations similar to a traditional datacenter. In particular, the flexible datacenter may include computing systems and other components (e.g., support infrastructure, a control system) configured to utilize BTM power from one or more generation stations. The flexible datacenter may be configured to use particular load ramping abilities (e.g., quickly increase or decrease power usage) to effectively operate during intermittent periods of time when power is available from a generation station and supplied to the flexible datacenter behind-the-meter, such as during situations when supplying generated power to the grid is not favorable for the generation station. In some instances, the amount of power consumed by the computing systems at a flexible datacenter can be ramped up and down quickly, and potentially with high granularity (i.e., the load can be changed in small increments if desired). This may be done based on monitored power system conditions or other information analyses as discussed herein. As recited above, this can enable a generation station to avoid negative power market pricing and to respond quickly to grid directives. And by extension, the flexible datacenter may obtain BTM power at a price lower than the cost for power from the grid.
Various types of computing systems can provide granular behind-the-meter ramping. Preferably, the computing systems utilizing BTM power is utilized to perform computational tasks that are immune to, or not substantially hindered by, frequent interruptions or slow-downs in processing as the computing systems ramp down or up. In some embodiments, a control system may be used to activate or de-activate one or more computing systems in an array of computing systems sited behind the meter. For example, the control system may provide control instructions to one or more blockchain miners (e.g., a group of blockchain miners), including instructions for powering on or off, adjusting frequency of computing systems performing operations (e.g., adjusting the processing frequency), adjusting the quantity of operations being performed, and when to operate within a low power mode (if available).
Within examples, a control system may correspond to a specialized computing system or may be a computing system within a flexible datacenter serving in the role of the control system. The location of the control system can vary within examples as well. For instance, the control system may be located at a flexible datacenter or physically separate from the flexible datacenter. In some examples, the control system may be part of a network of control systems that manage computational operations, power consumption, and other aspects of a fleet of flexible datacenters.
Some embodiments may involve using one or more control systems to direct time-insensitive (e.g., interruptible) computational tasks to computational hardware, such as central processing units (CPUs) and graphics processing units (GPUs), sited behind the meter, while other hardware is sited in front of the meter (i.e., consuming metered grid power via a customer meter (e.g., 106d, 106f)) and possibly remote from the behind-the-meter hardware. As such, parallel computing processes, such as Monte Carlo simulations, batch processing of financial transactions, graphics rendering, machine learning, neural network processing, queued operations, and oil and gas field simulation models, are good candidates for such interruptible computational operations.
Consistent with
Generation station 202 includes power generation equipment 210, which may include, as examples, wind turbines and/or photovoltaic panels. Power generation equipment 210 may further include other electrical equipment, including but not limited to switches, busses, collectors, inverters, and power unit transformers (e.g., transformers in wind turbines).
As illustrated in
In one configuration, generated power may travel from the power generation equipment 210 over one or more connectors 230A, 230B to one or more electrical busses 240A, 240B, respectively. Each of the connectors 230A, 230B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, connector 230B is shown with an open switch, and connector 230A is shown with a closed switch, but either or both may be reversed in some embodiments. Aspects of this configuration can be used in various embodiments when BTM power is supplied without significant power conversion to BTM loads.
In various configurations, the busses 240A and 240B may be separated by an open switch 240C or combined into a common bus by a closed switch 240C.
In another configuration, generated power may travel from the power generation equipment 210 to the high side of a local step-down transformer 214. The generated power may then travel from the low side of the local step-down transformer 214 over one or more connectors 232A, 232B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 232A, 232B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, connector 232A is shown with an open switch, and connector 232B is shown with a closed switch, but either or both may be reversed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the power generation equipment 210, but the generated power must be stepped down prior to use at the BTM loads.
In another configuration, generated power may travel from the power generation equipment 210 to the low side of a local step-up transformer 212. The generated power may then travel from the high side of the local step-up transformer 212 over one or more connectors 234A, 234B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 234A, 234B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, both connectors 234A, 234B are shown with open switches, but either or both may be closed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the outbound connector 250 or the high side of the local step-up transformer 212.
In another configuration, generated power may travel from the power generation equipment 210 to the low side of the local step-up transformer 212. The generated power may then travel from the high side of the local step-up transformer 212 to the high side of local step-down transformer 213. The generated power may then travel from the low side of the local step-down transformer 213 over one or more connectors 236A, 236B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 236A, 2346 may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, both connectors 236A, 236B are shown with open switches, but either or both may be closed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the outbound connector 250 or the high side of the local step-up transformer 212, but the power must be stepped down prior to use at the BTM loads.
In one embodiment, power generated at the generation station 202 may be used to power a generation station control system 216 located at the generation station 202, when power is available. The generation station control system 216 may typically control the operation of the generation station 202. Generated power used at the generation station control system 216 may be supplied from bus 240A via connector 216A and/or from bus 240B via connector 216B. Each of the connectors 216A, 216B may be a switched connector such that power may be routed independently to 240A and/or 240B. While the generation station control system 216 can consume BTM power when powered via bus 240A or bus 240B, the BTM power taken by generation station control system 216 is insignificant in terms of rendering an economic benefit. Further, the generation station control system 216 is not configured to operate intermittently, as it generally must remain always on. Further still, the generation station control system 216 does not have the ability to quickly ramp a BTM load up or down.
In another embodiment, grid power may alternatively or additionally be used to power the generation station control system 216. As illustrated here, metered grid power from a distribution network, such as distribution network 206 for simplicity of illustration purposes only, may be used to power generation station control system 216 over connector 216C. Connector 216C may be a switched connector so that metered grid power to the generation station control system 216 can be switched on or off as needed. More commonly, metered grid power would be delivered to the generation station control system 216 via a separate distribution network (not shown), and also over a switched connector. Any such grid power delivered to the generation station control system 216 is metered by a customer meter 206A and subject to T&D costs.
In another embodiment, when power generation equipment 210 is in an idle or off state and not generating power, grid power may backfeed into generation station 202 through POI 103 and such grid power may power the generation station control system 216.
In some configurations, an energy storage system 218 may be connected to the generation station 202 via connector 218A, which may be a switched connector. For illustrative purposes only, connector 218A is shown with an open switch but in some embodiments it may be closed. The energy storage system 218 may be connected to bus 240A and/or bus 240B and store energy produced by the power generation equipment 210. The energy storage system may also be isolated from generation station 202 by switch 242A. In times of need, such as when the power generation equipment in an idle or off state and not generating power, the energy storage system may feed power to, for example, the flexible datacenters 220. The energy storage system may also be isolated from the flexible datacenters 220 by switch 242B.
In a preferred embodiment, as illustrated, power generation equipment 210 supplies BTM power via connector 242 to flexible datacenters 220. The BTM power used by the flexible datacenters 220 was generated by the generation station 202 and did not pass through the POI 103 or utility-scale generation-side meter 253, and is not subject to T&D charges. Power received at the flexible datacenters 220 may be received through respective power input connectors 220A. Each of the respective connectors 220A may be switched connector that can electrically isolate the respective flexible datacenter 220 from the connector 242. Power equipment 220B may be arranged between the flexible datacenters 220 and the connector 242. The power equipment 220B may include, but is not limited to, power conditioners, unit transformers, inverters, and isolation equipment. As illustrated, each flexible datacenter 220 may be served by a respective power equipment 220B. However, in another embodiment, one power equipment 220B may serve multiple flexible datacenter 220.
In one embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter and electrically connected to the power generation equipment 210 behind (i.e., prior to) the generation station's POI 103 with the rest of the electrical grid.
In one embodiment, BTM power produced by the power generation equipment 210 is utilized by the flexible datacenters 220 behind (i.e., prior to) the generation station's POI with an electrical grid.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter as the flexible datacenters 220 are electrically connected to the generation station 202, and generation station 202 is subject to metering by utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter), and the flexible datacenters 220 receive power from the generation station 202, but the power received by the flexible datacenters 220 from the generation station 202 has not passed through a utility-scale generation-side meter. In this embodiment, the utility-scale generation-side meter 253 (or 253A) for the generation station 202 is located at the generation station's 202 POI 103. In another embodiment, the utility-scale generation-side meter for the generation station 202 is at a location other than the POI for the generation station 202—for example, a substation (not shown) between the generation station 202 and the generation station's POI 103.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where power produced at the generation station 202 is subject to metering by utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter), but the BTM power supplied to the flexible datacenters 220 is utilized before being metered at the utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter). In this embodiment, the utility-scale generation-side meter 253 (or 253A) for the generation station 202 is located at the generation station's 202 POI 103. In another embodiment, the utility-scale generation-side meter for the generation station 202 is at a location other than the POI for the generation station 202—for example, a substation (not shown) between the generation station 202 and the generation station's POI 103.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter as they are electrically connected to the generation station 202 that supplies power to the grid, and the flexible datacenters 220 receive power from the generation station 202 that is not subject to T&D charges, but power otherwise received from the grid that is supplied by the generation station 202 is subject to T&D charges.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where electrical power is generated at the generation station 202 that supplies power to a grid, and the generated power is not subject to T&D charges before being used by flexible datacenters 220, but power otherwise received from the connected grid is subject to T&D charges.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter because they receive power generated from the generation station 202 intended for the grid, and that received power is not routed through the electrical grid before being delivered to the flexible datacenters 220.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where electrical power is generated at the generation station 202 for distribution to the grid, and the flexible datacenters 220 receive that power, and that received power is not routed through the electrical grid before being delivered to the flexible datacenters 220.
In another embodiment, metered grid power may alternatively or additionally be used to power one or more of the flexible datacenters 220, or a portion within one or more of the flexible datacenters 220. As illustrated here for simplicity, metered grid power from a distribution network, such as distribution network 206, may be used to power one or more flexible datacenters 220 over connector 256A and/or 256B. Each of connector 256A and/or 256B may be a switched connector so that metered grid power to the flexible datacenters 220 can be switched on or off as needed. More commonly, metered grid power would be delivered to the flexible datacenters 220 via a separate distribution network (not shown), and also over switched connectors. Any such grid power delivered to the flexible datacenters 220 is metered by customer meters 206A and subject to T&D costs. In one embodiment, connector 256B may supply metered grid power to a portion of one or more flexible datacenters 220. For example, connector 256B may supply metered grid power to control and/or communication systems for the flexible datacenters 220 that need constant power and cannot be subject to intermittent BTM power. Connector 242 may supply solely BTM power from the generation station 202 to high power demand computing systems within the flexible datacenters 220, in which case at least a portion of each flexible datacenters 220 so connected is operating as a BTM load. In another embodiment, connector 256A and/or 256B may supply all power used at one or more of the flexible datacenters 220, in which case each of the flexible datacenters 220 so connected would not be operating as a BTM load.
In another embodiment, when power generation equipment 210 is in an idle or off state and not generating power, grid power may backfeed into generation station 202 through POI 103 and such grid power may power the flexible datacenters 220.
The flexible datacenters 220 are shown in an example arrangement relative to the generation station 202. Particularly, generated power from the generation station 202 may be supplied to the flexible datacenters 220 through a series of connectors and/or busses (e.g., 232B, 240B, 242, 220A). As illustrated, in other embodiments, connectors between the power generation equipment 210 and other components may be switched open or closed, allowing other pathways for power transfer between the power generation equipment 210 and components, including the flexible datacenters 220. Additionally, the connector arrangement shown is illustrative only and other circuit arrangements are contemplated within the scope of supplying BTM power to a BTM load at generation station 202. For example, there may be more or fewer transformers, or one or more of transformers 212, 213, 214 may be transformer systems with multiple steppings and/or may include additional power equipment including but not limited to power conditioners, filters, switches, inverters, and/or AC/DC-DC/AC isolators. As another example, metered grid power connections to flexible datacenters 220 are shown via both 256A and 256B; however, a single connection may connect one or more flexible datacenters 220 (or power equipment 220B) to metered grid power and the one or more flexible datacenters 220 (or power equipment 220B) may include switching apparatus to direct BTM power and/or metered grid power to control systems, communication systems, and/or computing systems as desired.
In some examples, BTM power may arrive at the flexible datacenters 220 in a three-phase AC format. As such, power equipment (e.g., power equipment 220B) at one or more of the flexible datacenters 220 may enable each flexible datacenter 220 to use one or more phases of the power. For instance, the flexible datacenters 220 may utilize power equipment (e.g., power equipment 220B, or alternatively or additionally power equipment that is part of the flexible datacenter 220) to convert BTM power received from the generation station 202 for use at computing systems at each flexible datacenter 220. In other examples, the BTM power may arrive at one or more of the flexible datacenters 220 as DC power. As such, the flexible datacenters 220 may use the DC power to power computing systems. In some such examples, the DC power may be routed through a DC-to-DC converter that is part of power equipment 220B and/or flexibles datacenter 220.
In some configurations, a flexible datacenter 220 may be arranged to only have access to power received behind-the-meter from a generation station 202. In the arrangement of
In some configurations, one or more of the flexible datacenters 220 can be arranged to have connections to multiple sources that are capable of supplying power to a flexible datacenter 220. To illustrate a first example, the flexible datacenters 220 are shown connected to connector 242, which can be connected or disconnected via switches to the energy storage system 218 via connector 218A, the generation station 202 via bus 240B, and grid power via metered connector 256A. In one embodiment, the flexible datacenters 220 may selectively use power received behind-the-meter from the generation station 202, stored power supplied by the energy storage system 218, and/or grid power. For instance, flexible datacenters 220 may use power stored in the energy storage system 218 when costs for using power supplied behind-the-meter from the generation station 202 are disadvantageous. By having access to the energy storage system 218 available, the flexible datacenters 220 may use the stored power and allow the generation station 202 to subsequently refill the energy storage system 218 when cost for power behind-the-meter is low. Alternatively, the flexible datacenters 220 may use power from multiple sources simultaneously to power different components (e.g., a first set and a second set of computing systems). Thus, the flexible datacenters 220 may leverage the multiple connections in a manner that can reduce the cost for power used by the computing systems at the flexible datacenters 220. The flexible datacenters 220 control system or the remote master control system 262 may monitor power conditions and other factors to determine whether the flexible datacenters 220 should use power from either the generation station 202, grid power, the energy storage system 218, none of the sources, or a subset of sources during a given time range. Other arrangements are possible as well. For example, the arrangement of
The selection of which power source to use at a flexible datacenter (e.g., the flexible datacenters 220) or another type of BTM load can change based on various factors, such as the cost and availability of power from both sources, the type of computing systems using the power at the flexible datacenters 220 (e.g., some systems may require a reliable source of power for a long period), the nature of the computational operations being performed at the flexible datacenters 220 (e.g., a high priority task may require immediate completion regardless of cost), and temperature and weather conditions, among other possible factors. As such, a datacenter control system at the flexible datacenters 220, the remote master control system 262, or another entity (e.g., an operator at the generation station 202) may also influence and/or determine the source of power that the flexible datacenters 220 use at a given time to complete computational operations.
In some example embodiments, the flexible datacenters 220 may use power from the different sources to serve different purposes. For example, the flexible datacenters 220 may use metered power from grid power to power one or more systems at the flexible datacenters 220 that are configured to be always-on (or almost always on), such as a control and/or communication system and/or one or more computing systems (e.g., a set of computing systems performing highly important computational operations). The flexible datacenters 220 may use BTM power to power other components within the flexible datacenters 220, such as one or more computing systems that perform less critical computational operations.
In some examples, one or more flexible datacenters 220 may be deployed at the generation station 202. In other examples, flexible datacenters 220 may be deployed at a location geographically remote from the generation station 202, while still maintaining a BTM power connection to the generation station 202.
In another example arrangement, the generation station 202 may be connected to a first BTM load (e.g., a flexible datacenter 220) and may supply power to additional BTM loads via connections between the first BTM load and the additional BTM loads (e.g., a connection between a flexible datacenter 220 and another flexible datacenter 220).
The arrangement in
Within the arrangement of
Information used to make decisions may include economic and/or power-related information, such as monitored power system conditions. Monitored power system conditions may include one or more of excess power generation at a generation station 202, excess power at a generation station 202 that a connected grid cannot receive, power generation at a generation station 202 subject to economic curtailment, power generation at a generation station 202 subject to reliability curtailment, power generation at a generation station 202 subject to power factor correction, low power generation at a generation station 202, start up conditions at a generation station 202, transient power generation conditions at a generation station 202, or testing conditions where there is an economic advantage to using behind-the-meter power generation at a generation station 202. These different monitored power system conditions can be weighted differently during processing and analysis.
In some examples, the information can include the cost for power from available sources (e.g., BTM power at the generation station 202 versus metered grid power) to enable comparisons to be made which power source costs less. In some instances, the information may include historic prices for power to enable the remote master control system 262 or another system to predict potential future prices in similar situations (e.g., the cost of power tends to trend upwards for grid power during warmer weather and peak-use hours). The information may also indicate the availability of power from the various sources (e.g., BTM power at the generation station 262, the energy storage system 218 at the generation station 262, and/or metered grid power).
In addition, the information may also include other data, including information associated with operations at components within the arrangement. For instance, the information may include data associated with performance of operations at the flexible datacenters 220 and the traditional datacenters 260, such as the number of computational tasks currently being performed, the types of tasks being performed (e.g., type of computational operation, time-sensitivity, etc.), the number, types, and capabilities of available computing systems, the amount of computational tasks awaiting performance, and the types of computing systems at one or more datacenters, among others. The information may also include data specifying the conditions at one or more datacenters (e.g., whether or not the temperatures are in a desired range, the amount of power available within an energy storage system such as 218), the amount of computational tasks awaiting performance in the queue of one or more of the datacenters, and the identities of the entities associated with the computational operations at one or more of the datacenters. Entities associated with computational operations may be, for example, owners of the datacenters, customers who purchase computational time at the datacenters, or other entities.
The information used by the remote master control system 262 or another component may include data associated with the computational operations to be performed, such as deadlines, priorities (e.g., high vs. low priority tasks), cost to perform based on required computing systems, the optimal computing systems (e.g., CPU vs GPU vs ASIC; processing unit capabilities, speeds, or frequencies, or instructional sets executable by the processing units) for performing each requested computational task, and prices each entity (e.g., company) is willing to pay for computational operations to be performed or otherwise supported via computing systems at a traditional datacenter 260 or a flexible datacenter 220, among others. In addition, the information may also include other data (e.g., weather conditions at locations of datacenters or power sources, any emergencies associated with a datacenter or power source, or the current value of bids associated with an auction for computational tasks).
The information may be updated in-real time and used to make the different operational decisions within the arrangement of
The remote master control system 262 represents a computing system that is capable of obtaining, managing, and using the information described above to manage and oversee one or more operations within the arrangement of
As shown in
The remote master control system 262 may capable of directing one or more flexible datacenters 220 to ramp-up or ramp-down to desired power consumption levels, and/or to control cooperative action of multiple flexible datacenters by determining how to power each individual flexible datacenter 220 in accordance with operational directives.
The configuration of the remote master control system 262 can vary within examples as further discussed with respect to
In addition, the remote master control system 262 may communicate with components within the arrangement of
The remote master control system 262 may also communicate with grid operators and/or an operator of generation station 202 to help determine power management strategies when distributing computational operations across the various datacenters. In addition, the remote master control system 262 may communicate with other sources, such as weather prediction systems, historical and current power price databases, and auction systems, etc.
In further examples, the remote master control system 262 or another computing system within the arrangement of
In the example arrangement shown in
The arrangement of
The remote master control system 300 may perform one or more operations described herein and may include a processor 302, a data storage unit 304, a communication interface 306, a user interface 308, an operations and environment analysis module 310, and a queue system 312. In other examples, the remote master control system 300 may include more or fewer components in other possible arrangements.
As shown in
As part of the arrangement of
Although the remote master control system 300 is shown as a single entity, a network of computing systems may perform the operations of the remote master control system 300 in some examples. For example, the remote master control system 300 may exist in the form of computing systems (e.g., datacenter control systems) distributed across multiple datacenters.
The remote master control system 300 may include one or more processors 302. As such, the processor 302 may represent one or more general-purpose processors (e.g., a microprocessor) and/or one or more special-purpose processors (e.g., a digital signal processor (DSP)). In some examples, the processor 302 may include a combination of processors within examples. The processor 302 may perform operations, including processing data received from the other components within the arrangement of
The data storage unit 304 may include one or more volatile, non-volatile, removable, and/or non-removable storage components, such as magnetic, optical, or flash storage, and/or can be integrated in whole or in part with the processor 302. As such, the data storage unit 304 may take the form of a non-transitory computer-readable storage medium, having stored thereon program instructions (e.g., compiled or non-compiled program logic and/or machine code) that, when executed by the processor 302, cause the remote master control system 300 to perform one or more acts and/or functions, such as those described in this disclosure. Such program instructions can define and/or be part of a discrete software application. In some instances, the remote master control system 300 can execute program instructions in response to receiving an input, such as from the communication interface 306, the user interface 308, or the operations and environment analysis module 310. The data storage unit 304 may also store other information, such as those types described in this disclosure.
In some examples, the data storage unit 304 may serve as storage for information obtained from one or more external sources. For example, data storage unit 304 may store information obtained from one or more of the traditional datacenters 260, a generation station 202, a system associated with the grid, and flexible datacenters 220. As examples only, data storage 304 may include, in whole or in part, local storage, dedicated server-managed storage, network attached storage, and/or cloud-based storage, and/or combinations thereof.
The communication interface 306 can allow the remote master control system 300 to connect to and/or communicate with another component according to one or more protocols. For instance, the communication interface 306 may be used to obtain information related to current, future, and past prices for power, power availability, current and predicted weather conditions, and information regarding the different datacenters (e.g., current workloads at datacenters, types of computing systems available within datacenters, price to obtain power at each datacenter, levels of power storage available and accessible at each datacenter, etc.). In an example, the communication interface 306 can include a wired interface, such as an Ethernet interface or a high-definition serial-digital-interface (HD-SDI). In another example, the communication interface 406 can include a wireless interface, such as a cellular, satellite, WiMAX, or WI-FI interface. A connection can be a direct connection or an indirect connection, the latter being a connection that passes through and/or traverses one or more components, such as such as a router, switcher, or other network device. Likewise, a wireless transmission can be a direct transmission or an indirect transmission. The communication interface 306 may also utilize other types of wireless communication to enable communication with datacenters positioned at various locations.
The communication interface 306 may enable the remote master control system 300 to communicate with the components of the arrangement of
The user interface 308 can facilitate interaction between the remote master control system 300 and an administrator or user, if applicable. As such, the user interface 308 can include input components such as a keyboard, a keypad, a mouse, a touch-sensitive panel, a microphone, and/or a camera, and/or output components such as a display device (which, for example, can be combined with a touch-sensitive panel), a sound speaker, and/or a haptic feedback system. More generally, the user interface 308 can include hardware and/or software components that facilitate interaction between remote master control system 300 and the user of the system.
In some examples, the user interface 308 may enable the manual examination and/or manipulation of components within the arrangement of
The operations and environment analysis module 310 represents a component of the remote master control system 300 associated with obtaining and analyzing information to develop instructions/directives for components within the arrangement of
In some examples, the operations and environment analysis module 310 may use location, weather, activity levels at the flexible datacenters or the generation station, and power cost information to determine control strategies for one or more components in the arrangement of
The queue system 312 represents a queue capable of organizing computational operations to be performed by one or more datacenters. Upon receiving a request to perform a computational operation, the remote master control system 300 may assign the computational operation to the queue until one or more computing systems are available to support the computational operation. The queue system 312 may be used for organizing and transferring computational tasks in real time.
The organizational design of the queue system 312 may vary within examples. In some examples, the queue system 312 may organize indications (e.g., tags, pointers) to sets of computational operations requested by various enterprises. The queue system 312 may operate as a First-In-First-Out (FIFO) data structure. In a FIFO data structure, the first element added to the queue will be the first one to be removed. As such, the queue system 312 may include one or more queues that operate using the FIFO data structure.
In some examples, one or more queues within the queue system 312 may use other designs of queues, including rules to rank or organize queues in a particular manner that can prioritize some sets of computational operations over others. The rules may include one or more of an estimated cost and/or revenue to perform each set of computational operations, an importance assigned to each set of computational operations, and deadlines for initiating or completing each set of computational operations, among others. Examples using a queue system are further described below with respect to
In some examples, the remote master control system 300 may be configured to monitor one or more auctions to obtain computational operations for datacenters to support. Particularly, the remote master control system 300 may use resource availability and power prices to develop and submit bids to an external or internal auction system for the right to support particular computational operations. As a result, the remote master control system 300 may identify computational operations that could be supported at one or more flexible datacenters 220 at low costs.
The generation station 400 can correspond to any type of grid-connected utility-scale power producer capable of supplying power to one or more loads. The size, amount of power generated, and other characteristics of the generation station 400 may differ within examples. For instance, the generation station 400 may be a power producer that provides power intermittently. The power generation may depend on monitored power conditions, such as weather at the location of the generation station 400 and other possible conditions. As such, the generation station 400 may be a temporary arrangement, or a permanent facility, configured to supply power. The generation station 400 may supply BTM power to one or more loads and supply metered power to the electrical grid. Particularly, the generation station 400 may supply power to the grid as shown in the arrangement of
The power generation equipment 401 represents the component or components configured to generate utility-scale power. As such, the power generation equipment 401 may depend on the type of facility that the generation station 400 corresponds to. For instance, the power generation equipment 401 may correspond to electric generators that transform kinetic energy into electricity. The power generation equipment 401 may use electromagnetic induction to generate power. In other examples, the power generation equipment 401 may utilize electrochemistry to transform chemical energy into power. The power generation equipment 401 may use the photovoltaic effect to transform light into electrical energy. In some examples, the power generation equipment 401 may use turbines to generate power. The turbines may be driven by, for example, wind, water, steam or burning gas. Other examples of power production are possible.
The communication interface 408 enable the generation station 400 to communicate with other components within the arrangement of
The generation station control system 414 may be one or more computing systems configured to control various aspects of the generation station 400.
The BTM interface 406 is a module configured to enable the power generation equipment 401 to supply BTM power to one or more loads and may include multiple components. The arrangement of the BTM interface 406 may differ within examples based on various factors, such as the number of flexible datacenters 220 (or 500) coupled to the generation station 400, the proximity of the flexible datacenters 220 (or 500), and the type of generation station 400, among others. In some examples, the BTM interface 406 may be configured to enable power delivery to one or more flexible datacenters positioned near the generation station 400. Alternatively, the BTM interface 406 may also be configured to enable power delivery to one or more flexible datacenters 220 (or 500) positioned remotely from the generation station 400.
The grid interface 404 is a module configured to enable the power generation equipment 401 to supply power to the grid and may include multiple components. As such, the grid interface 404 may couple to one or more transmission lines (e.g., transmission lines 404a shown in
The user interface 410 represents an interface that enables administrators and/or other entities to communicate with the generation station 400. As such, the user interface 410 may have a configuration that resembles the configuration of the user interface 308 shown in
The power transformation equipment 402 represents equipment that can be utilized to enable power delivery from the power generation equipment 401 to the loads and to transmission lines linked to the grid. Example power transformation equipment 402 includes, but is not limited to, transformers, inverters, phase converters, and power conditioners.
The example configuration shown in
The flexible datacenter 500 may include a design that allows for temporary and/or rapid deployment, setup, and start time for supporting computational operations. For instance, the flexible datacenter 500 may be rapidly deployed at a location near a source of generation station power (e.g., near a wind farm or solar farm). Rapid deployment may involve positioning the flexible datacenter 500 at a target location and installing and/or configuring one or more racks of computing systems within. The racks may include wheels to enable swift movement of the computing systems. Although the flexible datacenter 500 could theoretically be placed anywhere, transmission losses may be minimized by locating it proximate to BTM power generation.
The physical construction and layout of the flexible datacenter 500 can vary. In some instances, the flexible datacenter 500 may utilize a metal container (e.g., a metal container 602 shown in
Within the flexible datacenter 500, various internal components enable the flexible datacenter 500 to utilize power to perform some form of operations. The power input system 502 is a module of the flexible datacenter 500 configured to receive external power and input the power to the different components via assistance from the power distribution system 506. As discussed with respect to
In some embodiments, the power input system 502 may include some or all of flexible datacenter Power Equipment 220B. The power input system 502 may be designed to obtain power in different forms (e.g., single phase or three-phase behind-the-meter alternating current (“AC”) voltage, and/or direct current (“DC”) voltage). As shown, the power input system 502 includes a BTM power input sub-system 522, a grid power input sub-system 524, and an energy input sub-system 526. These sub-systems are included to illustrate example power input sub-systems that the flexible datacenter 500 may utilize, but other examples are possible. In addition, in some instances, these sub-systems may be used simultaneously to supply power to components of the flexible datacenter 500. The sub-systems may also be used based on available power sources.
In some implementations, the BTM power input sub-system 522 may include one or more AC-to-AC step-down transformers used to step down supplied medium-voltage AC to low voltage AC (e.g., 120V to 600V nominal) used to power computing systems 512 and/or other components of flexible datacenter 500. The power input system 502 may also directly receive single-phase low voltage AC from a generation station as BTM power, from grid power, or from a stored energy system such as energy storage system 218. In some implementations, the power input system 502 may provide single-phase AC voltage to the datacenter control system 504 (and/or other components of flexible datacenter 500) independent of power supplied to computing systems 512 to enable the datacenter control system 504 to perform management operations for the flexible datacenter 500. For instance, the grid power input sub-system 524 may use grid power to supply power to the datacenter control system 504 to ensure that the datacenter control system 504 can perform control operations and communicate with the remote master control system 300 (or 262) during situations when BTM power is not available. As such, the datacenter control system 504 may utilize power received from the power input system 502 to remain powered to control the operation of flexible datacenter 500, even if the computational operations performed by the computing system 512 are powered intermittently. In some instances, the datacenter control system 504 may switch into a lower power mode to utilize less power while still maintaining the ability to perform some functions.
The power distribution system 506 may distribute incoming power to the various components of the flexible datacenter 500. For instance, the power distribution system 506 may direct power (e.g., single-phase or three-phase AC) to one or more components within flexible datacenter 500. In some embodiments, the power distribution system 506 may include some or all of flexible datacenter Power Equipment 220B.
In some examples, the power input system 502 may provide three phases of three-phase AC voltage to the power distribution system 506. The power distribution system 506 may controllably provide a single phase of AC voltage to each computing system or groups of computing systems 512 disposed within the flexible datacenter 500. The datacenter control system 504 may controllably select which phase of three-phase nominal AC voltage that power distribution system 506 provides to each computing system 512 or groups of computing systems 512. This is one example manner in which the datacenter control system 504 may modulate power delivery (and load at the flexible datacenter 500) by ramping-up flexible datacenter 500 to fully operational status, ramping-down flexible datacenter 500 to offline status (where only datacenter control system 504 remains powered), reducing load by withdrawing power delivery from, or reducing power to, one or more of the computing systems 512 or groups of the computing systems 512, or modulating power factor correction for the generation station 300 (or 202) by controllably adjusting which phases of three-phase nominal AC voltage are used by one or more of the computing systems 512 or groups of the computing systems 512. The datacenter control system 504 may direct power to certain sets of computing systems based on computational operations waiting for computational resources within the queue system 514. In some embodiments, the flexible datacenter 500 may receive BTM DC power to power the computing systems 512.
One of ordinary skill in the art will recognize that a voltage level of three-phase AC voltage may vary based on an application or design and the type or kind of local power generation. As such, a type, kind, or configuration of the operational AC-to-AC step down transformer (not shown) may vary based on the application or design. In addition, the frequency and voltage level of three-phase AC voltage, single-phase AC voltage, and DC voltage may vary based on the application or design in accordance with one or more embodiments.
As discussed above, the datacenter control system 504 may perform operations described herein, such as dynamically modulating power delivery to one or more of the computing systems 512 disposed within flexible datacenter 500. For instance, the datacenter control system 504 may modulate power delivery to one or more of the computing systems 512 based on various factors, such as BTM power availability or an operational directive from a generation station 262 or 300 control system, a remote master control system 262 or 300, or a grid operator. In some examples, the datacenter control system 504 may provide computational operations to sets of computing systems 512 and modulate power delivery based on priorities assigned to the computational operations. For instance, an important computational operation (e.g., based on a deadline for execution and/or price paid by an entity) may be assigned to a particular computing system or set of computing systems 512 that has the capacity, computational abilities to support the computational operation. In addition, the datacenter control system 504 may also prioritize power delivery to the computing system or set of computing systems 512.
In some example, the datacenter control system 504 may further provide directives to one or more computing systems to change operations in some manner. For instance, the datacenter control system 504 may cause one or more computing systems 512 to operate at a lower or higher frequency, change clock cycles, or operate in a different power consumption mode (e.g., a low power mode). These abilities may vary depending on types of computing systems 512 available at the flexible datacenter 500. As a result, the datacenter control system 504 may be configured to analyze the computing systems 512 available either on a periodic basis (e.g., during initial set up of the flexible datacenter 500) or in another manner (e.g., when a new computational operation is assigned to the flexible datacenter 500).
The datacenter control system 504 may also implement directives received from the remote master control system 262 or 300. For instance, the remote master control system 262 or 300 may direct the flexible datacenter 500 to switch into a low power mode. As a result, one or more of the computing systems 512 and other components may switch to the low power mode in response.
The datacenter control system 504 may utilize the communication interface 503 to communicate with the remote master control system 262 or 300, other datacenter control systems of other datacenters, and other entities. As such, the communication interface 503 may include components and operate similar to the communication interface 306 of the remote master control system 300 described with respect to
The flexible datacenter 500 may also include a climate control system 508 to maintain computing systems 512 within a desired operational temperature range. The climate control system 508 may include various components, such as one or more air intake components, an evaporative cooling system, one or more fans, an immersive cooling system, an air conditioning or refrigerant cooling system, and one or more air outtake components. One of ordinary skill in the art will recognize that any suitable heat extraction system configured to maintain the operation of computing systems 512 within the desired operational temperature range may be used.
The flexible datacenter 500 may further include an energy storage system 510. The energy storage system 510 may store energy for subsequent use by computing systems 512 and other components of flexible datacenter 500. For instance, the energy storage system 510 may include a battery system. The battery system may be configured to convert AC voltage to DC voltage and store power in one or more storage cells. In some instances, the battery system may include a DC-to-AC inverter configured to convert DC voltage to AC voltage, and may further include an AC phase-converter, to provide AC voltage for use by flexible datacenter 500.
The energy storage system 510 may be configured to serve as a backup source of power for the flexible datacenter 500. For instance, the energy storage system 510 may receive and retain power from a BTM power source at a low cost (or no cost at all). This low-cost power can then be used by the flexible datacenter 500 at a subsequent point, such as when BTM power costs more. Similarly, the energy storage system 510 may also store energy from other sources (e.g., grid power). As such, the energy storage system 510 may be configured to use one or more of the sub-systems of the power input system 502.
In some examples, the energy storage system 510 may be external to the flexible datacenter 500. For instance, the energy storage system 510 may be an external source that multiple flexible datacenters utilize for back-up power.
The computing systems 512 represent various types of computing systems configured to perform computational operations. Performance of computational operations include a variety of tasks that one or more computing systems may perform, such as data storage, calculations, application processing, parallel processing, data manipulation, cryptocurrency mining, and maintenance of a distributed ledger, among others. As shown in
Due to different performance features and abilities associated with the different types of computing systems, the datacenter control system 504 may determine, maintain, and/or relay this information about the types and/or abilities of the computing systems, quantity of each type, and availability to the remote master control system 262 or 300 on a routine basis (e.g., periodically or on-demand). This way, the remote master control system 262 or 300 may have current information about the abilities of the computing systems 512 when distributing computational operations for performance at one or more flexible datacenters. Particularly, the remote master control system 262 or 300 may assign computational operations based on various factors, such as the types of computing systems available and the type of computing systems required by each computing operation, the availability of the computing systems, whether computing systems can operate in a low power mode, and/or power consumption and/or costs associated with operating the computing systems, among others.
The quantity and arrangement of these computing systems 512 may vary within examples. In some examples, the configuration and quantity of computing systems 512 may depend on various factors, such as the computational tasks that are performed by the flexible datacenter 500. In other examples, the computing systems 512 may include other types of computing systems as well, such as DSPs, SIMDs, neural processors, and/or quantum processors.
As indicated above, the computing systems 512 can perform various computational operations, including in different configurations. For instance, each computing system may perform a particular computational operation unrelated to the operations performed at other computing systems. Groups of the computing systems 512 may also be used to work together to perform computational operations.
In some examples, multiple computing systems may perform the same computational operation in a redundant configuration. This redundant configuration creates a back-up that prevents losing progress on the computational operation in situations of a computing failure or intermittent operation of one or more computing systems. In addition, the computing systems 512 may also perform computational operations using a check point system. The check point system may enable a first computing system to perform operations up to a certain point (e.g., a checkpoint) and switch to a second computing system to continue performing the operations from that certain point. The check point system may also enable the datacenter control system 504 to communicate statuses of computational operations to the remote master control system 262 or 300. This can further enable the remote master control system 262 300 to transfer computational operations between different flexible datacenters allowing computing systems at the different flexible datacenters to resume support of computational operations based on the check points.
The queue system 514 may operate similar to the queue system 312 of the remote master control system 300 shown in
As discussed above, the structural arrangement of the flexible datacenter 500 may depend on various factors, such as the ability to maintain temperature within the mobile container 602 within a desired temperature range. The desired temperature range may depend on the geographical location of the mobile container 602 and the type and quantity of the computing systems 512 operating within the flexible datacenter 500 as well as other possible factors. As such, the different design elements of the mobile container 602 including the inner contents and positioning of components may depend on factors that aim to maximize the use of space within mobile container 602, lower the amount of power required to cool the computing systems 512, and make setup of the flexible datacenter 500 efficient. For instance, a first flexible datacenter positioned in a cooler geographic region may include less cooling equipment than a second flexible datacenter positioned in a warmer geographic region.
As shown in
The datacenter control system 504 may independently, or cooperatively with one or more of the generation station control system 414, the remote master control system 300, and the grid operator 702, modulate power at the flexible datacenter 500. During operations, the power delivery to the flexible datacenter 500 may be dynamically adjusted based on conditions or operational directives. The conditions may correspond to economic conditions (e.g., cost for power, aspects of computational operations to be performed), power-related conditions (e.g., availability of the power, the sources offering power), demand response, and/or weather-related conditions, among others.
The generation station control system 414 may be one or more computing systems configured to control various aspects of a generation station (not independently illustrated, e.g., 216 or 400). As such, the generation station control system 414 may communicate with the remote master control system 300 over a networked connection 706 and with the datacenter control system 704 over a networked or other data connection 708.
As discussed with respect to
The grid operator 702 may be one or more computing systems that are configured to control various aspects of the power grid (not independently illustrated) that receives power from the generation station. The grid operator 702 may communicate with the generation station control system 300 over a networked or other data connection 712.
The datacenter control system 504 may monitor BTM power conditions at the generation station and determine when a datacenter ramp-up condition is met. The BTM power availability may include one or more of excess local power generation, excess local power generation that the grid cannot accept, local power generation that is subject to economic curtailment, local power generation that is subject to reliability curtailment, local power generation that is subject to power factor correction, conditions where the cost for power is economically viable (e.g., low cost to obtain power), low priced power, situations where local power generation is prohibitively low, start up situations, transient situations, or testing situations where there is an economic advantage to using locally generated behind-the-meter power generation, specifically power available at little to no cost and with no associated transmission or distribution losses or costs. For example, a datacenter control system may analyze future workload and near term weather conditions at the flexible datacenter.
In some instances, the datacenter ramp-up condition may be met if there is sufficient behind-the-meter power availability and there is no operational directive from the generation station control system 414, the remote master control system 300, or the grid operator 702 to go offline or reduce power. As such, the datacenter control system 504 may enable 714 the power input system 502 to provide power to the power distribution system 506 to power the computing systems 512 or a subset thereof.
The datacenter control system 504 may optionally direct one or more computing systems 512 to perform predetermined computational operations (e.g., distributed computing processes). For example, if the one or more computing systems 512 are configured to perform blockchain hashing operations, the datacenter control system 504 may direct them to perform blockchain hashing operations for a specific blockchain application, such as, for example, Bitcoin, Litecoin, Ripple, or Ethereum. Alternatively, one or more computing systems 512 may be configured to perform high-throughput computing operations and/or high performance computing operations.
The remote master control system 300 may specify to the datacenter control system 504 what sufficient behind-the-meter power availability constitutes, or the datacenter control system 504 may be programmed with a predetermined preference or criteria on which to make the determination independently. For example, in certain circumstances, sufficient behind-the-meter power availability may be less than that required to fully power the entire flexible datacenter 500. In such circumstances, the datacenter control system 504 may provide power to only a subset of computing systems, or operate the plurality of computing systems in a lower power mode, that is within the sufficient, but less than full, range of power that is available. In addition, the computing systems 512 may adjust operational frequency, such as performing more or less processes during a given duration.
While the flexible datacenter 500 is online and operational, a datacenter ramp-down condition may be met when there is insufficient or anticipated to be insufficient, behind-the-meter power availability or there is an operational directive from the generation station control system 414, the remote master control system 300, or the grid operator 702. The datacenter control system 504 may monitor and determine when there is insufficient, or anticipated to be insufficient, behind-the-meter power availability. As noted above, sufficiency may be specified by the remote master control system 300 or the datacenter control system 504 may be programmed with a predetermined preference or criteria on which to make the determination independently.
An operational directive may be based on current dispatchability, forward looking forecasts for when behind-the-meter power is, or is expected to be, available, economic considerations, reliability considerations, operational considerations, or the discretion of the generation station control system 414, the remote master control system 300, or the grid operator 702. For example, the generation station control system 414, the remote master control system 300, or the grid operator 702 may issue an operational directive to flexible datacenter 500 to go offline and power down. When the datacenter ramp-down condition is met, the datacenter control system 504 may disable power delivery to the plurality of computing systems (e.g., 512). The datacenter control system 504 may disable 714 the power input system 502 from providing power (e.g., three-phase nominal AC voltage) to the power distribution system 506 to power down the computing systems 512 while the datacenter control system 504 remains powered and is capable of returning service to operating mode at the flexible datacenter 500 when behind-the-meter power becomes available again.
While the flexible datacenter 500 is online and operational, changed conditions or an operational directive may cause the datacenter control system 504 to modulate power consumption by the flexible datacenter 500. The datacenter control system 504 may determine, or the generation station control system 414, the remote master control system 300, or the grid operator 702 may communicate, that a change in local conditions may result in less power generation, availability, or economic feasibility, than would be necessary to fully power the flexible datacenter 500. In such situations, the datacenter control system 504 may take steps to reduce or stop power consumption by the flexible datacenter 500 (other than that required to maintain operation of datacenter control system 504).
Alternatively, the generation station control system 414, the remote master control system 300, or the grid operator 702, may issue an operational directive to reduce power consumption for any reason, the cause of which may be unknown. In response, the datacenter control system 504 may dynamically reduce or withdraw power delivery to one or more computing systems 512 to meet the dictate. The datacenter control system 504 may controllably provide three-phase nominal AC voltage to a smaller subset of computing systems (e.g., 512) to reduce power consumption. The datacenter control system 504 may dynamically reduce the power consumption of one or more computing systems by reducing their operating frequency or forcing them into a lower power mode through a network directive.
One of ordinary skill in the art will recognize that datacenter control system 504 may be configured to have a number of different configurations, such as a number or type or kind of the computing systems 512 that may be powered, and in what operating mode, that correspond to a number of different ranges of sufficient and available behind-the-meter power. As such, the datacenter control system 504 may modulate power delivery over a variety of ranges of sufficient and available unutilized behind-the-meter power availability.
The remote master control system 300 may provide directive to datacenter control systems of the fleet of flexible datacenters in a similar manner to that shown and described with respect to
The arrangement of
In some examples, one or more components, such as the datacenter control system 504, the remote master control system 300, the queue system 312, or the control system 936, may be configured to identify situations that may arise where using the flexible datacenter 500 can reduce costs or increase productivity of the system, as compared to using the traditional datacenter 902 for computational operations. For example, a component within the arrangement of
In some examples, the datacenter control system 504 may monitor activity of the computing systems 512 within the flexible datacenter 500 and use the respective activity levels to determine when to obtain computational operations from the queue system 312. For instance, the datacenter control system 504 may analyze various factors prior to requesting or accessing a set of computational operations or an indication of the computational operations for the computing systems 512 to perform. The various factors may include power availability at the flexible datacenter 500 (e.g., either stored or from a BTM source), availability of the computing systems 512 (e.g., percentage of computing systems available), type of computational operations available, estimated cost to perform the computational operations at the flexible datacenter 500, cost for power, cost for power relative to cost for grid power, and instructions from other components within the system, among others. The datacenter control system 504 may analyze one or more of the factors when determining whether to obtain a new set of computational operations for the computing systems 512 to perform. In such a configuration, the datacenter control system 504 manages the activity of the flexible datacenter 500, including determining when to acquire new sets of computational operations when capacity among the computing systems 512 permit.
In other examples, a component (e.g., the remote master control system 300) within the system may assign or distribute one or more sets of computational operations organized by the queue system 312 to the flexible datacenter 500. For example, the remote master control system 300 may manage the queue system 312, including the distribution of computational operations organized by the queue system 312 to the flexible datacenter 500 and the traditional datacenter 902. The remote master control system 300 may utilize to information described with respect to the Figures above to determine when to assign computational operations to the flexible datacenter 500.
The traditional datacenter 902 may include a power input system 930, a power distribution system 932, a datacenter control system 936, and a set of computing systems 934. The power input system 930 may be configured to receive power from a power grid and distribute the power to the computing systems 934 via the power distribution system 932. The datacenter control system 936 may monitor activity of the computing systems 934 and obtain computational operations to perform from the queue system 312. The datacenter control system 936 may analyze various factors prior to requesting or accessing a set of computational operations or an indication of the computational operations for the computing systems 934 to perform. A component (e.g., the remote master control system 300) within the arrangement of
The communication link 916 represents one or more links that may serve to connect the flexible datacenter 500, the traditional datacenter 902, and other components within the system (e.g., the remote master control system 300, the queue system 312—connections not shown). In particular, the communication link 916 may enable direct or indirect communication between the flexible datacenter 500 and the traditional datacenter 902. The type of communication link 916 may depend on the locations of the flexible datacenter 500 and the traditional datacenter 902. Within embodiments, different types of communication links can be used, including but not limited to WAN connectivity, cloud-based connectivity, and wired and wireless communication links.
The queue system 312 represents an abstract data type capable of organizing computational operation requests received from entities. As each request for computational operations are received, the queue system 312 may organize the request in some manner for subsequent distribution to a datacenter. Different types of queues can make up the queue system 312 within embodiments. The queue system 312 may be a centralized queue that organizes all requests for computational operations. As a centralized queue, all incoming requests for computational operations may be organized by the centralized queue.
In other examples, the queue system 312 may be distributed consisting of multiple queue sub-systems. In the distributed configuration, the queue system 312 may use multiple queue sub-systems to organize different sets of computational operations. Each queue sub-system may be used to organize computational operations based on various factors, such as according to deadlines for completing each set of computational operations, locations of enterprises submitting the computational operations, economic value associated with the completion of computational operations, and quantity of computing resources required for performing each set of computational operations. For instance, a first queue sub-system may organize sets of non-intensive computational operations and a second queue sub-system may organize sets of intensive computational operations. In some examples, the queue system 312 may include queue sub-systems located at each datacenter. This way, each datacenter (e.g., via a datacenter control system) may organize computational operations obtained at the datacenter until computing systems are able to start executing the computational operations. In some examples, the queue system 312 may move computational operations between different computing systems or different datacenters in real-time.
Within the arrangement of
The queue system 312 may include a computing system configured to organize and maintain queues within the queue system 312. In another example, one or more other components of the system may maintain and support queues within the queue system 312. For instance, the remote master control system 300 may maintain and support the queue system 312. In other examples, multiple components may maintain and support the queue system 312 in a distributed manner, such as a blockchain configuration.
In some embodiments, the remote master control system 300 may serve as an intermediary that facilitates all communication between flexible datacenter 500 and the traditional datacenter 902. Particularly, the traditional datacenter 902 or the flexible datacenter 500 might need to transmit communications to the remote master control system 300 in order to communicate with the other datacenter. As also shown, the remote master control system 300 may connect to the queue system 312 via the communication link 918. Computational operations may be distributed between the queue system 312 and the remote master control system 300 via the communication link 918. The computational operations may be transferred in real-time and mid-performance from one datacenter to another (e.g., from the traditional datacenter 902 to the flexible datacenter 500). In addition, the remote master control system 300 may manage the queue system 312, including providing resources to support queues within the queue system 312.
As a result, the remote master control system 300 may offload some or all of the computational operations assigned to the traditional datacenter 902 to the flexible datacenter 500. This way, the flexible datacenter 500 can reduce overall computational costs by using the behind-the-meter power to provide computational resources to assist traditional datacenter 902. The remote master control system 300 may use the queue system 312 to temporarily store and organize the offloaded computational operations until a flexible datacenter (e.g., the flexible datacenter 500) is available to perform them. The flexible datacenter 500 consumes behind-the-meter power without transmission or distribution costs, which lowers the costs associated with performing computational operations originally assigned to the traditional datacenter 902. The remote master control system 300 may further communicate with the flexible datacenter 500 via communication link 922 and the traditional datacenter 902 via the communication link 924.
In step 1010, the datacenter control system, the remote master control system, or another computing system may monitor behind-the-meter power availability. In some embodiments, monitoring may include receiving information or an operational directive from the generation station control system or the grid operator corresponding to behind-the-meter power availability.
In step 1020, the datacenter control system or the remote master control system 300 may determine when a datacenter ramp-up condition is met. In some embodiments, the datacenter ramp-up condition may be met when there is sufficient behind-the-meter power availability and there is no operational directive from the generation station to go offline or reduce power.
In step 1030, the datacenter control system may enable behind-the-meter power delivery to one or more computing systems. In some instances, the remote mater control system may directly enable BTM power delivery to computing systems within the flexible system without instructing the datacenter control system.
In step 1040, once ramped-up, the datacenter control system or the remote master control system may direct one or more computing systems to perform predetermined computational operations. In some embodiments, the predetermined computational operations may include the execution of one or more distributed computing processes, parallel processes, and/or hashing functions, among other types of processes.
While operational, the datacenter control system, the remote master control system, or another computing system may receive an operational directive to modulate power consumption. In some embodiments, the operational directive may be a directive to reduce power consumption. In such embodiments, the datacenter control system or the remote master control system may dynamically reduce power delivery to one or more computing systems or dynamically reduce power consumption of one or more computing systems. In other embodiments, the operational directive may be a directive to provide a power factor correction factor. In such embodiments, the datacenter control system or the remote master control system may dynamically adjust power delivery to one or more computing systems to achieve a desired power factor correction factor. In still other embodiments, the operational directive may be a directive to go offline or power down. In such embodiments, the datacenter control system may disable power delivery to one or more computing systems.
In step 1070, the datacenter control system or the remote master control system may determine when a datacenter ramp-down condition is met. In certain embodiments, the datacenter ramp-down condition may be met when there is insufficient behind-the-meter power availability or anticipated to be insufficient behind-the-meter power availability or there is an operational directive from the generation station to go offline or reduce power.
In step 1080, the datacenter control system may disable behind-the-meter power delivery to one or more computing systems. In step 1090, once ramped-down, the datacenter control system remains powered and in communication with the remote master control system so that it may dynamically power the flexible datacenter when conditions change.
One of ordinary skill in the art will recognize that a datacenter control system may dynamically modulate power delivery to one or more computing systems of a flexible datacenter based on behind-the-meter power availability or an operational directive. The flexible datacenter may transition between a fully powered down state (while the datacenter control system remains powered), a fully powered up state, and various intermediate states in between. In addition, flexible datacenter may have a blackout state, where all power consumption, including that of the datacenter control system is halted. However, once the flexible datacenter enters the blackout state, it will have to be manually rebooted to restore power to datacenter control system. Generation station conditions or operational directives may cause flexible datacenter to ramp-up, reduce power consumption, change power factor, or ramp-down.
Within the system 1100, the remote master control system 262 may be configured to help manage operations at the flexible datacenters 1102, 1104, and the traditional datacenter 1106. Each datacenter may be electrically coupled to one or more power generation sources. For example, the flexible datacenter 1102 may be electrically coupled to a first power generation source from which flexible datacenter 1102 receives BTM power and the flexible datacenter 1104 may be electrically coupled to a second power generation source from which flexible datacenter 1104 receives BTM power. In addition, the traditional datacenter 1106 may be electrically coupled to the power grid from which it receives metered grid power. Other arrangements are possible.
Each datacenter may be configured with one or more computing systems to perform computational operations. Although computing systems are shown in
As shown in
The remote master control system 262 or another computing system may be configured to manage computational operations among computing systems (or hash cards) at one or more of the datacenters based on one or more monitored conditions. Particularly, the remote master control system 262 may monitor and analyze a set of conditions to assign, transfer, and otherwise manage computational operations using the one or more datacenters 1102-1106.
In one respect, the remote master control system 262 may assign new computational operations to computing systems within one or more datacenters. As shown, the remote master control system 262 may assign computational operations to one or more of the flexible datacenters 1102-1104 and the traditional datacenter 1106. For instance, the remote master control system 262 may assign a computational operation to a datacenter control system (not shown) or a queue system (not shown) at the flexible datacenter 1102. The datacenter control system (not shown) may subsequently distribute the computational operations to the computing systems 1108 or the queue system, which can be used to automatically assign computational operations to each computing system (or sets of computing systems) based on predefined conditions associated with the queue system. In addition, the remote master control system 262 may assign a computational operation directly to one or more computing systems 1108 at the flexible datacenter 1102. For instance, the remote master control system 262 may assign computational operations directly to one or more single computing systems, one or more groups of computing systems (e.g., the first set 1114A, the second set 1114B, and the third set 1114C), or all of the computing systems at one or more datacenters.
In addition, the remote master control system 262 may transfer computational operations between computing systems of one or more of the datacenters 1102-1106 based on one or more monitored conditions. For instance, the remote master control system may transfer computational operations between datacenters (e.g., between datacenters 1102-1106) and computational operations between particular computing systems within a datacenter.
To illustrate a first example, the remote master control system 262 may transfer a computational operation from computing systems 1108 of the flexible datacenter 1102 to the computing systems 1110 of the flexible datacenter 1104 and/or the traditional center 1106. Similar transfers between the datacenters may occur between the datacenters 1102-1106. In addition, transfers may occur between sets of computing systems at the same or different datacenters as well as between individual computing systems at the same or different datacenters. In some instances, a computational operation may be transferred from more computing systems to less computing systems. In other instances, a computational operation may be transferred from less computing systems to more computing systems. In further instances, a computational operation may be transferred between equal numbers of computing systems. A computational operation may be assigned or transferred in whole or in parts by the remote master control system, a queue system, or other computing systems.
The computational operations may also be managed in other ways. In one respect, the remote master control system 300 may divide the performance of a computational operation among multiple computing systems. For instance, the remote master control system 262 may divide and distribute a computational operation among the first set 1114A, the second set 1114B, and the third set 1114C of computing systems 1108 at flexible datacenter. Each set of computing systems 1114A-1114C may receive a different portion of the computational operation or the same portion of the computational operation to perform. Particularly, the remote master control system 262 may utilize the monitored conditions when distributing the computational operation. As a result, the remote master control system 262 may manage performance and distribution of computational operations among the datacenters 1102-1106 in communication with the remote master control system 262.
As indicated above, the remote master control system 262 (or another system) may monitor and use one or more conditions to determine distribution instructions for computational operations. Particularly, these monitored conditions may enable efficient distribution and performance of computational operations among computing systems at one or more datacenters (e.g., datacenters 1102-1106) in ways that can reduce costs and/or time to perform computational operations, take advantage of availability and abilities of computing systems at the datacenters 1102-1106, and/or take advantage in changes in the cost for power at the datacenters 1102-1106. In addition, the monitored conditions may be used to determine control instructions for the computing systems and/or hash cards. The control instructions may include power ramping instructions.
Example monitored conditions include, but are not limited to, power availability at each datacenter (i.e., power availability 1120) and the price of the different available power options (i.e., the power prices 1122), parameters related to the computing systems (e.g., abilities, quantity available, estimated time until availability of occupied computing systems) at the various datacenters (i.e., the computing systems parameters 1124), and parameters related to the computational operations requiring performance and currently being performed (e.g., quantity of operations, estimated time to complete, cost to perform each computational operation, deadlines and priorities associated with each computational operation) (i.e., the computational operations parameters 1128). Other monitored conditions may include prices of cryptocurrencies 1126, any potential power generation disruption due to emergencies or other events, and changes in temperatures or weather conditions at power generators or datacenters (i.e., the weather conditions 1129). In some embodiments, the monitored conditions may assist the remote master control system 262 (or another computing system) manage computational operations across computing systems at one or more datacenters in a way that can maximize profitability. As such, the operations and environment analysis module (or another component) of the remote master control system 262 may be configured to monitor one or more conditions described above.
The various monitored conditions described above as well as other potential conditions may change dynamically and with great frequency. Thus, to enable efficient distribution and performance of the computational operations at the datacenters, the remote master control system 262 may be configured to monitor changes in the various conditions to assist with the efficient management and operations of the computing systems (and/or hash cards) at each datacenter. For instance, the remote master control system 262 may engage in wired or wireless communication 1130 with datacenter control systems (e.g., datacenter control system 504) at each datacenter as well as other sources to monitor for changes in the conditions. In turn, the remote master control system 262 may analyze the different conditions in real-time to modulate operating attributes of one or more computing systems and/or hash cards at one or more of the datacenters. For instance, the conditions may assist with determining power ramping conditions and/or other operating attributes (e.g., operation frequency, hash rate) of the computing systems and/or hash cards. By using the monitored conditions, the remote master control system 262 may increase revenue, decrease costs (e.g., maximize profitability), and/or increase performance of computational operations via various modifications, such as transferring computational operations between datacenters or sets of computing systems within a datacenter and adjusting performance at one or more sets of computing systems (e.g., switching to a low power mode).
The remote master control system 262 may be configured to modulate operating attributes at one or more computing systems (and/or hash cards) in various ways, such as increasing processing speed or frequency or ramping up or down power consumption. The changes initiated at a datacenter may depend on the analysis of the monitored conditions described above and other potential conditions that can assist the remote master control system 262 potentially increase profitability and/or performance of computational operations. In addition, the remote master control system 262 may initiate multiple changes at a given time, such as transferring computational operations between datacenters and powering off some computing systems while switching the processing frequency on others.
In one respect, the remote master control system 262 or another datacenter control system may cause one or more computing systems and/or hash cards to switch into a low-power mode. The low-power mode may utilize a lower amount of power to perform computational operations at a potentially different rate. In another respect, the remote master control system 262 or another datacenter control system may cause one or more computing systems and/or hash cards to operate in another mode (e.g., high-power consumption mode). The high power mode may increase the rate that computational operations are performed.
In some situations, modulating operating attributes may involve adjusting other aspects of the computing systems and/or the hash cards, such as the processing speed, frequency, hash rate or another aspect of performance. The remote master control system may also modulate operating attributes at one or more sets of computing systems (e.g., hash cards) by switching one or more computing systems (or sets of computing systems) into a low-power mode that reduces power consumption at the computing systems or powering off one or more computing systems (or sets of computing systems).
When analyzing the monitored conditions, the remote master control system may perform a weighted analysis to manage computational operations among one or more computing systems at one or more datacenters. The weighted analysis may involve assigning weights to each monitored condition such that some of the conditions have more influence on the outcome. In some examples, the weights may be predefined by an administrator or another entity. When a weight is predefined, the remote master control system may use that weight during analysis. Alternatively, some weights may be developed using analysis of the monitored conditions and performance at the datacenters over time.
When managing computational operations, the remote master control system 262 (or another system) may use a checkpoint system to increase efficiency associated with destruction. Particularly, a checkpoint system may enable efficient management of computational operations among one or more datacenters (e.g., the datacenters 1102-1106) based on one or more monitored conditions.
In addition, the compute system 1200 may also be in communication with a datacenter control system 1210. In some examples, the datacenter control system 1210 is part of the compute system 1200. For instance, the compute system 1200 may be implemented within a flexible datacenter that includes the datacenter control system 1210. In other examples, the datacenter control system 1210 is an external component in communication with the computing system 1200. For example, the datacenter control system 1210 may be a remote master control system (e.g., the remote master control system 262). In further examples, the datacenter control system 1210 may represent multiple control systems in communication (e.g., a remote master control system and a datacenter control system of the datacenter).
The compute system 1200 may be configured to enable granular power ramping, which is particularly beneficial if functioning as a BTM load. Particularly, the two-stage set up involve a set of controllers (e.g., the controllers 1204-1208 may enable granular power ramping of computing systems and/or hash cards). In other examples, additional controllers may be used.
The set of controllers includes the set controller 1204 configured to control a first set of computing systems 1212 and the set controller 1206 configured to control a second set of computing systems 1214. The set controller 1204 is shown communicatively coupled via communication link 1216C to the computing systems 1220A, 1220B, 1220C, and 1220D. These computing systems 1220A-1220D make up the first set of computing systems 1212 of the group of computing systems 1202. The set controller 1206 is shown communicatively coupled via communication link 1216D to the computing systems 1220E, 1220F, 1220G, 1220H. These computing systems 1220E-1220H make up the second set of computing systems 1214 of the group of computing systems 1202.
In the example shown in
In addition, the number of sets and controllers can differ in other examples. For instance, a fourth and a fifth controllers may be included in a similar position as the first and set controller. In such an example, the fourth and fifth controllers may each control a set of computing systems (e.g., hash cards) based on instructions from the third controller (or another controller). Further, the example shown in
The controllers 1204-1208 are arranged in a two-stage configuration. The group controller 1208 may provide instructions to the set controllers 1204, 1206. The set controllers 1204, 1206 may control each set of computing systems 1212-1214, respectively, based on instructions received from the group controller 1208. This configuration may enable the group controller 1208 to collectively control at least some aspects of the group of computing systems 1202 indirectly via the set controllers 1204, 1206.
In some embodiments, the set controllers 1204, 1206 may be primary controllers within the compute system 1200. These controllers 1204-1206 may be primary controllers based on their direct connection and control of the computing systems 1220A-1220H. In addition, the group controller 1208 may be considered a secondary controller since the group controller's 1208 connection to the computing systems 1220A-1220H is indirect (i.e., through the set controllers 1204, 1206).
The set controller 1204 may be configured to control the first set of computing systems 1212 and the set controller 1206 may be configured to control the second set of computing systems 1214. Controlling a set of computing systems may involve controlling all the computing systems uniformly within the set or controlling computing systems individually, in subsets, or as the entire set. For instance, the set controller 1204 may ramp power consumption up or down at the first set of computing systems 1212 for one or more of the computing systems 1220A-1220D.
The set controller 1204 may also control other operating attributes of the computing systems 1220A-1220D in other ways. For instance, the first controller 1204 may cause one or more computing systems 1220A-1220D to switch to a lower power state or a full power state (i.e., adjust the amount of power consumed by each computing system). Adjusting the power consumption may modify the performance of a computing system in a way that reflects the change in power consumption. In addition, the first controller 1204 may control a boot up process for each computing system 1220A-1220D, which may involve booting up one or more computing systems 1220A-1220D at a particular time. The first controller 1204 may also control an operation frequency of the computing systems 1220A-1220D.
In some examples, the set controller 1204 may control a hash rate of one or more of the computing systems 1220A-1220D. For instance, the set controller 1204 increase and/or decrease the hash rate of one or more of the computing systems 1220A-1220D.
The set controller 1206 may control the second set of computing systems 1214 similar to how the set controller 1204 can control the first set of computing systems 1212. The control strategies used by the set controllers 1204-1206 may depend on instructions from the group controller 1208. Particularly, the group controller 1208 may provide control instructions to the first controller 1204 via the communication link 1216A and to the set controller 1206 via the communication link 1216B. With this configuration, the group controller 1208 may send instructions simultaneously to both the set controllers 1204-1206. The group controller 1208 may also send instructions only to the set controller 1204 or only to the set controller 1206 in some instances.
The group controller 1208 may determine instructions for the first and second controllers 1204-1206 based on communication with the datacenter control system 1210 via the communication link 1218. The communication may involve the datacenter control system 1210 providing instructions to the group controller 1208 based on one or more monitored conditions, such as the monitored conditions described above with respect to
In some examples, the group controller 1208 may be configured to instruct power consumption at the set controllers 1204-1206 and the computing systems associated with each set controller. For instance, the set controllers 1204-1206 may be configured to assign operations (e.g., hashing operations) on a per computing system basis (e.g., per hash card) while the group controller 1208 is unable to assign operations on a per computing basis. In another embodiment, the group controller 1208 may provide instructions to the set controllers 1204-1206 to adjust power consumption and the set controllers 1204-1206 may be configured to determine how to adjust power consumption across the computing systems as a result (e.g., adjust one or more of a frequency of operation, shut down one or more computing systems, adjust assignment of computational operations, etc.). The abilities of the set controllers 1204-1206 and the group controller 1208 to manipulate operations of computing systems and power consumption can vary within examples. As shown, some examples may involve the group controller 1208 providing high level instructions (e.g., adjust power consumption) to the set controllers 1204-1206 and the set controllers 1204-1206 making adjustments to the computing systems based on the high level instructions.
The position of the datacenter control system 1210 relative to the group controller 1208 may vary. In addition, in some examples, the datacenter control system 1210 and the group controller 1208 may be part of the same device. In some examples, the datacenter control system 1210 may be at the same location as the compute system 1200. For instance, the datacenter control system 1210 and the compute system 1200 may be part of the same flexible datacenter. The computing systems 1202 and potentially other components may use BTM power from a BTM power source to operate. Particularly, the group of computing systems 1202 may be used to granularly ramp power consumption up and down based on the availability of BTM power and/or other conditions. As such, the datacenter control system 1210 may provide instructions to the group controller 1208 to accomplish the power ramping.
In an embodiment, the datacenter control system 1210 may be a remote master control system (e.g., the remote master control system 262). In such a configuration, the datacenter control system 1210 may communicate with controllers at multiple datacenters in a similar position as the group controller 1208. As a result, the datacenter control system 1210 may provide instructions to control hash cards and/or computing systems positioned at the various datacenters.
In another embodiment, functions may be performed by a combination of one or more datacenter control systems (e.g., the datacenter control system 1210) and a remote master control system (e.g., the remote master control system 262). For instance, the remote master control system 262 may communicate with the datacenter control system 1210 such that the remote master control system 262 performs one or more operations remotely from the datacenter control system 1210 and the datacenter control system 1210 performs one or more operations such that operations of one or more computing systems 1220A-1220H is modified. For instance, the remote master control system 262 and the datacenter control system 1210 may determine granular ramping changes for the computing systems 1220A-1220H. As an example, the remote master control system 262 may monitor one or more conditions and responsively provide instructions to the datacenter control system 1210. In response to receiving the instructions, the datacenter control system 1210 may provide instructions to the group controller 1208.
In other embodiments, the set controllers 1304, 1306 may control different hash cards respectively. In addition, the controllers 1304, 1306 may control different numbers of hash cards in some examples (e.g., the first controller 1304 may control hash cards 1310A-1310D and the second controller 1306 may control hash cards 1310E and 1310F).
The hash cards 1310A-1310F and controllers 1304-1308 are shown positioned on a tray 1302. The tray 1302 may include one or more compartments for connection mechanisms (not shown) between the components of the hash system 1300. Alternatively, the communication links may be positioned on the same layer of the hash cards 1310A-1310F and the set controllers 1304-1308 as shown with communication links 1320-1326.
As shown in
In some embodiments, a flexible datacenter (e.g., the flexible datacenter 500 of
In some examples, the method 1400 may be performed with respect to computing systems rather than hash cards. In addition, the method 1400 may be performed using a combination of computing systems, hash cards, and/or other types of devices.
At step 1402, the method 1400 involves receiving behind-the-meter (“BTM”) power at a group of computing systems. Particularly, the group of computing systems may receive BTM power from a BTM power source (e.g., generation station 400). In some examples, the group of computing systems may include one or more hash cards.
In one embodiment, the BTM power source includes a generation station configured to generate utility-scale electrical power for supply to an electrical grid. In one embodiment, the group of computing systems is electrically connected to a generation station at a location behind a Point of Interconnection between the generation station and an electrical grid. In one embodiment, the BTM power received by the group of computing systems is electrical power produced by a generation station and transmitted to the group of computing systems behind the generation station's Point of Interconnection with an electrical grid.
In one embodiment, the group of computing systems is electrically connected to a generation station that is subject to metering by one or more utility-scale generation-side meter. Particularly, the BTM power received by the group of computing systems may not have passed through the one or more utility-scale generation-side meters. In one embodiment, the power received by the group of computing systems is received from a generation station that is subject to metering by one or more utility-scale generation-side meters. The BTM power received by the group of computing systems may not be metered by the one or more utility-scale generation-side meter.
In one embodiment, the group of computing systems is electrically connected to a generation station that supplies utility-scale power to a grid. The power supplied by the grid may be subject to Transmission and/or Distribution charges, and the BTM power received by the group of computing systems from the generation station may not be subject to Transmission and/or Distribution charges
At step 1404, the method 1400 involves controlling, by a first controller, a first set of computing systems of the group of computing systems. The first controller may control the first set of computing systems based on instructions from a third controller. For example, the set controller 1204 may control the first set of computing systems 1212 based on instructions from the group controller 1208 as shown in
Controlling the first set of hash cards may involve adjusting an operation frequency and/or hash rate of one or more computing systems of the first set of computing systems. Controlling the first set of computing systems may also involve adjusting power consumption rates at one or more computing systems. For instance, the first controller may cause one or more computing systems to ramp up or ramp down power consumption. In some examples, the first controller may switch the modes of the computing system (e.g., a low power mode and a high power mode). As such, the controls may be based on instructions from the third controller.
At step 1406, the method 1400 involves controlling, by a second controller, a second set of computing systems of the group of computing systems. The second controller may control the second set of computing systems based on instructions from the third controller. For example, the set controller 1206 may control the second set of computing systems 1214 based on instructions from the group controller 1208 as shown in
Controlling the second set of computing systems may involve adjusting an operation frequency and/or hash rate of one or more computing systems of the second set of computing systems. Controlling the second set of computing systems may also involve adjusting power consumption rates at one or more computing systems (e.g., hash cards). For instance, the second controller may cause one or more computing systems to ramp up or ramp down power consumption. In some examples, the second controller may switch the modes of one or more of the computing systems (e.g., a low power mode and a high power mode). As such, the controls may be based on instructions from the third controller.
In some examples, instructions for the computing systems may originate from a datacenter control system. Particularly, the datacenter control system may be configured to provide a directive (e.g., instructions) to the third controller based on a set of monitored conditions. The set of monitored conditions can include an availability of BTM power at the computing systems. In addition, the monitored conditions may also include one or more of prices for power from one or more sources at one or more datacenters, current prices of cryptocurrencies, parameters related to the computing systems (e.g., abilities, availability), parameters related to computational operations (e.g., quantity, deadlines and other time constraints, entities that submitted the computational operations, and priorities), and weather-related conditions, among other possible conditions. In some examples, the datacenter control system is a remote master control system positioned remotely from the group of computing systems.
In additional embodiments, the datacenter control system may be positioned at a flexible datacenter housing the group of computing systems. As such, the datacenter control system may communicate with a remote master control system. As a result, a combination of the datacenter control system and the remote master control system may determine a control strategy for the group of computing systems and provide the control strategy to the third controller. For instance, the remote master control system may provide a general control strategy (e.g., ramp up power consumption) to the datacenter control system, which may in turn determine which computing systems to ramp up power consumption based on the general control strategy.
In some examples, the method 1400 may further involve receiving, at the third controller, a directive to ramp up power consumption (or ramp down power consumption) at half of the group of computing systems. For instance, the third party controller may receive the directive from a datacenter control system. The method 1400 may also involve providing, by the third controller, instructions to ramp up power consumption (or ramp down power consumption) to either the first controller or the second controller.
In addition, other computing systems or control systems (e.g., the remote master control system 262) may perform one or more steps of the method 1500. In some examples, the compute system may communicate with one or more external sources when performing one or more steps of the method 1500. For instance, the compute system may communicate with a datacenter control system (e.g., a remote master control system) when performing the method 1500. In some examples, the method 1500 may be performed with respect to one or more hash cards. The method 1500 may be performed using a combination of computing systems and hash cards.
At block 1502, the method 1500 may involve receiving, at a secondary controller, a directive for controlling a group of computing systems. The group of computing systems may receive BTM power from a BTM power source when BTM power is available. In some examples, the secondary controller may be the third controller 1208 shown in
At block 1504, the method 1500 may involve providing, by the secondary controller, instructions to: (i) a first primary controller configured to control a first set of computing systems of the group of computing systems and (ii) a second primary controller configured to control a second set of computing systems of the group of computing systems. The secondary controller may provide the instructions based on the directive received at block 1502.
In some examples, the method 1500 may receiving the directive from a remote master control system positioned remotely from the secondary controller. For instance, the remote master control system may monitor a set of conditions and determine the directive for the secondary controller based on the monitored conditions.
Advantages of one or more embodiments of the present invention may include one or more of the following:
One or more embodiments of the present invention provides a green solution to two prominent problems: the exponential increase in power required for growing blockchain operations and the unutilized and typically wasted energy generated from renewable energy sources.
One or more embodiments of the present invention allows for the rapid deployment of mobile datacenters to local stations. The mobile datacenters may be deployed on site, near the source of power generation, and receive low cost or unutilized power behind-the-meter when it is available.
One or more embodiments of the present invention provide the use of a queue system to organize computational operations and enable efficient distribution of the computational operations across multiple datacenters.
One or more embodiments of the present invention enable datacenters to access and obtain computational operations organized by a queue system.
One or more embodiments of the present invention allows for the power delivery to the datacenter to be modulated based on conditions or an operational directive received from the local station or the grid operator.
One or more embodiments of the present invention may dynamically adjust power consumption by ramping-up, ramping-down, or adjusting the power consumption of one or more computing systems within the flexible datacenter.
One or more embodiments of the present invention may be powered by behind-the-meter power that is free from transmission and distribution costs. As such, the flexible datacenter may perform computational operations, such as distributed computing processes, with little to no energy cost.
One or more embodiments of the present invention provides a number of benefits to the hosting local station. The local station may use the flexible datacenter to adjust a load, provide a power factor correction, to offload power, or operate in a manner that invokes a production tax credit and/or generates incremental revenue.
One or more embodiments of the present invention allows for continued shunting of behind-the-meter power into a storage solution when a flexible datacenter cannot fully utilize excess generated behind-the-meter power.
One or more embodiments of the present invention allows for continued use of stored behind-the-meter power when a flexible datacenter can be operational but there is not an excess of generated behind-the-meter power.
One or more embodiments of the present invention allows for management and distribution of computational operations at computing systems across a fleet of datacenters such that the performance of the computational operations take advantages of increased efficiency and decreased costs.
It will also be recognized by the skilled worker that, in addition to improved efficiencies in controlling power delivery from intermittent generation sources, such as wind farms and solar panel arrays, to regulated power grids, the invention provides more economically efficient control and stability of such power grids in the implementation of the technical features as set forth herein.
While the present invention has been described with respect to the above-noted embodiments, those skilled in the art, having the benefit of this disclosure, will recognize that other embodiments may be devised that are within the scope of the invention as disclosed herein. Accordingly, the scope of the invention should be limited only by the appended claims.
Claims
1. A system comprising:
- a plurality of computing systems, wherein the plurality of computing systems receive behind-the-meter (“BTM”) power from a BTM power source;
- a first controller configured to granularly control a first set of computing systems of the plurality of computing systems;
- a second controller configured to granularly control a second set of computing systems of the plurality of computing systems; and
- a third controller communicatively coupled to the first controller and the second controller, wherein the third controller is configured to provide instructions to the first controller and the second controller based on BTM power availability at the plurality of computing systems.
2. (canceled)
3. The system of claim 1, wherein the plurality of computing systems is electrically connected to a generation station at a location behind a Point of Interconnection between the generation station and an electrical grid.
4. The system of claim 1, wherein the BTM power received by the plurality of computing systems is electrical power produced by a generation station and transmitted to the plurality of computing systems behind the generation station's Point of Interconnection with an electrical grid.
5. The system of claim 1, wherein the plurality of computing systems is electrically connected to a generation station that is subject to metering by one or more utility-scale generation-side meter, wherein the BTM power received by the plurality of computing systems has not passed through the one or more utility-scale generation-side meters.
6. The system of claim 1, wherein the power received by the plurality of computing systems is received from a generation station that is subject to metering by one or more utility-scale generation-side meters, and wherein the BTM power received by the plurality of computing systems is not metered by the one or more utility-scale generation-side meters.
7. The system of claim 1, wherein the plurality of computing systems is electrically connected to a generation station that supplies utility-scale power to a grid, wherein power supplied by the grid is subject to Transmission and/or Distribution charges, and wherein the BTM power received by the plurality of computing systems from the generation station is not subject to Transmission and/or Distribution charges.
8. The system of claim 1, further comprising:
- a datacenter control system, wherein the datacenter control system is configured to provide a directive to the third controller based on a set of monitored conditions.
9. The system of claim 8, wherein the set of monitored conditions includes operating attributes of each computing system of the plurality of computing systems.
10. The system of claim 9, wherein the set of monitored conditions includes a time constraint associated with completing a computational operation using one or more computing systems of the plurality of computing systems.
11. The system of claim 8, wherein the datacenter control system is a remote master control system located remotely from the plurality of computing systems.
12. The system of claim 11, wherein the directive specifies to ramp power consumption up at the plurality of computing systems; and
- wherein the third controller is configured to: receive the directive; and direct the first controller to ramp power consumption up at the first set of computing systems and the second controller to ramp power consumption up at the second set of computing systems based on the directive.
13. The system of claim 11, wherein the directive specifies to ramp power consumption down at the plurality of computing systems; and
- wherein the third controller is configured to: receive the directive; and direct the first controller to ramp power consumption down at the first set of computing systems and the second controller to ramp power consumption down at the second set of computing systems based on the directive.
14. The system of claim 11, wherein the directive specifies to ramp power consumption down at the first set of computing systems; and
- wherein the third controller is configured to: receive the directive; and direct the first controller to ramp power consumption down at the first set of computing systems based on the directive.
15. The system of claim 1, wherein the first controller is configured to cause the first set of computing systems to increase power consumption or decrease power consumption based on instructions from the third controller, and
- wherein the second controller is configured to cause the second set of computing systems to increase power consumption or decrease power consumption based on instructions from the third controller.
16. The system of claim 1, wherein the first controller is configured to cause the first set of computing systems to switch to a low power state or a full power state based on instructions from the third controller, and
- wherein the second controller is configured to cause the second set of computing systems to switch to a lower power state or a full power state based on instructions from the third controller.
17. The system of claim 1, wherein the first controller controls a boot up process of each computing system of the first set of computing systems based on instructions from the third controller, and
- wherein the second controller controls a boot up process of each computing system of the second set of computing systems based on instructions from the third controller.
18. The system of claim 1, wherein the first controller controls an operation frequency of each computing system of the first set of computing systems, and
- wherein the second controller controls an operation frequency of each computing system of the second set of computing systems.
19. The system of claim 1, wherein the plurality of computing systems corresponds to a plurality of hash cards,
- wherein the first controller controls a hash function rate of each hash card of the first set of computing systems, and
- wherein the second controller controls a hash function rate of each hash card of the second set of computing systems.
20. A method comprising:
- receiving behind-the-meter (“BTM”) power at a plurality of computing systems, wherein the plurality of computing systems receive BTM power from a BTM power source;
- granularly controlling, by a first controller, a first set of computing systems of the plurality of computing systems based on first instructions from a third controller, wherein controlling the first set of computing systems includes adjusting power consumption by the first set of computing systems based on the first instructions from the third controller; and
- granularly controlling, by a second controller, a second set of computing systems of the plurality of computing systems based on second instructions from the third controller, wherein controlling the second set of computing systems includes adjusting power consumption by the second set of computing systems based on the second instructions from the third controller, wherein the third controller is configured to provide respective instructions to the first controller and the second controller based on BTM power availability at the plurality of computing systems.
21. The method of claim 20, wherein the BTM power source comprises a generation station configured to generate utility-scale electrical power for supply to an electrical grid.
22. The method of claim 20, wherein the plurality of computing systems is electrically connected to a generation station at a location behind a Point of Interconnection between the generation station and an electrical grid.
23. The method of claim 20, wherein the BTM power received by the plurality of computing systems is electrical power produced by a generation station and transmitted to the plurality of computing systems behind the generation station's Point of Interconnection with an electrical grid.
24. The method of claim 20, wherein the plurality of computing systems is electrically connected to a generation station that is subject to metering by one or more utility-scale generation-side meter, wherein the BTM power received by the plurality of computing systems has not passed through the one or more utility-scale generation-side meters.
25. The method of claim 20, wherein the power received by the plurality of computing systems is received from a generation station that is subject to metering by one or more utility-scale generation-side meters, and wherein the BTM power received by the plurality of computing systems is not metered by the one or more utility-scale generation-side meter.
26. The method of claim 20, wherein the plurality of computing systems is electrically connected to a generation station that supplies utility-scale power to a grid, wherein power supplied by the grid is subject to Transmission and/or Distribution charges, and wherein the BTM power received by the plurality of computing systems from the generation station is not subject to Transmission and/or Distribution charges.
27. The method of claim 20, further comprising:
- receiving, at the third controller, a directive to ramp up power consumption at half of the plurality of computing systems, wherein the third controller receives the directive from a datacenter control system; and
- providing, by the third controller, instructions to ramp up power consumption to either the first controller or the second controller.
28. The method of claim 20, wherein controlling, by the first controller, the first set of computing systems of the plurality of computing systems comprises:
- adjusting an operation frequency of one or more computing systems of the first set of computing systems.
29. A method comprising:
- receiving, at a secondary controller, a directive for controlling power consumption by a plurality of computing systems, wherein the plurality of computing systems receive behind-the-meter (“BTM”) power from a BTM power source, and wherein the directive depends on BTM power availability at the plurality of computing systems; and
- based on the directive, providing, by the secondary controller, instructions to: (i) a first primary controller configured to granularly control a first set of computing systems of the plurality of computing systems and (ii) a second primary controller configured to granularly control a second set of computing systems of the plurality of computing systems.
30. The method of claim 29, wherein receiving, at the secondary controller, the directive for controlling the plurality of computing systems comprises:
- receiving the directive from a remote master control system positioned remotely from the secondary controller, wherein the directive depends on a set of monitored conditions.
31. The method of claim 1 wherein the BTM power source includes a generation station configured to generate utility-scale electrical power for supply to an electrical grid.
Type: Application
Filed: Aug 1, 2019
Publication Date: Feb 4, 2021
Patent Grant number: 11868106
Inventors: Michael T. McNamara (Newport Beach, CA), Raymond E. Cline, JR. (Houston, TX)
Application Number: 16/529,360