METHODS AND SYSTEMS FOR ADJUSTING POWER CONSUMPTION BASED ON A DYNAMIC POWER OPTION AGREEMENT
Examples relate to adjusting load power consumption based on a power option agreement. A computing system may receive power option data that is based on a power option agreement and specify minimum power thresholds associated with time intervals. The computing system may determine a performance strategy for a load (e.g., set of computing systems) based on a combination of the power option data and one or more monitored conditions. The performance strategy may specify a power consumption target for the load for each time interval such that each power consumption target is equal to or greater than the minimum power threshold associated with each time interval. The computing system may provide instructions the set of computing systems to perform one or more computational operations based on the performance strategy.
The present application is a Continuation of copending U.S. application Ser. No. 17/328,337, filed May 24, 2021, which will issue as U.S. Pat. No. 11,581,734 on Feb. 14, 2023, which is a Continuation of copending U.S. application Ser. No. 16/702,894, filed Dec. 4, 2019, which issued as U.S. Pat. No. 11,016,458 on May 25, 2021, which claims priority to U.S. Provisional Patent Application No. 62/927,119, filed Oct. 28, 2019. The disclosures set forth in the referenced applications are incorporated herein by reference in their entireties.
FIELDThis specification relates to power consumption adjustments when using grid power and/or intermittent behind-the-meter power.
BACKGROUND“Electrical grid” or “grid,” as used herein, refers to a Wide Area Synchronous Grid (also known as an Interconnection), and is a regional scale or greater electric power grid that that operates at a synchronized frequency and is electrically tied together during normal system conditions. An electrical grid delivers electricity from generation stations to consumers. An electrical grid includes: (i) generation stations that produce electrical power at large scales for delivery through the grid, (ii) high voltage transmission lines that carry that power from the generation stations to demand centers, and (iii) distribution networks carry that power to individual customers.
A generation segment 102 includes one or more generation stations that produce utility-scale electricity (typically >50 MW), such as a nuclear plant 102a, a coal plant 102b, a wind power station (i.e., wind farm) 102c, and/or a photovoltaic power station (i.e., a solar farm) 102d. Generation stations are differentiated from building-mounted and other decentralized or local wind or solar power applications because they supply power at the utility level and scale (>50 MW), rather than to a local user or users. The primary purpose of generation stations is to produce power for distribution through the grid, and in exchange for payment for the supplied electricity. Each of the generation stations 102a-d includes power generation equipment 102e-h, respectively, typically capable of supply utility-scale power (>50 MW). For example, the power generation equipment 102g at wind power station 102c includes wind turbines, and the power generation equipment 102h at photovoltaic power station 102d includes photovoltaic panels.
Each of the generation stations 102a-d may further include station electrical equipment 102i-1 respectively. Station electrical equipment 102i-1 are each illustrated in
Each generation station 102a-d may produce AC or DC electrical current which is then typically stepped up to a higher AC voltage before leaving the respective generation station. For example, wind turbines may typically produce AC electrical energy at 600V to 700V, which may then be stepped up to 34.5 kV before leaving the generation station 102d. In some cases, the voltage may be stepped up multiple times and to a different voltage before exiting the generation station 102c. As another example, photovoltaic arrays may produce DC voltage at 600V to 900V, which is then inverted to AC voltage and may be stepped up to 34.5 kV before leaving the generation station 102d. In some cases, the voltage may be stepped up multiple times and to a different voltage before exiting the generation station 102d.
Upon exiting the generation segment 102, electrical power generated at generation stations 102a-d passes through a respective Point of Interconnection (“POI”) 103 between a generation station (e.g., 102a-d) and the rest of the grid. A respective POI 103 represents the point of connection between a generation station's (e.g. 102a-d) equipment and a transmission system (e.g., transmission segment 104) associated with electrical grid. In some cases, at the POI 103, generated power from generation stations 102a-d may be stepped up at transformer systems 103e-h to high voltage scales suitable for long-distance transmission along transmission lines 104a. Typically, the generated electrical energy leaving the POI 103 will be at 115 kV AC or above, but in some cases it may be as low as, for example, 69 kV for shorter distance transmissions along transmission lines 104a. Each of transformer systems 103e-h may be a single transformer or may be multiple transformers operating in parallel or series and may be co-located or located in geographically distinct locations. Each of the transformer systems 103e-h may include substations and other links between the generation stations 102a-d and the transmission lines 104a.
A key aspect of the POI 103 is that this is where generation-side metering occurs. One or more utility-scale generation-side meters 103a-d (e.g., settlement meters) are located at settlement metering points at the respective POI 103 for each generation station 102a-d. The utility-scale generation-side meters 103a-d measure power supplied from generation stations 102a-d into the transmission segment 104 for eventual distribution throughout the grid.
For electricity consumption, the price consumers pay for power distributed through electric power grids is typically composed of, among other costs, Generation, Administration, and Transmission & Distribution (“T&D”) costs. T&D costs represent a significant portion of the overall price paid by consumers for electricity. These costs include capital costs (land, equipment, substations, wire, etc.), costs associated with electrical transmission losses, and operation and maintenance costs.
For utility-scale electricity supply, operators of generation stations (e.g., 102a-d) are paid a variable market price for the amount of power the operator generates and provides to the grid, which is typically determined via a power purchase agreement (PPA) between the generation station operator and a grid operator. The amount of power the generation station operator generates and provides to the grid is measured by utility-scale generation-side meters (e.g., 103a-d) at settlement metering points. As illustrated in
After passing through the utility-scale generation-side meters in the POI 103, the power originally generated at the generation stations 102a-d is transmitted onto and along the transmission lines 104a in the transmission segment 104. Typically, the electrical energy is transmitted as AC at 115 kV+ or above, though it may be as low as 69 kV for short transmission distances. In some cases, the transmission segment 104 may include further power conversions to aid in efficiency or stability. For example, transmission segment 104 may include high-voltage DC (“HVDC”) portions (along with conversion equipment) to aid in frequency synchronization across portions of the transmission segment 104. As another example, transmission segment 104 may include transformers to step AC voltage up and then back down to aid in long distance transmission (e.g., 230 kV, 500 kV, 765 kV, etc.).
Power generated at the generation stations 104a-d is ultimately destined for use by consumers connected to the grid. Once the energy has been transmitted along the transmission segment 104, the voltage will be stepped down by transformer systems 105a-c in the step down segment 105 so that it can move into the distribution segment 106.
In the distribution segment 106, distribution networks 106a-c take power that has been stepped down from the transmission lines 104a and distribute it to local customers, such as local sub-grids (illustrated at 106a), industrial customers, including large EV charging networks (illustrated at 106b), and/or residential and retail customers, including individual EV charging stations (illustrated at 106c). Customer meters 106d, 106f measure the power used by each of the grid-connected customers in distribution networks 106a-c. Customer meters 106d are typically load meters that are unidirectional and measure power use. Some of the local customers in the distribution networks 106a-d may have local wind or solar power systems 106e owned by the customer. As discussed above, these local customer power systems 106e are decentralized and supply power directly to the customer(s). Customers with decentralized wind or solar power systems 106e may have customer meters 106f that are bidirectional or net-metering meters that can track when the local customer power systems 106e produce power in excess of the customer's use, thereby allowing the utility to provide a credit to the customer's monthly electricity bill. Customer meters 106d, 106f differ from utility-scale generation-side meters (e.g., settlement meters) in at least the following characteristics: design (electro-mechanical or electronic vs current transformer), scale (typically less than 1600 amps vs. typically greater than 50 MW; typically less than 600V vs. typically greater than 14 kV), primary function (use vs. supply metering), economic purpose (credit against use vs payment for power), and location (in a distribution network at point of use vs. at a settlement metering point at a Point of Interconnection between a generation station and a transmission line).
To maintain stability of the grid, the grid operator strives to maintain a balance between the amount of power entering the grid from generation stations (e.g., 102a-d) and the amount of grid power used by loads (e.g., customers in the distribution segment 106). In order to maintain grid stability and manage congestion, grid operators may take steps to reduce the supply of power arriving from generation stations (e.g., 102a-d) when necessary (e.g., curtailment). Particularly, grid operators may decrease the market price paid for generated power to dis-incentivize generation stations (e.g., 102a-d) from generating and supplying power to the grid. In some cases, the market price may even go negative such that generation station operators must pay for power they allow into the grid. In addition, some situations may arise where grid operators explicitly direct a generation station (e.g., 102a-d) to reduce or stop the amount of power the station is supplying to the grid.
Power market fluctuations, power system conditions (e.g., power factor fluctuation or generation station startup and testing), and operational directives resulting in reduced or discontinued generation all can have disparate effects on renewal energy generators and can occur multiple times in a day and last for indeterminate periods of time. Curtailment, in particular, is particularly problematic.
According to the National Renewable Energy Laboratory's Technical Report TP-6A20-60983 (March 2014):
-
- [C]urtailment [is] a reduction in the output of a generator from what it could otherwise produce given available resources (e.g., wind or sunlight), typically on an involuntary basis. Curtailments can result when operators or utilities command wind and solar generators to reduce output to minimize transmission congestion or otherwise manage the system or achieve the optimal mix of resources. Curtailment of wind and solar resources typically occurs because of transmission congestion or lack of transmission access, but it can also occur for reasons such as excess generation during low load periods that could cause baseload generators to reach minimum generation thresholds, because of voltage or interconnection issues, or to maintain frequency requirements, particularly for small, isolated grids. Curtailment is one among many tools to maintain system energy balance, which can also include grid capacity, hydropower and thermal generation, demand response, storage, and institutional changes. Deciding which method to use is primarily a matter of economics and operational practice.
- “Curtailment” today does not necessarily mean what it did in the early 2000s. Two separate changes in the electric sector have shaped curtailment practices since that time: the utility-scale deployment of wind power, which has no fuel cost, and the evolution of wholesale power markets. These simultaneous changes have led to new operational challenges but have also expanded the array of market-based tools for addressing them.
- Practices vary significantly by region and market design. In places with centrally-organized wholesale power markets and experience with wind power, manual wind energy curtailment processes are increasingly being replaced by transparent offer-based market mechanisms that base dispatch on economics. Market protocols that dispatch generation based on economics can also result in renewable energy plants generating less than what they could potentially produce with available wind or sunlight. This is often referred to by grid operators by other terms, such as “downward dispatch.” In places served primarily by vertically integrated utilities, power purchase agreements (PPAs) between the utility and the wind developer increasingly contain financial provisions for curtailment contingencies.
- ****
- Some reductions in output are determined by how a wind operator values dispatch versus non-dispatch. Other curtailments of wind are determined by the grid operator in response to potential reliability events. Still other curtailments result from overdevelopment of wind power in transmission-constrained areas.
- Dispatch below maximum output (curtailment) can be more of an issue for wind and solar generators than it is for fossil generation units because of differences in their cost structures. The economics of wind and solar generation depend on the ability to generate electricity whenever there is sufficient sunlight or wind to power their facilities.
- Because wind and solar generators have substantial capital costs but no fuel costs (i.e., minimal variable costs), maximizing output improves their ability to recover capital costs. In contrast, fossil generators have higher variable costs, such as fuel costs. Avoiding these costs can, depending on the economics of a specific generator, to some degree reduce the financial impact of curtailment, especially if the generator's capital costs are included in a utility's rate base.
Curtailment may result in available energy being wasted because solar and wind operators have zero variable cost (which may not be true to the same extent for fossil generation units which can simply reduce the amount of fuel that is being used). With wind generation, in particular, it may also take some time for a wind farm to become fully operational following curtailment. As such, until the time that the wind farm is fully operational, the wind farm may not be operating with optimum efficiency and/or may not be able to provide power to the grid.
SUMMARYIn an example, a system includes a set of computing systems. The set of computing systems is configured to perform computational operations using power from a power grid. The system also includes a control system configured to monitor a set of conditions and, while monitoring the set of conditions, receive first power option data based, at least in part, on a power option agreement. The first power option data specify a first minimum power threshold associated with a first time interval. The control system is further configured to provide first control instructions for the set of computing systems based on a combination of at least a portion of the first power option data and at least one condition of the set of conditions responsive to receiving the first power option data. The first control instructions comprises a first power consumption target for the set of computing systems for the first time interval, and the first power consumption target is equal to or greater than the first minimum power threshold associated with the first time interval. The control system is also configured to, while monitoring the set of conditions, receive second power option data based, at least in part, on the power option agreement. The second power option data specify a second minimum power threshold associated with a second time interval. Responsive to receiving the second power option data, the control system is configured to provide second control instructions for the set of computing systems based on a combination of at least a portion of the second power data and at least one condition of the set of conditions. The second control instructions comprises a second power consumption target for the set of computing systems for the second time interval, and wherein the second power consumption target is equal to or greater than the second minimum power threshold associated with the second time interval.
In another example, a method involves monitoring, at a computing system, a set of conditions, and while monitoring the set of conditions, receiving first power option data based, at least in part, on a power option agreement. The first power option data specify a first minimum power threshold associated with a first time interval. The method further involves, responsive to receiving the first power option data, providing first control instructions for a set of computing systems based on a combination of at least a portion of the first power option data and at least one condition of the set of conditions. The first control instructions comprises a first power consumption target for the set of computing systems for the first time interval, and the first power consumption target is equal to or greater than the first minimum power threshold associated with the first time interval. The method further involves, while monitoring the set of conditions, receiving second power option data based, at least in part, on the power option agreement. The second power option data specify a second minimum power threshold associated with a second time interval. The method also involves, responsive to receiving the second power option data, providing second control instructions for the set of computing systems based on a combination of at least a portion of the second power data and at least one condition of the set of conditions. The second control instructions comprises a second power consumption target for the set of computing systems for the second time interval, and the second power consumption target is equal to or greater than the second minimum power threshold associated with the second time interval.
In yet another example, a system is provided. The system includes a set of computing systems, where the set of computing systems is configured to perform computational operations using power from a power grid. The system also includes a control system configured to monitor a set of conditions and receive power option data based, at least in part, on a power option agreement. The power option data specify: (i) a set of minimum power thresholds, and (ii) a set of time intervals, where each minimum power threshold in the set of minimum power thresholds is associated with a time interval in the set of time intervals. The control system is further configured to, responsive to receiving the power option data, determine a performance strategy for the set of computing systems based on a combination of at least a portion of the power option data and at least one condition in the set of conditions. The performance strategy comprises a power consumption target for the set of computing systems for each time interval in the set of time intervals, where each power consumption target is equal to or greater than the minimum power threshold associated with each time interval. The control system is also configured to provide instructions to the set of computing systems to perform one or more computational operations based on the performance strategy.
In a further example, non-transitory computer-readable medium is described that is configured to store instructions, that when executed by a computing system, causes the computing system to perform operations consistent with the method steps described above.
Other aspects of the present invention will be apparent from the following description and claims.
Disclosed examples will now be described more fully hereinafter with reference to the accompanying drawings, in which some, but not all of the disclosed examples are shown. Different examples may be described and should not be construed as limited to the examples set forth herein.
As discussed above, the market price paid to generation stations for supplying power to the grid often fluctuates due to various factors, including the need to maintain grid stability and based on current demand and usage by connected loads in distribution networks. Due to these factors, situations can arise where generation stations are offered substantially lower prices to deter an over-supply of power to the grid. Although these situations typically exist temporarily, generation stations are sometimes forced to either sell power to the grid at the much lower prices or adjust operations to decrease the amount of power generated. Furthermore, some situations may even require generation stations to incur costs in order to offload power to the grid or to shut down generation temporarily.
The volatility in the market price offered for power supplied to the grid can be especially problematic for some types of generation stations. In particular, wind farms and some other types of renewable resource power producers may lack the ability to quickly adjust operations in response to changes in the market price offered for supplying power to the grid. As a result, power generation and management at some generation stations can be inefficient, which can frequently result in power being sold to the grid at low or negative prices. In some situations, a generation station may even opt to halt power generation temporarily to avoid such unfavorable pricing. As such, the time required to halt and to restart the power generation at a generation station can reduce the generation station's ability to take advantage of rising market prices for power supplied to the grid.
Example embodiments provided herein aim to assist generation stations in managing power generation operations and avoid unfavorable power pricing situations like those described above. In particular, example embodiments may involve providing a load that is positioned behind-the-meter (“BTM”) and enabling the load to utilize power received behind-the-meter at a generation station in a timely manner. As a general rule of thumb, BTM power is not subject to traditional T&D costs.
For purposes herein, a generation station is considered to be configured for the primary purpose of generating utility-scale power for supply to the electrical grid (e.g., a Wide Area Synchronous Grid or a North American Interconnect).
In one embodiment, equipment located behind-the-meter (“BTM equipment”) is equipment that is electrically connected to a generation station's power generation equipment behind (i.e., prior to) the generation station's POI with an electrical grid.
In one embodiment, behind-the-meter power (“BTM power”) is electrical power produced by a generation station's power generation equipment and utilized behind (i.e., prior to) the generation station's POI with an electrical grid.
In another embodiment, equipment may be considered behind-the-meter if it is electrically connected to a generation station that is subject to metering by a utility-scale generation-side meter (e.g., settlement meter), and the BTM equipment receives power from the generation station, but the power received by the BTM equipment from the generation station has not passed through the utility-scale generation-side meter. In one embodiment, the utility-scale generation-side meter for the generation station is located at the generation station's POI. In another embodiment, the utility-scale generation-side meter for the generation station is at a location other than the POI for the generation station—for example, a substation between the generation station and the generation station's POI.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station that is subject to metering by a utility-scale generation-side meter (e.g., settlement meter), and the BTM power is utilized before being metered at the utility-scale generation-side meter. In one embodiment, the utility-scale generation-side meter for the generation station is located at the generation station's POI. In another embodiment, the utility-scale generation-side meter for the generation station is at a location other than the POI for the generation station—for example, a substation between the generation station and the generation station's POI.
In another embodiment, equipment may be considered behind-the-meter if it is electrically connected to a generation station that supplies power to a grid, and the BTM equipment receives power from the generation station that is not subject to T&D charges, but power received from the grid that is supplied by the generation station is subject to T&D charges.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station that supplies power to a grid, and the BTM power is not subject to T&D charges before being used by electrical equipment, but power received from the grid that is supplied by the generation station is subject to T&D charges.
In another embodiment, equipment may be considered behind-the-meter if the BTM equipment receives power generated from the generation station and that received power is not routed through the electrical grid before being delivered to the BTM equipment.
In another embodiment, power may be considered behind-the-meter if it is electrical power produced at a generation station, and BTM equipment receives that generated power, and that generated power received by the BTM equipment is not routed through the electrical grid before being delivered to the BTM equipment.
For purposes herein, BTM equipment may also be referred to as a behind-the-meter load (“BTM load”) when the BTM equipment is actively consuming BTM power.
Beneficially, where BTM power is not subject to traditional T&D costs, a wind farm or other type of generation station can be connected to BTM loads which can allow the generation station to selectively avoid the adverse or less-than optimal cost structure occasionally associated with supplying power to the grid by shunting generated power to the BTM load.
An arrangement that positions and connects a BTM load to a generation station can offer several advantages. In such arrangements, the generation station may selectively choose whether to supply power to the grid or to the BTM load, or both. The operator of a BTM load may pay to utilize BTM power at a cost less than that charged through a consumer meter (e.g., 106d, 106f) located at a distribution network (e.g., 106a-c) receiving power from the grid. The operator of a BTM load may additionally or alternatively charge less than the market rate to consume excess power generated at the generation station during curtailment. As a result, the generation station may direct generated power based on the “best” price that the generation station can receive during a given time frame, and/or the lowest cost the generation station may incur from negative market pricing during curtailment. The “best” price may be the highest price that the generation station may receive for its generated power during a given duration, but can also differ within embodiments and may depend on various factors, such as a prior PPA.
In one example, by having a behind-the-meter option available, a generation station may transition from supplying all generated power to the grid to supplying some or all generated power to one or more BTM loads when the market price paid for power by grid operators drops below a predefined threshold (e.g., the price that the operator of the BTM load is willing to pay the generation station for power). Thus, by having an alternative option for power consumption (i.e., one or more BTM loads), the generation station can selectively utilize the different options to maximize the price received for generated power. In addition, the generation station may also utilize a BTM load to avoid or reduce the economic impact in situations when supplying power to the grid would result in the generation station incurring a net cost.
Providing BTM power to a load can also benefit the BTM load operator. A BTM load may be able to receive and utilize BTM power received from the generation station at a cost that is lower than the cost for power from the grid (e.g., at a customer meter 106d, 106f). This is primarily due to the avoidance (or significant reduction) in T&D costs and the market effects of curtailment. As indicated above, the generation station may be willing to divert generated power to the BTM load rather than supplying the grid due to changing market conditions, or during maintenance periods, or for other non-market conditions. Thus, some situations may arise where the generation station offers power to the BTM load at a price that is substantially lower than the price available on the grid. Furthermore, in some situations, the BTM load may even be able to obtain and utilize BTM power from a generation station at no cost or even at negative pricing since the generation station may rather supply the BTM load with generated power during a given time range instead of paying a higher price for the grid to take the power or modifying operations to decrease power output.
Another example of cost-effective use of BTM power is when the generation station 202 is selling power to the grid at a negative price that is offset by a production tax credit. In certain circumstances, the value of the production tax credit may exceed the price the generation station 202 would have to pay to the grid power to offload generation's station 202 generated power. Advantageously, one or more flexible datacenters 220 may take the generated power behind-the-meter, thereby allowing the generation station 202 to produce and obtain the production tax credit, while selling less power to the grid at the negative price.
Another example of cost-effective behind-the-meter power is when the generation station 202 is selling power to the grid at a negative price because the grid is oversupplied and/or the generation station 202 is instructed to stand down and stop producing altogether. A grid operator may select and direct certain generation stations to go offline and stop supplying power to the grid. Advantageously, one or more flexible datacenters may be used to take power behind-the-meter, thereby allowing the generation station 202 to stop supplying power to the grid, but still stay online and make productive use of the power generated.
Another example of beneficial behind-the-meter power use is when the generation station 202 is producing power that is, with reference to the grid, unstable, out of phase, or at the wrong frequency, or the grid is already unstable, out of phase, or at the wrong frequency. A grid operator may select certain generation stations to go either offline and stop producing power, or to take corrective action with respect to the grid power stability, phase, or frequency. Advantageously, one or more flexible datacenters 220 may be used to selectively consume power behind-the-meter, thereby allowing the generation station 202 to stop providing power to the grid and/or provide corrective feedback to the grid.
Another example of beneficial behind-the-meter power use is that cost-effective behind-the-meter power availability may occur when the generation station 202 is starting up or testing. Individual equipment in the power generation equipment 210 may be routinely offline for installation, maintenance, and/or service and the individual units must be tested prior to coming online as part of overall power generation equipment 210. During such testing or maintenance time, one or more flexible datacenters may be intermittently powered by the one or more units of the power generation equipment 210 that are offline from the overall power generation equipment 210.
Another example of beneficial behind-the-meter power use is that datacenter control systems at the flexible datacenters 220 may quickly ramp up and ramp down power consumption by computing systems in the flexible datacenters 220 based on power availability from the generation station 202. For instance, if the grid requires additional power and signals the demand via a higher local price for power, the generation station 202 can supply the grid with power nearly instantly by having active flexible datacenters 220 quickly ramp down and turn off computing systems (or switch to a stored energy source), thereby reducing an active BTM load.
Another example of beneficial behind-the-meter power use is in new photovoltaic generation stations 202. For example, it is common to design and build new photovoltaic generation stations with a surplus of power capacity to account for degradation in efficiency of the photovoltaic panels over the life of the generation stations. Excess power availability at the generation station can occur when there is excess local power generation and/or low grid demand. In high incident sunlight situations, a photovoltaic generation station 202 may generate more power than the intended capacity of generation station 202. In such situations, a photovoltaic generation station 202 may have to take steps to protect its equipment from damage, which may include taking one or more photovoltaic panels offline or shunting their voltage to dummy loads or the ground. Advantageously, one or more flexible datacenters (e.g., the flexible datacenters 220) may take power behind-the-meter at the Generations Station 202, thereby allowing the generation station 202 to operate the power generation equipment 210 within operating ranges while the flexible datacenters 220 receive BTM power without transmission or distribution costs.
Thus, for at least the reasons described herein, arrangements that involves providing a BTM load as an alternative option for a generation station to direct its generated power to can serve as a mutually beneficial relationship in which both the generation station and the BTM load can economically benefit. The above-noted examples of beneficial use of BTM power are merely exemplary and are not intended to limit the scope of what one of ordinary skill in the art would recognize as benefits to unutilized BTM power capacity, BTM power pricing, or BTM power consumption.
Within example embodiments described herein, various types of utility-scale power producers may operate as generation stations 202 that are capable of supplying power to one or more loads behind-the-meter. For instance, renewable energy sources (e.g., wind, solar, hydroelectric, wave, water current, tidal), fossil fuel power generation sources (coal, natural gas), and other types of power producers (e.g., nuclear power) may be positioned in an arrangement that enables the intermittent supply of generated power behind-the-meter to one or more BTM loads. One of ordinary skill in the art will recognize that the generation station 202 may vary based on an application or design in accordance with one or more example embodiments.
In addition, the particular arrangement (e.g., connections) between the generation station and one or more BTM loads can vary within examples. In one embodiment, a generation station may be positioned in an arrangement wherein the generation station selectively supplies power to the grid and/or to one or more BTM loads. As such, power cost-analysis and other factors (e.g., predicted weather conditions, contractual obligations, etc.) may be used by the generation station, a BTM load control system, a remote master control system, or some other system or enterprise, to selectively output power to either the grid or to one or more BTM loads in a manner that maximizes revenue to the generation station. In such an arrangement, the generation station may also be able to supply both the grid and one or more BTM loads simultaneously. In some instances, the arrangement may be configured to allow dynamic manipulation of the percentage of the overall generated power that is supplied to each option at a given time. For example, in some time periods, the generation station may supply no power to the BTM load.
In addition, the type of loads that are positioned behind-the-meter can vary within example embodiments. In general, a load that is behind-the-meter may correspond to any type of load capable of receiving and utilizing power behind-the-meter from a generation station. Some examples of loads include, but are not limited to, datacenters and electric vehicle (EV) charging stations.
Preferred BTM loads are loads that can be subject to intermittent power supply because BTM power may be available intermittently. In some instances, the generation station may generate power intermittently. For example, wind power station 102c and/or photovoltaic power station 102d may only generate power when resource are available or favorable. Additionally or alternatively, BTM power availability at a generation station may only be available intermittently due to power market fluctuations, power system conditions (e.g., power factor fluctuation or generation station startup and testing), and/or operational directives from grid operators or generation station operators.
Some example embodiments of BTM loads described herein involve using one or more computing systems to serve as a BTM load at a generation station. In particular, the computing system or computing systems may receive power behind-the-meter from the generation station to perform various computational operations, such as processing or storing information, performing calculations, mining for cryptocurrencies, supporting blockchain ledgers, and/or executing applications, etc.
Multiple computing systems positioned behind-the-meter may operate as part of a “flexible” datacenter that is configured to operate only intermittently and to receive and utilize BTM power to carry out various computational operations similar to a traditional datacenter. In particular, the flexible datacenter may include computing systems and other components (e.g., support infrastructure, a control system) configured to utilize BTM power from one or more generation stations. The flexible datacenter may be configured to use particular load ramping abilities (e.g., quickly increase or decrease power usage) to effectively operate during intermittent periods of time when power is available from a generation station and supplied to the flexible datacenter behind-the-meter, such as during situations when supplying generated power to the grid is not favorable for the generation station.
In some instances, the amount of power consumed by the computing systems at a flexible datacenter can be ramped up and down quickly, and potentially with high granularity (i.e., the load can be changed in small increments if desired). This may be done based on monitored power system conditions or other information analyses as discussed herein. As recited above, this can enable a generation station to avoid negative power market pricing and to respond quickly to grid directives. And by extension, the flexible datacenter may obtain BTM power at a price lower than the cost for power from the grid.
Various types of computing systems can provide granular power ramping. Preferably, the computing systems can perform computational tasks that are immune to, or not substantially hindered by, frequent interruptions or slow-downs in processing as the computing systems ramp down or up. In some embodiments, a control system may be used to activate or de-activate one or more computing systems in an array of computing systems. For example, the control system may provide control instructions to one or more blockchain miners (e.g., a group of blockchain miners), including instructions for powering on or off, adjusting frequency of computing systems performing operations (e.g., adjusting the processing frequency), adjusting the quantity of operations being performed, and when to operate within a low power mode (if available).
Within examples, a control system may correspond to a specialized computing system or may be a computing system within a datacenter serving in the role of the control system. The location of the control system can vary within examples as well. For instance, the control system may be located at a datacenter or physically separate from the datacenter. In some examples, the control system may be part of a network of control systems that manage computational operations, power consumption, and other aspects of a fleet of datacenters. The fleet of datacenters may include one or more traditional datacenters and/or flexible datacenters.
Some embodiments may involve using one or more control systems to direct time-insensitive (e.g., interruptible) computational tasks to computational hardware, such as central processing units (CPUs) and graphics processing units (GPUs), sited behind the meter, while other hardware is sited in front of the meter (i.e., consuming metered grid power via a customer meter (e.g., 106d, 106f)) and possibly remote from the behind-the-meter hardware. As such, parallel computing processes, such as Monte Carlo simulations, batch processing of financial transactions, graphics rendering, machine learning, neural network processing, queued operations, and oil and gas field simulation models, are good candidates for such interruptible computational operations.
Consistent with
Generation station 202 includes power generation equipment 210, which may include, as examples, wind turbines and/or photovoltaic panels. Power generation equipment 210 may further include other electrical equipment, including but not limited to switches, busses, collectors, inverters, and power unit transformers (e.g., transformers in wind turbines).
As illustrated in
In one configuration, generated power may travel from the power generation equipment 210 over one or more connectors 230A, 230B to one or more electrical busses 240A, 240B, respectively. Each of the connectors 230A, 230B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, connector 230B is shown with an open switch, and connector 230A is shown with a closed switch, but either or both may be reversed in some embodiments. Aspects of this configuration can be used in various embodiments when BTM power is supplied without significant power conversion to BTM loads.
In various configurations, the busses 240A and 240B may be separated by an open switch 240C or combined into a common bus by a closed switch 240C.
In another configuration, generated power may travel from the power generation equipment 210 to the high side of a local step-down transformer 214. The generated power may then travel from the low side of the local step-down transformer 214 over one or more connectors 232A, 232B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 232A, 232B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, connector 232A is shown with an open switch, and connector 232B is shown with a closed switch, but either or both may be reversed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the power generation equipment 210, but the generated power must be stepped down prior to use at the BTM loads.
In another configuration, generated power may travel from the power generation equipment 210 to the low side of a local step-up transformer 212. The generated power may then travel from the high side of the local step-up transformer 212 over one or more connectors 234A, 234B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 234A, 234B may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, both connectors 234A, 234B are shown with open switches, but either or both may be closed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the outbound connector 250 or the high side of the local step-up transformer 212.
In another configuration, generated power may travel from the power generation equipment 210 to the low side of the local step-up transformer 212. The generated power may then travel from the high side of the local step-up transformer 212 to the high side of local step-down transformer 213. The generated power may then travel from the low side of the local step-down transformer 213 over one or more connectors 236A, 236B to the one or more electrical busses 240A, 240B, respectively. Each of the connectors 236A, 2346 may be a switched connector such that power may be routed independently to 240A and/or 240B. For illustrative purposes only, both connectors 236A, 236B are shown with open switches, but either or both may be closed in some embodiments. Aspects of this configuration can be used when it is preferable to connect BTM power to the outbound connector 250 or the high side of the local step-up transformer 212, but the power must be stepped down prior to use at the BTM loads.
In one embodiment, power generated at the generation station 202 may be used to power a generation station control system 216 located at the generation station 202, when power is available. The generation station control system 216 may typically control the operation of the generation station 202. Generated power used at the generation station control system 216 may be supplied from bus 240A via connector 216A and/or from bus 240B via connector 216B. Each of the connectors 216A, 216B may be a switched connector such that power may be routed independently to 240A and/or 240B. While the generation station control system 216 can consume BTM power when powered via bus 240A or bus 240B, the BTM power taken by generation station control system 216 is insignificant in terms of rendering an economic benefit. Further, the generation station control system 216 is not configured to operate intermittently, as it generally must remain always on. Further still, the generation station control system 216 does not have the ability to quickly ramp a BTM load up or down.
In another embodiment, grid power may alternatively or additionally be used to power the generation station control system 216. As illustrated here, metered grid power from a distribution network, such as distribution network 206 for simplicity of illustration purposes only, may be used to power generation station control system 216 over connector 216C. Connector 216C may be a switched connector so that metered grid power to the generation station control system 216 can be switched on or off as needed. More commonly, metered grid power would be delivered to the generation station control system 216 via a separate distribution network (not shown), and also over a switched connector. Any such grid power delivered to the generation station control system 216 is metered by a customer meter 206A and subject to T&D costs.
In another embodiment, when power generation equipment 210 is in an idle or off state and not generating power, grid power may backfeed into generation station 202 through POI 103 and such grid power may power the generation station control system 216.
In some configurations, an energy storage system 218 may be connected to the generation station 202 via connector 218A, which may be a switched connector. For illustrative purposes only, connector 218A is shown with an open switch but in some embodiments it may be closed. The energy storage system 218 may be connected to bus 240A and/or bus 240B and store energy produced by the power generation equipment 210. The energy storage system may also be isolated from generation station 202 by switch 242A. In times of need, such as when the power generation equipment in an idle or off state and not generating power, the energy storage system may feed power to, for example, the flexible datacenters 220. The energy storage system may also be isolated from the flexible datacenters 220 by switch 242B.
In a preferred embodiment, as illustrated, power generation equipment 210 supplies BTM power via connector 242 to flexible datacenters 220. The BTM power used by the flexible datacenters 220 was generated by the generation station 202 and did not pass through the POI 103 or utility-scale generation-side meter 253, and is not subject to T&D charges. Power received at the flexible datacenters 220 may be received through respective power input connectors 220A. Each of the respective connectors 220A may be switched connector that can electrically isolate the respective flexible datacenter 220 from the connector 242. Power equipment 220B may be arranged between the flexible datacenters 220 and the connector 242. The power equipment 220B may include, but is not limited to, power conditioners, unit transformers, inverters, and isolation equipment. As illustrated, each flexible datacenter 220 may be served by a respective power equipment 220B. However, in another embodiment, one power equipment 220B may serve multiple flexible datacenter 220.
In one embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter and electrically connected to the power generation equipment 210 behind (i.e., prior to) the generation station's POI 103 with the rest of the electrical grid.
In one embodiment, BTM power produced by the power generation equipment 210 is utilized by the flexible datacenters 220 behind (i.e., prior to) the generation station's POI with an electrical grid.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter as the flexible datacenters 220 are electrically connected to the generation station 202, and generation station 202 is subject to metering by utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter), and the flexible datacenters 220 receive power from the generation station 202, but the power received by the flexible datacenters 220 from the generation station 202 has not passed through a utility-scale generation-side meter. In this embodiment, the utility-scale generation-side meter 253 (or 253A) for the generation station 202 is located at the generation station's 202 POI 103. In another embodiment, the utility-scale generation-side meter for the generation station 202 is at a location other than the POI for the generation station 202—for example, a substation (not shown) between the generation station 202 and the generation station's POI 103.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where power produced at the generation station 202 is subject to metering by utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter), but the BTM power supplied to the flexible datacenters 220 is utilized before being metered at the utility-scale generation-side meter 253 (or 253A, or another utility-scale generation-side meter). In this embodiment, the utility-scale generation-side meter 253 (or 253A) for the generation station 202 is located at the generation station's 202 POI 103. In another embodiment, the utility-scale generation-side meter for the generation station 202 is at a location other than the POI for the generation station 202—for example, a substation (not shown) between the generation station 202 and the generation station's POI 103.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter as they are electrically connected to the generation station 202 that supplies power to the grid, and the flexible datacenters 220 receive power from the generation station 202 that is not subject to T&D charges, but power otherwise received from the grid that is supplied by the generation station 202 is subject to T&D charges.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where electrical power is generated at the generation station 202 that supplies power to a grid, and the generated power is not subject to T&D charges before being used by flexible datacenters 220, but power otherwise received from the connected grid is subject to T&D charges.
In another embodiment, flexible datacenters 220 may be considered BTM equipment located behind-the-meter because they receive power generated from the generation station 202 intended for the grid, and that received power is not routed through the electrical grid before being delivered to the flexible datacenters 220.
In another embodiment, power from the generation station 202 is supplied to the flexible datacenters 220 as BTM power, where electrical power is generated at the generation station 202 for distribution to the grid, and the flexible datacenters 220 receive that power, and that received power is not routed through the electrical grid before being delivered to the flexible datacenters 220.
In another embodiment, metered grid power may alternatively or additionally be used to power one or more of the flexible datacenters 220, or a portion within one or more of the flexible datacenters 220. As illustrated here for simplicity, metered grid power from a distribution network, such as distribution network 206, may be used to power one or more flexible datacenters 220 over connector 256A and/or 256B. Each of connector 256A and/or 256B may be a switched connector so that metered grid power to the flexible datacenters 220 can be switched on or off as needed. More commonly, metered grid power would be delivered to the flexible datacenters 220 via a separate distribution network (not shown), and also over switched connectors. Any such grid power delivered to the flexible datacenters 220 is metered by customer meters 206A and subject to T&D costs. In one embodiment, connector 256B may supply metered grid power to a portion of one or more flexible datacenters 220. For example, connector 256B may supply metered grid power to control and/or communication systems for the flexible datacenters 220 that need constant power and cannot be subject to intermittent BTM power. Connector 242 may supply solely BTM power from the generation station 202 to high power demand computing systems within the flexible datacenters 220, in which case at least a portion of each flexible datacenters 220 so connected is operating as a BTM load. In another embodiment, connector 256A and/or 256B may supply all power used at one or more of the flexible datacenters 220, in which case each of the flexible datacenters 220 so connected would not be operating as a BTM load.
In another embodiment, when power generation equipment 210 is in an idle or off state and not generating power, grid power may backfeed into generation station 202 through POI 103 and such grid power may power the flexible datacenters 220.
The flexible datacenters 220 are shown in an example arrangement relative to the generation station 202. Particularly, generated power from the generation station 202 may be supplied to the flexible datacenters 220 through a series of connectors and/or busses (e.g., 232B, 240B, 242, 220A). As illustrated, in other embodiments, connectors between the power generation equipment 210 and other components may be switched open or closed, allowing other pathways for power transfer between the power generation equipment 210 and components, including the flexible datacenters 220. Additionally, the connector arrangement shown is illustrative only and other circuit arrangements are contemplated within the scope of supplying BTM power to a BTM load at generation station 202. For example, there may be more or fewer transformers, or one or more of transformers 212, 213, 214 may be transformer systems with multiple steppings and/or may include additional power equipment including but not limited to power conditioners, filters, switches, inverters, and/or AC/DC-DC/AC isolators. As another example, metered grid power connections to flexible datacenters 220 are shown via both 256A and 256B; however, a single connection may connect one or more flexible datacenters 220 (or power equipment 220B) to metered grid power and the one or more flexible datacenters 220 (or power equipment 220B) may include switching apparatus to direct BTM power and/or metered grid power to control systems, communication systems, and/or computing systems as desired.
In some examples, BTM power may arrive at the flexible datacenters 220 in a three-phase AC format. As such, power equipment (e.g., power equipment 220B) at one or more of the flexible datacenters 220 may enable each flexible datacenter 220 to use one or more phases of the power. For instance, the flexible datacenters 220 may utilize power equipment (e.g., power equipment 220B, or alternatively or additionally power equipment that is part of the flexible datacenter 220) to convert BTM power received from the generation station 202 for use at computing systems at each flexible datacenter 220. In other examples, the BTM power may arrive at one or more of the flexible datacenters 220 as DC power. As such, the flexible datacenters 220 may use the DC power to power computing systems. In some such examples, the DC power may be routed through a DC-to-DC converter that is part of power equipment 220B and/or flexibles datacenter 220.
In some configurations, a flexible datacenter 220 may be arranged to only have access to power received behind-the-meter from a generation station 202. In the arrangement of
In some configurations, one or more of the flexible datacenters 220 can be arranged to have connections to multiple sources that are capable of supplying power to a flexible datacenter 220. To illustrate a first example, the flexible datacenters 220 are shown connected to connector 242, which can be connected or disconnected via switches to the energy storage system 218 via connector 218A, the generation station 202 via bus 240B, and grid power via metered connector 256A. In one embodiment, the flexible datacenters 220 may selectively use power received behind-the-meter from the generation station 202, stored power supplied by the energy storage system 218, and/or grid power. For instance, flexible datacenters 220 may use power stored in the energy storage system 218 when costs for using power supplied behind-the-meter from the generation station 202 are disadvantageous. By having access to the energy storage system 218 available, the flexible datacenters 220 may use the stored power and allow the generation station 202 to subsequently refill the energy storage system 218 when cost for power behind-the-meter is low. Alternatively, the flexible datacenters 220 may use power from multiple sources simultaneously to power different components (e.g., a first set and a second set of computing systems). Thus, the flexible datacenters 220 may leverage the multiple connections in a manner that can reduce the cost for power used by the computing systems at the flexible datacenters 220. The flexible datacenters 220 control system or the remote master control system 262 may monitor power conditions and other factors to determine whether the flexible datacenters 220 should use power from either the generation station 202, grid power, the energy storage system 218, none of the sources, or a subset of sources during a given time range. Other arrangements are possible as well. For example, the arrangement of
The selection of which power source to use at a flexible datacenter (e.g., the flexible datacenters 220) or another type of BTM load can change based on various factors, such as the cost and availability of power from both sources, the type of computing systems using the power at the flexible datacenters 220 (e.g., some systems may require a reliable source of power for a long period), the nature of the computational operations being performed at the flexible datacenters 220 (e.g., a high priority task may require immediate completion regardless of cost), and temperature and weather conditions, among other possible factors. As such, a datacenter control system at the flexible datacenters 220, the remote master control system 262, or another entity (e.g., an operator at the generation station 202) may also influence and/or determine the source of power that the flexible datacenters 220 use at a given time to complete computational operations.
In some example embodiments, the flexible datacenters 220 may use power from the different sources to serve different purposes. For example, the flexible datacenters 220 may use metered power from grid power to power one or more systems at the flexible datacenters 220 that are configured to be always-on (or almost always on), such as a control and/or communication system and/or one or more computing systems (e.g., a set of computing systems performing highly important computational operations). The flexible datacenters 220 may use BTM power to power other components within the flexible datacenters 220, such as one or more computing systems that perform less critical computational operations.
In some examples, one or more flexible datacenters 220 may be deployed at the generation station 202. In other examples, flexible datacenters 220 may be deployed at a location geographically remote from the generation station 202, while still maintaining a BTM power connection to the generation station 202.
In another example arrangement, the generation station 202 may be connected to a first BTM load (e.g., a flexible datacenter 220) and may supply power to additional BTM loads via connections between the first BTM load and the additional BTM loads (e.g., a connection between a flexible datacenter 220 and another flexible datacenter 220).
The arrangement in
Within the arrangement of
Information used to make decisions may include economic and/or power-related information, such as monitored power system conditions. Monitored power system conditions may include one or more of excess power generation at a generation station 202, excess power at a generation station 202 that a connected grid cannot receive, power generation at a generation station 202 subject to economic curtailment, power generation at a generation station 202 subject to reliability curtailment, power generation at a generation station 202 subject to power factor correction, low power generation at a generation station 202, start up conditions at a generation station 202, transient power generation conditions at a generation station 202, or testing conditions where there is an economic advantage to using behind-the-meter power generation at a generation station 202. These different monitored power system conditions can be weighted differently during processing and analysis.
In some examples, the information can include the cost for power from available sources (e.g., BTM power at the generation station 202 versus metered grid power) to enable comparisons to be made which power source costs less. In some instances, the information may include historic prices for power to enable the remote master control system 262 or another system to predict potential future prices in similar situations (e.g., the cost of power tends to trend upwards for grid power during warmer weather and peak-use hours). The information may also indicate the availability of power from the various sources (e.g., BTM power at the generation station 262, the energy storage system 218 at the generation station 262, and/or metered grid power).
In addition, the information may also include other data, including information associated with operations at components within the arrangement. For instance, the information may include data associated with performance of operations at the flexible datacenters 220 and the traditional datacenters 260, such as the number of computational tasks currently being performed, the types of tasks being performed (e.g., type of computational operation, time-sensitivity, etc.), the number, types, and capabilities of available computing systems, the amount of computational tasks awaiting performance, and the types of computing systems at one or more datacenters, among others. The information may also include data specifying the conditions at one or more datacenters (e.g., whether or not the temperatures are in a desired range, the amount of power available within an energy storage system such as 218), the amount of computational tasks awaiting performance in the queue of one or more of the datacenters, and the identities of the entities associated with the computational operations at one or more of the datacenters. Entities associated with computational operations may be, for example, owners of the datacenters, customers who purchase computational time at the datacenters, or other entities.
The information used by the remote master control system 262 or another component may include data associated with the computational operations to be performed, such as deadlines, priorities (e.g., high vs. low priority tasks), cost to perform based on required computing systems, the optimal computing systems (e.g., CPU vs GPU vs ASIC; processing unit capabilities, speeds, or frequencies, or instructional sets executable by the processing units) for performing each requested computational task, and prices each entity (e.g., company) is willing to pay for computational operations to be performed or otherwise supported via computing systems at a traditional datacenter 260 or a flexible datacenter 220, among others. In addition, the information may also include other data (e.g., weather conditions at locations of datacenters or power sources, any emergencies associated with a datacenter or power source, or the current value of bids associated with an auction for computational tasks).
The information may be updated in-real time and used to make the different operational decisions within the arrangement of
The remote master control system 262 represents a computing system that is capable of obtaining, managing, and using the information described above to manage and oversee one or more operations within the arrangement of
As shown in
The remote master control system 262 may be capable of directing one or more flexible datacenters 220 to ramp-up or ramp-down to desired power consumption levels, and/or to control cooperative action of multiple flexible datacenters by determining how to power each individual flexible datacenter 220 in accordance with operational directives.
The configuration of the remote master control system 262 can vary within examples as further discussed with respect to
In addition, the remote master control system 262 may communicate with components within the arrangement of
The remote master control system 262 may also communicate with grid operators and/or an operator of generation station 202 to help determine power management strategies when distributing computational operations across the various datacenters. In addition, the remote master control system 262 may communicate with other sources, such as weather prediction systems, historical and current power price databases, and auction systems, etc.
In further examples, the remote master control system 262 or another computing system within the arrangement of
In the example arrangement shown in
The arrangement of
The remote master control system 300 may perform one or more operations described herein and may include a processor 302, a data storage unit 304, a communication interface 306, a user interface 308, an operations and environment analysis module 310, and a queue system 312. In other examples, the remote master control system 300 may include more or fewer components in other possible arrangements.
As shown in
As part of the arrangement of
Although the remote master control system 300 is shown as a single entity, a network of computing systems may perform the operations of the remote master control system 300 in some examples. For example, the remote master control system 300 may exist in the form of computing systems (e.g., datacenter control systems) distributed across multiple datacenters.
The remote master control system 300 may include one or more processors 302. As such, the processor 302 may represent one or more general-purpose processors (e.g., a microprocessor) and/or one or more special-purpose processors (e.g., a digital signal processor (DSP)). In some examples, the processor 302 may include a combination of processors within examples. The processor 302 may perform operations, including processing data received from the other components within the arrangement of
The data storage unit 304 may include one or more volatile, non-volatile, removable, and/or non-removable storage components, such as magnetic, optical, or flash storage, and/or can be integrated in whole or in part with the processor 302. As such, the data storage unit 304 may take the form of a non-transitory computer-readable storage medium, having stored thereon program instructions (e.g., compiled or non-compiled program logic and/or machine code) that, when executed by the processor 302, cause the remote master control system 300 to perform one or more acts and/or functions, such as those described in this disclosure. Such program instructions can define and/or be part of a discrete software application. In some instances, the remote master control system 300 can execute program instructions in response to receiving an input, such as from the communication interface 306, the user interface 308, or the operations and environment analysis module 310. The data storage unit 304 may also store other information, such as those types described in this disclosure.
In some examples, the data storage unit 304 may serve as storage for information obtained from one or more external sources. For example, data storage unit 304 may store information obtained from one or more of the traditional datacenters 260, a generation station 202, a system associated with the grid, and flexible datacenters 220. As examples only, data storage 304 may include, in whole or in part, local storage, dedicated server-managed storage, network attached storage, and/or cloud-based storage, and/or combinations thereof.
The communication interface 306 can allow the remote master control system 300 to connect to and/or communicate with another component according to one or more protocols. For instance, the communication interface 306 may be used to obtain information related to current, future, and past prices for power, power availability, current and predicted weather conditions, and information regarding the different datacenters (e.g., current workloads at datacenters, types of computing systems available within datacenters, price to obtain power at each datacenter, levels of power storage available and accessible at each datacenter, etc.). In an example, the communication interface 306 can include a wired interface, such as an Ethernet interface or a high-definition serial-digital-interface (HD-SDI). In another example, the communication interface 406 can include a wireless interface, such as a cellular, satellite, WiMAX, or WI-FI interface. A connection can be a direct connection or an indirect connection, the latter being a connection that passes through and/or traverses one or more components, such as such as a router, switcher, or other network device. Likewise, a wireless transmission can be a direct transmission or an indirect transmission. The communication interface 306 may also utilize other types of wireless communication to enable communication with datacenters positioned at various locations.
The communication interface 306 may enable the remote master control system 300 to communicate with the components of the arrangement of
The user interface 308 can facilitate interaction between the remote master control system 300 and an administrator or user, if applicable. As such, the user interface 308 can include input components such as a keyboard, a keypad, a mouse, a touch-sensitive panel, a microphone, and/or a camera, and/or output components such as a display device (which, for example, can be combined with a touch-sensitive panel), a sound speaker, and/or a haptic feedback system. More generally, the user interface 308 can include hardware and/or software components that facilitate interaction between remote master control system 300 and the user of the system.
In some examples, the user interface 308 may enable the manual examination and/or manipulation of components within the arrangement of
The operations and environment analysis module 310 represents a component of the remote master control system 300 associated with obtaining and analyzing information to develop instructions/directives for components within the arrangement of
In some examples, the operations and environment analysis module 310 may use location, weather, activity levels at the flexible datacenters or the generation station, and power cost information to determine control strategies for one or more components in the arrangement of
The queue system 312 represents a queue capable of organizing computational operations to be performed by one or more datacenters. Upon receiving a request to perform a computational operation, the remote master control system 300 may assign the computational operation to the queue until one or more computing systems are available to support the computational operation. The queue system 312 may be used for organizing and transferring computational tasks in real time.
The organizational design of the queue system 312 may vary within examples. In some examples, the queue system 312 may organize indications (e.g., tags, pointers) to sets of computational operations requested by various enterprises. The queue system 312 may operate as a First-In-First-Out (FIFO) data structure. In a FIFO data structure, the first element added to the queue will be the first one to be removed. As such, the queue system 312 may include one or more queues that operate using the FIFO data structure.
In some examples, one or more queues within the queue system 312 may use other designs of queues, including rules to rank or organize queues in a particular manner that can prioritize some sets of computational operations over others. The rules may include one or more of an estimated cost and/or revenue to perform each set of computational operations, an importance assigned to each set of computational operations, and deadlines for initiating or completing each set of computational operations, among others. Examples using a queue system are further described below with respect to
In some examples, the remote master control system 300 may be configured to monitor one or more auctions to obtain computational operations for datacenters to support. Particularly, the remote master control system 300 may use resource availability and power prices to develop and submit bids to an external or internal auction system for the right to support particular computational operations. As a result, the remote master control system 300 may identify computational operations that could be supported at one or more flexible datacenters 220 at low costs.
The generation station 400 can correspond to any type of grid-connected utility-scale power producer capable of supplying power to one or more loads. The size, amount of power generated, and other characteristics of the generation station 400 may differ within examples. For instance, the generation station 400 may be a power producer that provides power intermittently. The power generation may depend on monitored power conditions, such as weather at the location of the generation station 400 and other possible conditions. As such, the generation station 400 may be a temporary arrangement, or a permanent facility, configured to supply power. The generation station 400 may supply BTM power to one or more loads and supply metered power to the electrical grid. Particularly, the generation station 400 may supply power to the grid as shown in the arrangement of
The power generation equipment 401 represents the component or components configured to generate utility-scale power. As such, the power generation equipment 401 may depend on the type of facility that the generation station 400 corresponds to. For instance, the power generation equipment 401 may correspond to electric generators that transform kinetic energy into electricity. The power generation equipment 401 may use electromagnetic induction to generate power. In other examples, the power generation equipment 401 may utilize electrochemistry to transform chemical energy into power. The power generation equipment 401 may use the photovoltaic effect to transform light into electrical energy. In some examples, the power generation equipment 401 may use turbines to generate power. The turbines may be driven by, for example, wind, water, steam or burning gas. Other examples of power production are possible.
The communication interface 408 can enable the generation station 400 to communicate with other components within the arrangement of
The generation station control system 414 may be one or more computing systems configured to control various aspects of the generation station 400.
The BTM interface 406 is a module configured to enable the power generation equipment 401 to supply BTM power to one or more loads and may include multiple components. The arrangement of the BTM interface 406 may differ within examples based on various factors, such as the number of flexible datacenters 220 (or 500) coupled to the generation station 400, the proximity of the flexible datacenters 220 (or 500), and the type of generation station 400, among others. In some examples, the BTM interface 406 may be configured to enable power delivery to one or more flexible datacenters positioned near the generation station 400. Alternatively, the BTM interface 406 may also be configured to enable power delivery to one or more flexible datacenters 220 (or 500) positioned remotely from the generation station 400.
The grid interface 404 is a module configured to enable the power generation equipment 401 to supply power to the grid and may include multiple components. As such, the grid interface 404 may couple to one or more transmission lines (e.g., transmission lines 404a shown in
The user interface 410 represents an interface that enables administrators and/or other entities to communicate with the generation station 400. As such, the user interface 410 may have a configuration that resembles the configuration of the user interface 308 shown in
The power transformation equipment 402 represents equipment that can be utilized to enable power delivery from the power generation equipment 401 to the loads and to transmission lines linked to the grid. Example power transformation equipment 402 includes, but is not limited to, transformers, inverters, phase converters, and power conditioners.
The example configuration shown in
The flexible datacenter 500 may include a design that allows for temporary and/or rapid deployment, setup, and start time for supporting computational operations. For instance, the flexible datacenter 500 may be rapidly deployed at a location near a source of generation station power (e.g., near a wind farm or solar farm). Rapid deployment may involve positioning the flexible datacenter 500 at a target location and installing and/or configuring one or more racks of computing systems within. The racks may include wheels to enable swift movement of the computing systems. Although the flexible datacenter 500 could theoretically be placed anywhere, transmission losses may be minimized by locating it proximate to BTM power generation.
The physical construction and layout of the flexible datacenter 500 can vary. In some instances, the flexible datacenter 500 may utilize a metal container (e.g., a metal container 602 shown in
Within the flexible datacenter 500, various internal components enable the flexible datacenter 500 to utilize power to perform some form of operations. The power input system 502 is a module of the flexible datacenter 500 configured to receive external power and input the power to the different components via assistance from the power distribution system 506. As discussed with respect to
In some embodiments, the power input system 502 may include some or all of flexible datacenter Power Equipment 220B. The power input system 502 may be designed to obtain power in different forms (e.g., single phase or three-phase behind-the-meter alternating current (“AC”) voltage, and/or direct current (“DC”) voltage). As shown, the power input system 502 includes a BTM power input sub-system 522, a grid power input sub-system 524, and an energy input sub-system 526. These sub-systems are included to illustrate example power input sub-systems that the flexible datacenter 500 may utilize, but other examples are possible. In addition, in some instances, these sub-systems may be used simultaneously to supply power to components of the flexible datacenter 500. The sub-systems may also be used based on available power sources.
In some implementations, the BTM power input sub-system 522 may include one or more AC-to-AC step-down transformers used to step down supplied medium-voltage AC to low voltage AC (e.g., 120V to 600V nominal) used to power computing systems 512 and/or other components of flexible datacenter 500. The power input system 502 may also directly receive single-phase low voltage AC from a generation station as BTM power, from grid power, or from a stored energy system such as energy storage system 218. In some implementations, the power input system 502 may provide single-phase AC voltage to the datacenter control system 504 (and/or other components of flexible datacenter 500) independent of power supplied to computing systems 512 to enable the datacenter control system 504 to perform management operations for the flexible datacenter 500. For instance, the grid power input sub-system 524 may use grid power to supply power to the datacenter control system 504 to ensure that the datacenter control system 504 can perform control operations and communicate with the remote master control system 300 (or 262) during situations when BTM power is not available. As such, the datacenter control system 504 may utilize power received from the power input system 502 to remain powered to control the operation of flexible datacenter 500, even if the computational operations performed by the computing system 512 are powered intermittently. In some instances, the datacenter control system 504 may switch into a lower power mode to utilize less power while still maintaining the ability to perform some functions.
The power distribution system 506 may distribute incoming power to the various components of the flexible datacenter 500. For instance, the power distribution system 506 may direct power (e.g., single-phase or three-phase AC) to one or more components within flexible datacenter 500. In some embodiments, the power distribution system 506 may include some or all of flexible datacenter Power Equipment 220B.
In some examples, the power input system 502 may provide three phases of three-phase AC voltage to the power distribution system 506. The power distribution system 506 may controllably provide a single phase of AC voltage to each computing system or groups of computing systems 512 disposed within the flexible datacenter 500. The datacenter control system 504 may controllably select which phase of three-phase nominal AC voltage that power distribution system 506 provides to each computing system 512 or groups of computing systems 512. This is one example manner in which the datacenter control system 504 may modulate power delivery (and load at the flexible datacenter 500) by ramping-up flexible datacenter 500 to fully operational status, ramping-down flexible datacenter 500 to offline status (where only datacenter control system 504 remains powered), reducing load by withdrawing power delivery from, or reducing power to, one or more of the computing systems 512 or groups of the computing systems 512, or modulating power factor correction for the generation station 300 (or 202) by controllably adjusting which phases of three-phase nominal AC voltage are used by one or more of the computing systems 512 or groups of the computing systems 512. The datacenter control system 504 may direct power to certain sets of computing systems based on computational operations waiting for computational resources within the queue system 514. In some embodiments, the flexible datacenter 500 may receive BTM DC power to power the computing systems 512.
One of ordinary skill in the art will recognize that a voltage level of three-phase AC voltage may vary based on an application or design and the type or kind of local power generation. As such, a type, kind, or configuration of the operational AC-to-AC step down transformer (not shown) may vary based on the application or design. In addition, the frequency and voltage level of three-phase AC voltage, single-phase AC voltage, and DC voltage may vary based on the application or design in accordance with one or more embodiments.
As discussed above, the datacenter control system 504 may perform operations described herein, such as dynamically modulating power delivery to one or more of the computing systems 512 disposed within flexible datacenter 500. For instance, the datacenter control system 504 may modulate power delivery to one or more of the computing systems 512 based on various factors, such as BTM power availability or an operational directive from a generation station 262 or 300 control system, a remote master control system 262 or 300, or a grid operator. In some examples, the datacenter control system 504 may provide computational operations to sets of computing systems 512 and modulate power delivery based on priorities assigned to the computational operations. For instance, an important computational operation (e.g., based on a deadline for execution and/or price paid by an entity) may be assigned to a particular computing system or set of computing systems 512 that has the capacity, computational abilities to support the computational operation. In addition, the datacenter control system 504 may also prioritize power delivery to the computing system or set of computing systems 512.
In some example, the datacenter control system 504 may further provide directives to one or more computing systems to change operations in some manner. For instance, the datacenter control system 504 may cause one or more computing systems 512 to operate at a lower or higher frequency, change clock cycles, or operate in a different power consumption mode (e.g., a low power mode). These abilities may vary depending on types of computing systems 512 available at the flexible datacenter 500. As a result, the datacenter control system 504 may be configured to analyze the computing systems 512 available either on a periodic basis (e.g., during initial set up of the flexible datacenter 500) or in another manner (e.g., when a new computational operation is assigned to the flexible datacenter 500).
The datacenter control system 504 may also implement directives received from the remote master control system 262 or 300. For instance, the remote master control system 262 or 300 may direct the flexible datacenter 500 to switch into a low power mode. As a result, one or more of the computing systems 512 and other components may switch to the low power mode in response.
The datacenter control system 504 may utilize the communication interface 503 to communicate with the remote master control system 262 or 300, other datacenter control systems of other datacenters, and other entities. As such, the communication interface 503 may include components and operate similar to the communication interface 306 of the remote master control system 300 described with respect to
The flexible datacenter 500 may also include a climate control system 508 to maintain computing systems 512 within a desired operational temperature range. The climate control system 508 may include various components, such as one or more air intake components, an evaporative cooling system, one or more fans, an immersive cooling system, an air conditioning or refrigerant cooling system, and one or more air outtake components. One of ordinary skill in the art will recognize that any suitable heat extraction system configured to maintain the operation of computing systems 512 within the desired operational temperature range may be used.
The flexible datacenter 500 may further include an energy storage system 510. The energy storage system 510 may store energy for subsequent use by computing systems 512 and other components of flexible datacenter 500. For instance, the energy storage system 510 may include a battery system. The battery system may be configured to convert AC voltage to DC voltage and store power in one or more storage cells. In some instances, the battery system may include a DC-to-AC inverter configured to convert DC voltage to AC voltage, and may further include an AC phase-converter, to provide AC voltage for use by flexible datacenter 500.
The energy storage system 510 may be configured to serve as a backup source of power for the flexible datacenter 500. For instance, the energy storage system 510 may receive and retain power from a BTM power source at a low cost (or no cost at all). This low-cost power can then be used by the flexible datacenter 500 at a subsequent point, such as when BTM power costs more. Similarly, the energy storage system 510 may also store energy from other sources (e.g., grid power). As such, the energy storage system 510 may be configured to use one or more of the sub-systems of the power input system 502.
In some examples, the energy storage system 510 may be external to the flexible datacenter 500. For instance, the energy storage system 510 may be an external source that multiple flexible datacenters utilize for back-up power.
The computing systems 512 represent various types of computing systems configured to perform computational operations. Performance of computational operations include a variety of tasks that one or more computing systems may perform, such as data storage, calculations, application processing, parallel processing, data manipulation, cryptocurrency mining, and maintenance of a distributed ledger, among others. As shown in
Due to different performance features and abilities associated with the different types of computing systems, the datacenter control system 504 may determine, maintain, and/or relay this information about the types and/or abilities of the computing systems, quantity of each type, and availability to the remote master control system 262 or 300 on a routine basis (e.g., periodically or on-demand). This way, the remote master control system 262 or 300 may have current information about the abilities of the computing systems 512 when distributing computational operations for performance at one or more flexible datacenters. Particularly, the remote master control system 262 or 300 may assign computational operations based on various factors, such as the types of computing systems available and the type of computing systems required by each computing operation, the availability of the computing systems, whether computing systems can operate in a low power mode, and/or power consumption and/or costs associated with operating the computing systems, among others.
The quantity and arrangement of these computing systems 512 may vary within examples. In some examples, the configuration and quantity of computing systems 512 may depend on various factors, such as the computational tasks that are performed by the flexible datacenter 500. In other examples, the computing systems 512 may include other types of computing systems as well, such as DSPs, SIMDs, neural processors, and/or quantum processors.
As indicated above, the computing systems 512 can perform various computational operations, including in different configurations. For instance, each computing system may perform a particular computational operation unrelated to the operations performed at other computing systems. Groups of the computing systems 512 may also be used to work together to perform computational operations.
In some examples, multiple computing systems may perform the same computational operation in a redundant configuration. This redundant configuration creates a back-up that prevents losing progress on the computational operation in situations of a computing failure or intermittent operation of one or more computing systems. In addition, the computing systems 512 may also perform computational operations using a check point system. The check point system may enable a first computing system to perform operations up to a certain point (e.g., a checkpoint) and switch to a second computing system to continue performing the operations from that certain point. The check point system may also enable the datacenter control system 504 to communicate statuses of computational operations to the remote master control system 262 or 300. This can further enable the remote master control system 262 300 to transfer computational operations between different flexible datacenters allowing computing systems at the different flexible datacenters to resume support of computational operations based on the check points.
The queue system 514 may operate similar to the queue system 312 of the remote master control system 300 shown in
As discussed above, the structural arrangement of the flexible datacenter 500 may depend on various factors, such as the ability to maintain temperature within the mobile container 602 within a desired temperature range. The desired temperature range may depend on the geographical location of the mobile container 602 and the type and quantity of the computing systems 512 operating within the flexible datacenter 500 as well as other possible factors. As such, the different design elements of the mobile container 602 including the inner contents and positioning of components may depend on factors that aim to maximize the use of space within mobile container 602, lower the amount of power required to cool the computing systems 512, and make setup of the flexible datacenter 500 efficient. For instance, a first flexible datacenter positioned in a cooler geographic region may include less cooling equipment than a second flexible datacenter positioned in a warmer geographic region.
As shown in
The datacenter control system 504 may independently or cooperatively with one or more of the generation station control system 414, the remote master control system 300, and/or the grid operator 702 modulate power at the flexible datacenter 500. During operations, the power delivery to the flexible datacenter 500 may be dynamically adjusted based on conditions or operational directives. The conditions may correspond to economic conditions (e.g., cost for power, aspects of computational operations to be performed), power-related conditions (e.g., availability of the power, the sources offering power), demand response, and/or weather-related conditions, among others.
The generation station control system 414 may be one or more computing systems configured to control various aspects of a generation station (not independently illustrated, e.g., 216 or 400). As such, the generation station control system 414 may communicate with the remote master control system 300 over a networked connection 706 and with the datacenter control system 704 over a networked or other data connection 708.
As discussed with respect to
The grid operator 702 may be one or more computing systems that are configured to control various aspects of the power grid (not independently illustrated) that receives power from the generation station. The grid operator 702 may communicate with the generation station control system 300 over a networked or other data connection 712.
The datacenter control system 504 may monitor BTM power conditions at the generation station and determine when a datacenter ramp-up condition is met. The BTM power availability may include one or more of excess local power generation, excess local power generation that the grid cannot accept, local power generation that is subject to economic curtailment, local power generation that is subject to reliability curtailment, local power generation that is subject to power factor correction, conditions where the cost for power is economically viable (e.g., low cost to obtain power), low priced power, situations where local power generation is prohibitively low, start up situations, transient situations, or testing situations where there is an economic advantage to using locally generated behind-the-meter power generation, specifically power available at little to no cost and with no associated transmission or distribution losses or costs. For example, a datacenter control system may analyze future workload and near term weather conditions at the flexible datacenter.
In some instances, the datacenter ramp-up condition may be met if there is sufficient behind-the-meter power availability and there is no operational directive from the generation station control system 414, the remote master control system 300, or the grid operator 702 to go offline or reduce power. As such, the datacenter control system 504 may enable 714 the power input system 502 to provide power to the power distribution system 506 to power the computing systems 512 or a subset thereof.
The datacenter control system 504 may optionally direct one or more computing systems 512 to perform predetermined computational operations (e.g., distributed computing processes). For example, if the one or more computing systems 512 are configured to perform blockchain hashing operations, the datacenter control system 504 may direct them to perform blockchain hashing operations for a specific blockchain application, such as, for example, Bitcoin, Litecoin, or Ethereum. Alternatively, one or more computing systems 512 may be configured to perform high-throughput computing operations and/or high performance computing operations.
The remote master control system 300 may specify to the datacenter control system 504 what sufficient behind-the-meter power availability constitutes, or the datacenter control system 504 may be programmed with a predetermined preference or criteria on which to make the determination independently. For example, in certain circumstances, sufficient behind-the-meter power availability may be less than that required to fully power the entire flexible datacenter 500. In such circumstances, the datacenter control system 504 may provide power to only a subset of computing systems, or operate the plurality of computing systems in a lower power mode, that is within the sufficient, but less than full, range of power that is available. In addition, the computing systems 512 may adjust operational frequency, such as performing more or less processes during a given duration. The computing systems 512 may also adjust internal clocks via over-clocking or under-clocking when performing operations.
While the flexible datacenter 500 is online and operational, a datacenter ramp-down condition may be met when there is insufficient or anticipated to be insufficient, behind-the-meter power availability or there is an operational directive from the generation station control system 414, the remote master control system 300, or the grid operator 702. The datacenter control system 504 may monitor and determine when there is insufficient, or anticipated to be insufficient, behind-the-meter power availability. As noted above, sufficiency may be specified by the remote master control system 300 or the datacenter control system 504 may be programmed with a predetermined preference or criteria on which to make the determination independently.
An operational directive may be based on current dispatch-ability, forward looking forecasts for when behind-the-meter power is, or is expected to be, available, economic considerations, reliability considerations, operational considerations, or the discretion of the generation station control system 414, the remote master control system 300, or the grid operator 702. For example, the generation station control system 414, the remote master control system 300, or the grid operator 702 may issue an operational directive to flexible datacenter 500 to go offline and power down. When the datacenter ramp-down condition is met, the datacenter control system 504 may disable power delivery to the plurality of computing systems (e.g., 512). The datacenter control system 504 may disable 714 the power input system 502 from providing power (e.g., three-phase nominal AC voltage) to the power distribution system 506 to power down the computing systems 512 while the datacenter control system 504 remains powered and is capable of returning service to operating mode at the flexible datacenter 500 when behind-the-meter power becomes available again.
While the flexible datacenter 500 is online and operational, changed conditions or an operational directive may cause the datacenter control system 504 to modulate power consumption by the flexible datacenter 500. The datacenter control system 504 may determine, or the generation station control system 414, the remote master control system 300, or the grid operator 702 may communicate, that a change in local conditions may result in less power generation, availability, or economic feasibility, than would be necessary to fully power the flexible datacenter 500. In such situations, the datacenter control system 504 may take steps to reduce or stop power consumption by the flexible datacenter 500 (other than that required to maintain operation of datacenter control system 504).
Alternatively, the generation station control system 414, the remote master control system 300, or the grid operator 702, may issue an operational directive to reduce power consumption for any reason, the cause of which may be unknown. In response, the datacenter control system 504 may dynamically reduce or withdraw power delivery to one or more computing systems 512 to meet the dictate. The datacenter control system 504 may controllably provide three-phase nominal AC voltage to a smaller subset of computing systems (e.g., 512) to reduce power consumption. The datacenter control system 504 may dynamically reduce the power consumption of one or more computing systems by reducing their operating frequency or forcing them into a lower power mode through a network directive.
Similarly, the flexible datacenter 500 may ramp up power consumption based on various conditions. For instance, the datacenter control system 504 may determine, or the generation control system 414, the remote master control system 300, or the grid operator 702 may communicate, that a change in local conditions may result in greater power generation, availability, or economic feasibility. In such situations, the datacenter control system 504 may take steps to increase power consumption by the flexible datacenter 500.
Alternatively, the generation station control system 414, the remote master control system 300, or the grid operator 702, may issue an operational directive to increase power consumption for any reason, the cause of which may be unknown. In response, the datacenter control system 504 may dynamically increase power delivery to one or more computing systems 512 (or operations at the computing systems 512) to meet the dictate. For instance, one or more computing systems 512 may transition into a higher power mode, which may involve increasing power consumption and/or operation frequency.
One of ordinary skill in the art will recognize that datacenter control system 504 may be configured to have a number of different configurations, such as a number or type or kind of the computing systems 512 that may be powered, and in what operating mode, that correspond to a number of different ranges of sufficient and available behind-the-meter power. As such, the datacenter control system 504 may modulate power delivery over a variety of ranges of sufficient and available unutilized behind-the-meter power availability.
The remote master control system 300 may provide directive to datacenter control systems of the fleet of flexible datacenters in a similar manner to that shown and described with respect to
The arrangement of
In some examples, one or more components, such as the datacenter control system 504, the remote master control system 300, the queue system 312, or the control system 936, may be configured to identify situations that may arise where using the flexible datacenter 500 can reduce costs or increase productivity of the system, as compared to using the traditional datacenter 902 for computational operations. For example, a component within the arrangement of
In some examples, the datacenter control system 504 may monitor activity of the computing systems 512 within the flexible datacenter 500 and use the respective activity levels to determine when to obtain computational operations from the queue system 312. For instance, the datacenter control system 504 may analyze various factors prior to requesting or accessing a set of computational operations or an indication of the computational operations for the computing systems 512 to perform. The various factors may include power availability at the flexible datacenter 500 (e.g., either stored or from a BTM source), availability of the computing systems 512 (e.g., percentage of computing systems available), type of computational operations available, estimated cost to perform the computational operations at the flexible datacenter 500, cost for power, cost for power relative to cost for grid power, and instructions from other components within the system, among others. The datacenter control system 504 may analyze one or more of the factors when determining whether to obtain a new set of computational operations for the computing systems 512 to perform. In such a configuration, the datacenter control system 504 manages the activity of the flexible datacenter 500, including determining when to acquire new sets of computational operations when capacity among the computing systems 512 permit.
In other examples, a component (e.g., the remote master control system 300) within the system may assign or distribute one or more sets of computational operations organized by the queue system 312 to the flexible datacenter 500. For example, the remote master control system 300 may manage the queue system 312, including the distribution of computational operations organized by the queue system 312 to the flexible datacenter 500 and the traditional datacenter 902. The remote master control system 300 may utilize to information described with respect to the Figures above to determine when to assign computational operations to the flexible datacenter 500.
The traditional datacenter 902 may include a power input system 930, a power distribution system 932, a datacenter control system 936, and a set of computing systems 934. The power input system 930 may be configured to receive power from a power grid and distribute the power to the computing systems 934 via the power distribution system 932. The datacenter control system 936 may monitor activity of the computing systems 934 and obtain computational operations to perform from the queue system 312. The datacenter control system 936 may analyze various factors prior to requesting or accessing a set of computational operations or an indication of the computational operations for the computing systems 934 to perform. A component (e.g., the remote master control system 300) within the arrangement of
The communication link 916 represents one or more links that may serve to connect the flexible datacenter 500, the traditional datacenter 902, and other components within the system (e.g., the remote master control system 300, the queue system 312—connections not shown). In particular, the communication link 916 may enable direct or indirect communication between the flexible datacenter 500 and the traditional datacenter 902. The type of communication link 916 may depend on the locations of the flexible datacenter 500 and the traditional datacenter 902. Within embodiments, different types of communication links can be used, including but not limited to WAN connectivity, cloud-based connectivity, and wired and wireless communication links.
The queue system 312 represents an abstract data type capable of organizing computational operation requests received from entities. As each request for computational operations are received, the queue system 312 may organize the request in some manner for subsequent distribution to a datacenter. Different types of queues can make up the queue system 312 within embodiments. The queue system 312 may be a centralized queue that organizes all requests for computational operations. As a centralized queue, all incoming requests for computational operations may be organized by the centralized queue.
In other examples, the queue system 312 may be distributed consisting of multiple queue sub-systems. In the distributed configuration, the queue system 312 may use multiple queue sub-systems to organize different sets of computational operations. Each queue sub-system may be used to organize computational operations based on various factors, such as according to deadlines for completing each set of computational operations, locations of enterprises submitting the computational operations, economic value associated with the completion of computational operations, and quantity of computing resources required for performing each set of computational operations. For instance, a first queue sub-system may organize sets of non-intensive computational operations and a second queue sub-system may organize sets of intensive computational operations. In some examples, the queue system 312 may include queue sub-systems located at each datacenter. This way, each datacenter (e.g., via a datacenter control system) may organize computational operations obtained at the datacenter until computing systems are able to start executing the computational operations. In some examples, the queue system 312 may move computational operations between different computing systems or different datacenters in real-time.
Within the arrangement of
The queue system 312 may include a computing system configured to organize and maintain queues within the queue system 312. In another example, one or more other components of the system may maintain and support queues within the queue system 312. For instance, the remote master control system 300 may maintain and support the queue system 312. In other examples, multiple components may maintain and support the queue system 312 in a distributed manner, such as a blockchain configuration.
In some embodiments, the remote master control system 300 may serve as an intermediary that facilitates all communication between flexible datacenter 500 and the traditional datacenter 902. Particularly, the traditional datacenter 902 or the flexible datacenter 500 might need to transmit communications to the remote master control system 300 in order to communicate with the other datacenter. As also shown, the remote master control system 300 may connect to the queue system 312 via the communication link 918. Computational operations may be distributed between the queue system 312 and the remote master control system 300 via the communication link 918. The computational operations may be transferred in real-time and mid-performance from one datacenter to another (e.g., from the traditional datacenter 902 to the flexible datacenter 500). In addition, the remote master control system 300 may manage the queue system 312, including providing resources to support queues within the queue system 312.
As a result, the remote master control system 300 may offload some or all of the computational operations assigned to the traditional datacenter 902 to the flexible datacenter 500. This way, the flexible datacenter 500 can reduce overall computational costs by using the behind-the-meter power to provide computational resources to assist traditional datacenter 902. The remote master control system 300 may use the queue system 312 to temporarily store and organize the offloaded computational operations until a flexible datacenter (e.g., the flexible datacenter 500) is available to perform them. The flexible datacenter 500 consumes behind-the-meter power without transmission or distribution costs, which lowers the costs associated with performing computational operations originally assigned to the traditional datacenter 902. The remote master control system 300 may further communicate with the flexible datacenter 500 via communication link 922 and the traditional datacenter 902 via the communication link 924.
In step 1010, the datacenter control system, the remote master control system, or another computing system may monitor behind-the-meter power availability. In some embodiments, monitoring may include receiving information or an operational directive from the generation station control system or the grid operator corresponding to behind-the-meter power availability.
In step 1020, the datacenter control system or the remote master control system 300 may determine when a datacenter ramp-up condition is met. In some embodiments, the datacenter ramp-up condition may be met when there is sufficient behind-the-meter power availability and there is no operational directive from the generation station to go offline or reduce power.
In step 1030, the datacenter control system may enable behind-the-meter power delivery to one or more computing systems. In some instances, the remote mater control system may directly enable BTM power delivery to computing systems within the flexible system without instructing the datacenter control system.
In step 1040, once ramped-up, the datacenter control system or the remote master control system may direct one or more computing systems to perform predetermined computational operations. In some embodiments, the predetermined computational operations may include the execution of one or more distributed computing processes, parallel processes, and/or hashing functions, among other types of processes.
While operational, the datacenter control system, the remote master control system, or another computing system may receive an operational directive to modulate power consumption. In some embodiments, the operational directive may be a directive to reduce power consumption. In such embodiments, the datacenter control system or the remote master control system may dynamically reduce power delivery to one or more computing systems or dynamically reduce power consumption of one or more computing systems. In other embodiments, the operational directive may be a directive to provide a power factor correction factor. In such embodiments, the datacenter control system or the remote master control system may dynamically adjust power delivery to one or more computing systems to achieve a desired power factor correction factor. In still other embodiments, the operational directive may be a directive to go offline or power down. In such embodiments, the datacenter control system may disable power delivery to one or more computing systems.
In step 1070, the datacenter control system or the remote master control system may determine when a datacenter ramp-down condition is met. In certain embodiments, the datacenter ramp-down condition may be met when there is insufficient behind-the-meter power availability or anticipated to be insufficient behind-the-meter power availability or there is an operational directive from the generation station to go offline or reduce power.
In step 1080, the datacenter control system may disable behind-the-meter power delivery to one or more computing systems. In step 1090, once ramped-down, the datacenter control system remains powered and in communication with the remote master control system so that it may dynamically power the flexible datacenter when conditions change.
One of ordinary skill in the art will recognize that a datacenter control system may dynamically modulate power delivery to one or more computing systems of a flexible datacenter based on behind-the-meter power availability or an operational directive. The flexible datacenter may transition between a fully powered down state (while the datacenter control system remains powered), a fully powered up state, and various intermediate states in between. In addition, flexible datacenter may have a blackout state, where all power consumption, including that of the datacenter control system is halted. However, once the flexible datacenter enters the blackout state, it will have to be manually rebooted to restore power to datacenter control system. Generation station conditions or operational directives may cause flexible datacenter to ramp-up, reduce power consumption, change power factor, or ramp-down.
In general, a power option agreement is an agreement between a power entity 1140 associated with the delivery of power to a load (e.g., a grid operator, power generation station, or local control station) and the load (e.g., the datacenters 1102-1106). As part of the power option agreement, the load (e.g., load operator, contracting agent for the load, semi-automated control system associated with the load, and/or automated control system associated with the load) provides the power entity 1140 with the right, but not obligation, to reduce the amount of power delivered (e.g., grid power) to the load up to an agreed amount of power during an agreed upon time interval. In order to provide the power entity 1140 with this option, the load needs to be using at least the amount of power subject to the option (e.g., a minimum power threshold). For instance, the load may agree to use at least 1 MW of grid power at all times during a specified 24-hour time interval to provide the power entity 1140 with the option of being able to reduce the amount of power delivered to the load by any amount up to 1 MW at any point during the specified 24-hour time interval. The load may grant the power entity 1140 with this option in exchange for a monetary consideration (e.g., receive power at a reduced price and/or monetary payment if the option is exercised by the power entity).
The power option agreement may be used by the power entity 1140 to reserve the right to reduce the amount of grid power delivered to the load during a set time frame (e.g., the next 24 hours). For instance, the power entity 1140 may exercise a predefined power option to reduce the amount of grid power delivered to the load during a time when the grid power may be better redirected to other loads coupled to the power grid. As such, the power entity 1140 may exercise power option agreements to balance loads coupled to the power grid. In some embodiments, a power option agreement may also specify other parameters, such as costs associated with different levels of power consumption and/or maximum power thresholds for the load to operate according to.
To illustrate an example, a power option agreement may specify that a load (e.g., the datacenters 1102-1106) is required to use at least 10 MW or more at all times during the next 12 hours. Thus, the minimum power threshold according to the power option agreement is 10 MW and this minimum power threshold extends across the time interval of the next 12 hours. In order to comply with the agreement, the load must subsequently operate using 10 MW or more power at all times during the next 12 hours. This way, the load can accommodate a situation where the power entity 1140 exercises the option. Particularly, exercising the option may trigger the load to reduce the amount of power it consumes by an amount up to 10 MW at any point during the 12 hour interval. By establishing this power option agreement, the power entity 1140 can manipulate the amount of power consumed at the load during the next 12 hours by up to 10 MW if power needs to be redirected to another load or a reduction in power consumption is needed for other reasons.
In the example arrangement of the system 1100 shown in
As shown in
The different sets of computing systems as well as the multiple datacenters are included in
The remote master control system 262 may serve as a control system that can determine performance strategies and provide control instructions to the load (e.g., one or more of the datacenters 1102-1106). In particular, the remote master control system 262 can monitor conditions in concert with the minimum power thresholds and time intervals (e.g., power option data) set forth in, and/or derived from, one or more power option agreements to determine performance strategies that can enable the load to meet the expectations of the power option agreement(s) while also efficiently using power to accomplish computational operations. In some instances, the remote master control system 262 may also be subject to the power option agreement and may adjust its own power consumption based on the power option agreement (e.g., ramp up or down power consumption based on the defined minimum power thresholds during time intervals).
To establish a power option agreement, the remote master control system 262 (or another computing system) may communicate with the power entity 1140. For instance, the remote master control system 262 may provide a request (e.g., a signal and/or a bid) to the power entity 1140 and receive the terms of one or more power option agreements, or power option data related to power option agreements (e.g., data such as minimum power thresholds and time intervals, but not all terms contained within a potential power option agreement) in response. In some examples, the remote master control system 262 may evaluate one or more conditions prior to establishing a power option agreement to ensure that the conditions could enable the load (e.g., the datacenters 1102-1106) to operate in accordance with the power option agreement. For instance, the remote master control system 262 may check the quantity and deadlines associated with computational operations assigned to specific datacenters prior to establishing specific datacenters as a load subject to a power option agreement. In some cases, multiple power option agreements may be established. For example, each datacenter 1102-1106 may be subject to a different power option agreement, which may result in the remote master control system 262 managing the power consumption at each of the datacenters 1102-1106 differently.
Within the system 1100 shown in
Once a power option agreement is established, the remote master control system 262 may obtain power option data from the power entity 1140 (or another source) that specifies the power and time expectations of the power entity 1140. As shown in
In some examples, the power option data may also include an indication of a monetary penalty that would be imposed upon the load for failure to operate as agreed upon for the power option agreement. In addition, the power option data may also include an indication of a monetary benefit provided to the load operating at power consumption levels that are in accordance with a power option agreement. For instance, monetary benefits could include reduced prices for power, credits for power, and/or monetary payments. In addition, the power option data may include further constraints upon power use, such as one or more maximum power thresholds and corresponding time intervals for the maximum power thresholds.
In some embodiments, the power entity 1140 may correspond to a qualified scheduling entity (QSE). A QSE may submit bids and offers on behalf of resource entities (REs) or load serving entities (LSEs), such as retail electric providers (REPs). QSEs may submit offers to sell and/or bids to buy power (energy) in the Day-Ahead Market (e.g., the next 24 hours) and the Real-Time Market. As such, the remote master control system 262 or another computing system may communicate with one or more QSEs to engage and control one or more loads in accordance with one or more power option agreements.
In some examples, a power option agreement may take the form of a fixed duration power option agreement 1144. The fixed duration power option agreement 1144 may specify a set of minimum power thresholds and a set of time intervals in advance for an upcoming fixed duration of time covered by the agreement. Each minimum power threshold in the set of minimum power thresholds may be associated with a time interval in the set of time intervals. Examples of such association are provided in
In other examples, a power option agreement may take the form of a dynamic power option agreement 1146. For a dynamic power option agreement 1146, minimum power thresholds may be provided to the remote master control system 262 in real-time (or near real-time). For instance, a dynamic power option agreement may specify that the power entity 1140 may provide adjustments to minimum power thresholds and corresponding time intervals in real-time to the remote master control system 262. For example, a dynamic power option agreement may provide power option data that specifies a minimum power threshold for immediate adjustments (e.g., for the next hour).
In an embodiment, a dynamic power option agreement 1146 may involve repeat communication between the remote master control system 262 and the power entity 1140. Particularly, the power entity 1140 may provide signals to the remote master control system 262 that request power consumption adjustments to be initiated at one or more datacenters by the remote master control system 262 over short time intervals, such as across minutes or seconds. For example, the power entity 1140 may communicate to the remote master control system 262 to ramp power consumption down to a particular level within the next 5 minutes. As a result, the remote master control system 262 may provide instructions to one or more datacenters to ramp down power consumption using a linear ramp over the next 5 minutes to meet the particular level specified by the power entity 1140. The remote master control system 262 may monitor the linear ramp down of power consumption and increase or decrease the rate that the datacenter(s) ramp down power use based on projections and updates received from the power entity 1140. As a result, although the ramp down of power consumption may initially be performed in a linear manner to meet a power target threshold, the remote master control system 262 may adjust the rate of power consumption decrease based on updates from the power entity 1140. For example, 25 percent of the overall power consumption ramp down may occur during a first period (e.g., 4 minutes 30 seconds) of the 5 minutes and the remaining 75 percent of the overall power consumption ramp down may occur during the remaining period of the 5 minutes (e.g., the final 30 seconds). The example percentages are included for illustration purposes and can vary within examples based on various parameters, such as additional communication (e.g., adjustments) provided by the power entity 1140.
In further examples, a power option agreement may operate similarly to both a fixed-duration 1144 and a dynamic power option agreement 1146. Particularly, power option data specifying minimum power thresholds and corresponding time intervals may be provided in advance for the entire fixed-duration of time (e.g., the next 24 hours). Additional power option data may then be subsequently provided enabling the remote master control system 262 to make one or more adjustments to accommodate any changes specified within the additional power option data. For instance, additional power option data may indicate that a power entity exercised its option to deliver less power to the load. As a result, the remote master control system may instruct the load to adjust power consumption based on the power entity reducing the power threshold minimum via exercising the option.
As indicated above, the remote master control system 262 may monitor conditions in addition to the constraints set forth in power option data received from the power entity 1140. Particularly, the remote master control system 262 may monitor and analyze a set of conditions (including the power option data) to determine strategies for assigning, transferring, and otherwise managing computational operations using the one or more datacenters 1102-1106. The determined strategies may enable efficient operation by the datacenters while also ensuring that the datacenters operate at target power consumption levels that meet or exceed the minimum power thresholds set forth within one or more power option agreements.
Example monitored conditions include, but are not limited to, power availability 1120, power prices 1122, computing systems parameters 1124, cryptocurrency prices 1126, computational operation parameters 1128, and weather conditions 1129. Power availability 1120 may include determining power consumption ranges at a set of computing systems and/or at one or more datacenters. In addition, power availability 1120 may also involve determining the source or sources of power available at a datacenter. For instance, the remote master control system 262 may identify the types of power sources (e.g., BTM, grid power, and/or a battery system) that a datacenter has available. Power prices 1122 may involve an analysis of the different costs associated with powering a set of computing systems. For instance, the remote master control system 262 may determine cost of power from the grid without a power option agreement relative to the cost power from the grid under the power option agreement. In addition, the remote master control system 262 may also compare the cost of grid power relative to the cost of BTM power when available at a datacenter. The power prices 1122 may also involve comparing the cost of using power at different datacenters to determine which datacenter may perform computational operations at a lower cost.
Monitoring computing system parameters 1124 may involve determining parameters related to the computing systems at one or more datacenters. For instance, the remote master control system 262 may monitor various parameters of the computing systems at a datacenter, such as the abilities and availability of various computing systems, the status of the queue used to store computational operations awaiting performance by the computing systems. The remote master control system 262 may determine types and operation modes of the computing systems, including which computing systems could operate in different modes (e.g., a higher power or a lower power mode) and/or at different hash rates and/or frequencies. The remote master control system 262 may also estimate when computing systems may complete current computational operations and/or how many computational operations are assigned to computing systems.
Monitoring cryptocurrency prices 1126 may involve monitoring the current price of one or more cryptocurrencies, the hash rate and/or estimated power consumption associated with mining each cryptocurrency, and other factors associated with the cryptocurrencies. The remote master control system 262 may use data related to monitoring cryptocurrency prices 1126 to determine whether using computing systems to mine a cryptocurrency generates more revenue than the cost of power required for performance of the mining operations.
The remote master control system 262 may monitor parameters related to computational operations (e.g., computational operation parameters 1128). For example, the remote master control system 262 may monitor parameters related to the computational operations requiring performance and currently being performed, such quantity of operations, estimated time to complete, cost to perform each computational operation, deadlines and priorities associated with each computational operation. In addition, the remote master control system 262 may analyze computational operations to determine if a particular type of computing system may perform the computational operation better than other types of computing systems.
Monitoring weather conditions 1129 may include monitoring for any potential power generation disruption due to emergencies or other events, and changes in temperatures or weather conditions at power generators or datacenters that could affect power generation. As such, the operations and environment analysis module (or another component) of the remote master control system 262 may be configured to monitor one or more conditions described above.
The performance strategy determined by the remote master control system 262 based on the monitored conditions and/or power option data can include control instructions for the load (e.g., the datacenters and/or one or more sets of computing systems). For instance, a performance strategy can specify operating parameters, such as operating frequencies, power consumption targets, operating modes, power on/off and/or standby states, and other operation aspects for computing systems at a datacenter.
The performance strategy can also involve aspects related to the assignment, transfer, and performance of computational operations at the computing systems. For instance, the performance strategy may specify computational operations to be performed at the computing systems, an order for completing computational operations based on priorities associated with the computational operations, and an identification of which computing systems should perform which computational operations. In some instances, priorities may depend on revenue associated with completing each computational operation and deadlines for each computational operation.
The monitored conditions may enable efficient distribution and performance of computational operations among computing systems at one or more datacenters (e.g., datacenters 1102-1106) in ways that can reduce costs and/or time to perform computational operations, take advantage of availability and abilities of computing systems at the datacenters 1102-1106, and/or take advantage in changes in the cost for power at the datacenters 1102-1106. In addition, the monitored conditions may also involve consideration of the power option data to ensure that the computing systems consume enough power to meet minimum power thresholds set forth in one or more power option agreements.
The various monitored conditions described above as well as other potential conditions may change dynamically and with great frequency. Thus, to enable efficient distribution and performance of the computational operations at the datacenters, the remote master control system 262 may be configured to monitor changes in the various conditions to assist with the efficient management and operations of the computing systems at each datacenter. For instance, the remote master control system 262 may engage in wired or wireless communication 1130 with datacenter control systems (e.g., datacenter control system 504) at each datacenter as well as other sources (e.g., the power entity 1140) to monitor for changes in the conditions.
The remote master control system 262 may analyze the different conditions in real-time to modulate operating attributes of computing systems at one or more of the datacenters. By using the monitored conditions, the remote master control system 262 may increase revenue, decrease costs, and/or increase performance of computational operations via various modifications, such as transferring computational operations between datacenters or sets of computing systems within a datacenter and adjusting performance at one or more sets of computing systems (e.g., switching to a low power mode).
In some examples, the traditional datacenter 1106 may be the load subject to a power option agreement. As such, the remote master control system 262 may factor the power option agreement when determining whether to perform computational operations using the computing systems 1112 at the traditional datacenter 1106 and/or transfer computational operations to the computing systems 1108, 1110 at the flexible datacenters 1102, 1104. For instance, the monitored conditions may indicate that the price of grid power is substantially higher than BTM power. As a result, the remote master control system 262 may transfer a subset of computational operations from the traditional datacenter 1106 to the flexible datacenters 1102, 1104. The traditional datacenter 1106 may still have some computational operations to perform to ensure that the traditional datacenter 1106 is using enough power to meet the minimum power threshold or thresholds set forth in the power option agreement.
In some examples, the remote master control system 262 may monitor the grid frequency signal received from the power entity 1140. When the frequency of the grid deviates a threshold amount (e.g., 0.036 Hz above or below 60 Hz), the remote master control system 262 may adjust performance strategies at the load. In some cases, the remote master control system 262 may adjust the power consumption at the load, the number of miners (or computing systems) operating at the load, and/or the frequency or hash rate, among other possible changes. The remote master control system may readjust performance strategies at the load in response to receiving additional power option data from the power entity 1140 (e.g., an indication that the frequency of the grid is back to 60 Hz). In addition, the remote master control system 262 may communicate changes in operations at the load to the power entity 1140. This way, the power entity 1140 may obtain confirmation that the load is adjusting in accordance with a power option agreement.
In some embodiments, a power generation source (e.g., the generation station 400 shown in
In some examples, a power option agreement may depend on parameters associated balancing grid capacity and demand. For instance, power option agreements may incentivize power consumption ramping during periods of peak grid power use.
The graph line 1206 represents sets of minimum power thresholds 1206A, 1206B, 1206C that are specified by power option data based on the power option agreement. As shown, the graph line 1206 extends the entire 24 hour duration, which indicates that the set of time intervals associated with minimum power thresholds add up to 24 hours. In other examples, the power option agreement may not include a minimum power threshold during a portion of the duration.
The graph line 1206 of the graph 1200 is further used to illustrate power consumption levels that one or more loads (e.g., a set of computing systems) operating according to the power option agreement may utilize during the 24 hour duration. Particularly, the power quantities above the graph line 1206 represents power levels that the load(s) may consume from the power grid during the 24 hour duration that would satisfy the requirements (i.e., the minimum power thresholds 1206A-1206C) set forth by the power option agreement. In particular, the power quantities above the graph line 1206 include any power quantity that meets or exceeds the minimum power threshold at that time. By extension, the power quantities positioned below the graph line 1206 represents the amount of power that the load could be directed to reduce power consumption by per the power option agreement.
To further illustrate, an initial minimum power threshold 1206A is shown associated with the time interval starting at hour 0 and extending to hour 8. In particular, the minimum power threshold 1206A is set at 5 MW during this time interval. Thus, based on the power option data shown in
As further shown in the graph 1200 illustrated in
The last minimum power threshold 1206C is associated with the time interval that starts at hour 16 and extends until hour 24. Similar to the initial minimum power threshold 1206A associated with the beginning of the graph line 1206, the last minimum power threshold 1206 is also set at 5 MW. As such, at any point during this interval (hour 16 to hour 24) the loads may consume 5 MW or more to operate in accordance with the power option agreement. As discussed above, by operating at 5 MW or more, the load enables the power consumed from the power grid to be reduced any amount from zero up to 5 MW during this time interval.
When determining the power consumption strategy for a load, a computing system (e.g., the remote master control system 262) may consider various conditions in addition to the power option data received based on one or more power option agreements. Particularly, the computing system may consider and weigh different conditions in addition to the power option data to determine power consumption targets and/or other control instructions for a load. The conditions may include, but are not limited to, the price of grid power, the price of alternative power sources (e.g., BTM power, stored energy), the revenue associated with mining for one or more cryptocurrencies, parameters related to the computational operations requiring performance (e.g., priorities, deadlines, status of the queue organizing the operations, and/or revenue associated with completing each computational operation), parameters related to the set of computing systems (e.g., types and availabilities of computing systems), and other conditions (e.g., penalties if a minimum power threshold is not met and/or monetary benefits from operating under a power option agreement). By weighing various conditions, the computing system may efficiently manage the set of computing systems, including enabling performance of computational operations cost effectively and/or ensuring at that computing systems operate at target power consumption levels that one or more satisfy power option agreements.
In some examples, the computing system may decrease the amount of power that a set of computing systems consumes from one source and while also increasing the amount of power that the set consumes from another source. For instance, the computing system may determine that the price of power grid power is above a threshold price that makes computational operations relatively expensive to perform using grid power. As a result, the computing system may provide control instructions for the computing systems to consume power grid power that matches a minimum power threshold specified by power option data. This may enable the computing systems to satisfy the power option agreement while also avoiding using pricey grid power beyond the minimum amount required per the power option data. In addition, the computing system may instruct some computing systems to switch to a low power mode or temporarily stop until the price of power from the grid decreases. The computing system may instruct one or more computing systems to operate using power from another source (e.g., BTM power and/or stored energy from a battery system) and/or transfer one or more computational operations to another set of computing systems (e.g., a different datacenter).
When the power option agreement is a fixed duration power option agreement, the computing system may receive an indication of all the minimum power thresholds 1206A-1206C and an indication of the associated time interval altogether and in advance of the duration associated with the power option agreement. By providing all of the minimum power thresholds 1206A-1206C and the time intervals in advance, the computing system may determine a performance strategy for the load that can extend across the entire duration. Particularly, the computing system may factor the minimum power thresholds and associated time intervals as well as other monitored conditions to determine the performance strategy for the total duration. This can enable the computing system to accept and assign computational operations to computing systems in advance while also using a performance strategy that meets the expectations of a power option agreement.
In some examples, the performance strategy determined by the computing system may include control instructions for the set of computing systems to execute if a power option is exercised. For instance, the performance strategy may specify different power consumption targets for the computing systems that depend on whether a power option is exercised during each time interval.
In some instances, the computing system may modify the performance strategy when one or more conditions change enough to warrant a modification. For instance, the computing system may receive an indication of a change in a minimum power threshold (e.g., a decrease in the minimum power threshold) and determine one or more modifications based on the new minimum power threshold and/or other conditions (e.g., a change in the price of power).
In other examples, the power option agreement may be a dynamic power option agreement. Particularly, the load may be subject to a changing minimum power threshold that can vary during a predefined duration associated with the power option agreement. For example, a dynamic power option agreement may specify that the load is subject to a minimum power threshold that may vary from 0 MW up to 5 MW during the next 24 hours and the particular minimum threshold for each hour may depend on power option data received from the power entity during the prior hour. The dynamic power option agreement may further specify the expected response time from the load. For instance, the power option agreement may indicate that an indication of a new minimum power threshold will be provided an hour prior to the start of the minimum power threshold. The computing system, for example, may receive an indication at hour 7 about the increase in the minimum power threshold 1206B starting at hour 8. The indication may (or may not) specify the total time interval associated with a new minimum power threshold. For instance, the indication received by the computing system may specify that the 10 MW minimum power threshold 1206B extends from hour 8 until hour 16. In other instances, the power option data may indicate that the computing system should abide by the new minimum power threshold until receiving further power option data indicating a change to another new minimum power threshold.
In some examples, the power option data may arrive at the computing system in an unknown order from the power entity with expectations of swift power consumption adjustments by the load. As a result, the power option agreement may require fast ramping of the load to meet changes. Ramping may involve ramping up or down power consumption as well as ramping operating techniques (e.g., adjusting frequency or operation mode).
In some embodiments, the type of power option power agreement may depend on the delivery and content of power option data provided to the load (or a control system controlling the load). For instance, a computing system may receive minimum power thresholds set across an entire duration associated with a power option agreement in advance when the power option agreement is a fixed-duration power option agreement. In other instances, the computing system may receive power option data dynamically and adjust operations in real-time (or near real-time). For instance, the computing system may receive a series of power option data that each specifies minimum power threshold changes during the duration set forth in the dynamic power option agreement. To illustrate an example, the computing system may receive power option data during hour 1 that specifies the minimum power threshold for hour 2, power option data during hour 2 that specifies the minimum power threshold for hour 3, and so on across the duration of the dynamic power option agreement.
In some examples, the minimum power threshold for a time interval may be zero during the duration of a power option agreement. As such, the load may use any amount of power from the power grid in accordance with the power option agreement, including no power at all during this time interval. When the price for power is high during this time frame, the load may ramp down power usage to zero MW to avoid paying the high price for power while still being in compliance with the power option agreement.
At step 1302, the method 1300 involves monitoring a set of conditions. For instance, a computing system (e.g., a control system) may monitor various conditions that could impact the performance of operations at one or more loads, including the power consumption targets at the loads. The set of monitored conditions may include a variety of information obtained from one or more external sources, such as one or more datacenters, databases, power generation stations, or types of sources.
Some example conditions include, but are not limited to, the price of grid power, the price and availability of alternative power options (e.g. BTM power, and/or stored energy), parameters of the load (e.g., ramping abilities, type of computing systems, operation modes, etc.), parameters of tasks to be performed using the power at the load (e.g., types, deadlines, priorities, and/or revenue associated with computational operations), availability of other computing systems and their associated costs, and/or revenue associated with mining a cryptocurrency. The computing system may monitor one or more of these conditions as well as others.
At step 1304, the method 1300 involves receiving power option data based, at least in part, on a power option agreement. As discussed above, the computing system (e.g., a remote master control system) may engage in a power option agreement with a power entity. As a result, the computing system may control a load (e.g., a set of computing systems) in accordance with power thresholds and time intervals received from the power entity based on the power option agreement.
In some examples, the power option data may specify a set of minimum power thresholds and a set of time intervals. Each minimum power threshold in the set of minimum power thresholds may be associated with a time interval in the set of time intervals. To illustrate an example, the power option data may specify a first minimum power threshold associated with a first time interval and a second minimum power threshold associated with a second time interval, with the second time interval subsequent to the first time interval.
The set of time intervals may add up to the duration represented by the power option agreement. For instance, the total duration of the set of time intervals may correspond to a twenty-four hour period (e.g., the next day). In other examples, the power option agreement may span across a different duration (e.g., 12 hours). In additional embodiments, the power option data may specify other information, such as monetary incentives associated with parameters of the power option agreement and/or one or more maximum power thresholds.
At step 1306, the method 1300 involves determining a performance strategy for the set of computing systems based on a combination of at least a portion of the power option data and at least one condition in the set of conditions. The performance strategy may be determined responsive to receiving the power option data. In addition, the performance strategy may include a power consumption target for the set of computing systems for each time interval in the set of time intervals. In some examples, each power consumption target is equal to or greater than the minimum power threshold associated with each time interval.
As an example, the performance strategy may specify a first power consumption target for the set of computing systems for a first time interval such that the first power consumption target is equal to or greater than a first minimum power threshold associated with the first time interval and a second power consumption target for the set for a second time interval in a similar manner (i.e., the second power consumption target is equal to or greater than a second minimum power threshold).
In some examples, the performance strategy may include an sequence for the set of computing systems to follow when performing computational operations. The sequence, for example, may be based on priorities associated with the computational operations. In addition, the performance strategy may include one or more power consumption targets that are greater than the minimum power thresholds when the price of power from the power grid is below a threshold price during the time intervals associated with the minimum power thresholds.
The performance strategy may also involve transferring, delaying, or adjusting one or more computational operations performed at the set of computing systems. In addition, the performance strategy may involve adjusting operations at the computing systems. For instance, one or more computing systems may switch modes (e.g., operate at a higher frequency or switch to a low power mode).
In addition, the performance strategy may also specify power consumption targets for the set of computing systems to use if the power option is exercised during an interval. This way, the computing systems may continue to perform computational operations (or suspend performance) based on the power option being exercised.
At step 1308, the method 1300 involves providing instructions to the set of computing systems to perform one or more computational operations based on the performance strategy. For example, the set of computing systems may operate according to the performance strategy to ensure that the minimum power thresholds are met during the defined time intervals based on the power option agreement.
Some examples may further involve receiving subsequent power option data based, at least in part, on the power option agreement. The subsequent power option data may specify to decrease one or more minimum power thresholds of the set of power thresholds. Responsive to receiving the subsequent power option data, the performance strategy for the set of computing systems may be modified based on a combination of at least a portion of the subsequent power option data and one or more conditions of the monitored conditions. The modified performance strategy may include one or more reduced power consumption targets for the set of computing systems. The amount of the reduction in a power consumption target may depend linearly with the amount that the corresponding minimum power threshold was reduced by. For instance, when a minimum power threshold for a time interval is reduced from 10 MW to 5 MW, the power consumption target for that time interval may be reduced from 10 MW to 5 MW. Instructions may be provided to the set of computing systems to perform computational operations based on the modified performance strategy.
At block 1402, the method 1400 involves monitoring a set of conditions. Similar to block 1302 of the method 1300, a computing system may monitor various conditions to determine instructions for controlling a set of computing systems.
At block 1404, the method 1400 involves receiving first power option data based, at least in part, on a power option agreement while monitoring the set of conditions. The first power option data may specify a first minimum power threshold associated with a first time interval. For example, the first power option data may specify a minimum power threshold of 10 MW for the next hour, which may start in an hour or less.
The power option agreement may correspond to a dynamic power option agreement in some examples. When managing a load with respect to a dynamic power option agreement, a computing system may receive power option data specifying changes in minimum power thresholds that a load (e.g., the set of computing systems) may be designated to use in the near term (e.g., the next hour). For example, the computing system may receive power option data during each hour of the duration specified by a power option agreement that indicates a minimum power threshold for the next hour.
At block 1406, the method 1400 involves providing first control instructions for a set of computing systems based on a combination of at least a portion of the first power option data and at least one condition. The first control instructions may be provided responsive to receiving the first power option data.
The first control instructions may include a first power consumption target for the set of computing systems for the first time interval. Particularly, the first power consumption target may be equal to or greater than the first minimum power threshold associated with the first time interval. For example, the first power consumption target may be greater than the first minimum power threshold when a cost of power from the power grid is below a threshold price during the first time interval. In other instances, the first power consumption target may be equal to the first minimum power threshold when the cost of power from the power grid is greater than the threshold price.
In some examples, control instructions may specify a sequence for the computing systems to follow when performing computational operations. The sequence may be based on priorities associated with each computational operation.
The first control instructions may be determined based on a combination of the first power option data, the price of power from the power grid, and parameters associated with computational operations to be performed at the set of computing systems.
In some examples, the first control instructions may involve ramping up or down power consumption at the set of computing systems. The power consumption may be ramped up or down based on the first minimum power threshold and one or more other conditions (e.g., the price of power).
At block 1408, the method 1400 involves receiving second power option data based, at least in part, on the power option agreement while monitoring the set of conditions. The computing system may receive the second power option data subsequent to receiving the first power option data. The second power option data may specify a second minimum power threshold associated with a second time interval. For example, the second minimum power threshold may be 7 MW over the duration of the upcoming hour. In other examples, the second minimum power threshold may differ as shown in
In some instances, the computing system may receive the second power option data during the first time interval such that the second time interval overlaps the first time interval. For instance, the computing system may receive the second power option data to enable real-time adjustments to be made to the power consumed at the set of computing systems.
At block 1410, the method 1400 involves providing second control instructions for the set of computing systems based on a combination of at least a portion of the second power option data and at least one condition. The second control instructions may be provided responsive to receiving the second power option data. The second control instructions may specify a second power consumption target for the set of computing systems for the second time interval. The second power consumption target may be equal to or greater than the second minimum power threshold associated with the second time interval.
In some examples, the computing system may provide a request to a QSE to determine the power option agreement. As such, the computing system may receive power option data (e.g., the first and second power option data) in response to providing the request to the QSE.
The computing system may monitor the price of power from the power grid, and the global mining hash rate and a price for a cryptocurrency (e.g., Bitcoin), among other conditions. The computing system may determine control instructions (e.g., the first and/or second control instructions) based on a combination of power option data, the price of power from the power grid, and the global mining hash rate and the price for the cryptocurrency. For instance, the computing system may cause one or more computing systems (e.g., a subset of computing systems) to perform mining operations for the cryptocurrency when the price of power from the power grid is equal to or less than a revenue obtained by performing the mining operations for the cryptocurrency.
Advantages of one or more embodiments of the present invention may include one or more of the following:
One or more embodiments of the present invention provides a green solution to two prominent problems: the exponential increase in power required for growing blockchain operations and the unutilized and typically wasted energy generated from renewable energy sources.
One or more embodiments of the present invention allows for the rapid deployment of mobile datacenters to local stations. The mobile datacenters may be deployed on site, near the source of power generation, and receive low cost or unutilized power behind-the-meter when it is available.
One or more embodiments of the present invention provide the use of a queue system to organize computational operations and enable efficient distribution of the computational operations across multiple datacenters.
One or more embodiments of the present invention enable datacenters to access and obtain computational operations organized by a queue system.
One or more embodiments of the present invention allows for the power delivery to the datacenter to be modulated based on conditions or an operational directive received from the local station or the grid operator.
One or more embodiments of the present invention may dynamically adjust power consumption by ramping-up, ramping-down, or adjusting the power consumption of one or more computing systems within the flexible datacenter.
One or more embodiments of the present invention may be powered by behind-the-meter power that is free from transmission and distribution costs. As such, the flexible datacenter may perform computational operations, such as distributed computing processes, with little to no energy cost.
One or more embodiments of the present invention provides a number of benefits to the hosting local station. The local station may use the flexible datacenter to adjust a load, provide a power factor correction, to offload power, or operate in a manner that invokes a production tax credit and/or generates incremental revenue.
One or more embodiments of the present invention allows for continued shunting of behind-the-meter power into a storage solution when a flexible datacenter cannot fully utilize excess generated behind-the-meter power.
One or more embodiments of the present invention allows for continued use of stored behind-the-meter power when a flexible datacenter can be operational but there is not an excess of generated behind-the-meter power.
One or more embodiments of the present invention allows for management and distribution of computational operations at computing systems across a fleet of datacenters such that the performance of the computational operations take advantages of increased efficiency and decreased costs.
It will also be recognized by the skilled worker that, in addition to improved efficiencies in controlling power delivery from intermittent generation sources, such as wind farms and solar panel arrays, to regulated power grids, the invention provides more economically efficient control and stability of such power grids in the implementation of the technical features as set forth herein.
While the present invention has been described with respect to the above-noted embodiments, those skilled in the art, having the benefit of this disclosure, will recognize that other embodiments may be devised that are within the scope of the invention as disclosed herein. Accordingly, the scope of the invention should be limited only by the appended claims.
The foregoing specification can be understood with reference to the following numbered paragraphs:
Numbered Paragraph 1. A system comprising:
-
- a set of computing systems, wherein the set of computing systems is configured to perform computational operations using power from a power grid; and
- a control system configured to:
- monitor a set of conditions;
- receive first power option data specifying a first minimum power usage threshold associated with a first time interval;
- responsive to receiving the first power option data, provide first control instructions for the set of computing systems based on a combination of at least: (i) a first power consumption target for the set of computing systems for the first time interval, wherein the first power consumption target is equal to or greater than the first minimum power usage threshold associated with the first time interval, and (ii) at least one condition of the set of conditions, wherein the first control instructions comprises a directive to operate a computing system of the set of computing systems during the first time interval;
- receive second power option data specifying a second minimum power usage threshold associated with a second time interval; and
- responsive to receiving the second power option data, provide second control instructions for the set of computing systems based on a combination of at least: (i) a second power consumption target for the set of computing systems for the second time interval, wherein the second power consumption target is equal to or greater than the second minimum power usage threshold associated with the second time interval, and (ii) at least one condition of the set of conditions.
Numbered Paragraph 2. The system of Numbered Paragraph 1, wherein the second control instructions comprise a directive to stop operating the computing system of the set of computing systems during the second time interval.
Numbered Paragraph 3. The system of Numbered Paragraph 1, wherein the second control instructions comprise a directive to operate a second computing system of the set of computing systems during the second time interval.
Numbered Paragraph 4. The system of Numbered Paragraph 1, wherein the control system is configured to: - receive the second power option data subsequent to receiving the first power option data.
Numbered Paragraph 5. The system of Numbered Paragraph 4, wherein the second time interval is subsequent to the first interval.
Numbered Paragraph 6. The system of Numbered Paragraph 1 wherein the set of conditions comprises a price of power from the power grid.
Numbered Paragraph 7. The system of Numbered Paragraph 1, wherein the set of conditions comprises: - a price of power from the power grid; and
- a plurality of parameters associated with one or more computational operations to be performed at the set of computing systems.
Numbered Paragraph 8. The system of Numbered Paragraph 7, wherein the control system is configured to determine the first control instructions for the set of computing systems based on a combination of at least the portion of the first power option data, the price of power from the power grid, and the plurality of parameters associated with the one or more computational operations.
Numbered Paragraph 9. The system of Numbered Paragraph 8, wherein the first control instructions specify an order for the set of computing systems to follow when performing the one or more computational operations, wherein the order is based on respective priorities associated with the one or more computational operations.
Numbered Paragraph 10. The system of Numbered Paragraph 1, wherein the first control instructions specify an assignment and/or transfer of computational operations among the set of computing systems.
Numbered Paragraph 11. The system of Numbered Paragraph 1, wherein the first power consumption target is greater than the first minimum power threshold when a cost of power from the power grid is below a threshold price during the first time interval.
Numbered Paragraph 12. The system of Numbered Paragraph 1, wherein the first power consumption target is equal to the first minimum power threshold when a cost of power from the power grid is above a threshold price during the first time interval.
Numbered Paragraph 13. The system of Numbered Paragraph 1, wherein the control system is a remote master control system positioned remotely from the set of computing systems.
Numbered Paragraph 14. The system of Numbered Paragraph 1, wherein the control system is further configured to: - provide a request to a qualified scheduling entity (QSE); and
- receive the first power option data in response to providing the request to the QSE.
Numbered Paragraph 15. The system of Numbered Paragraph 1, wherein the set of conditions monitored by the control system further comprises: - a price of power from the power grid; and
- a global mining hash rate and a price for a cryptocurrency; and
- wherein the control system is further configured to:
- determine the second control instructions for the set of computing systems based on a combination of the first power consumption target for the set of computing systems for the first time interval and at least one of: the price of power from the power grid, the global mining hash rate, and the price for the cryptocurrency,
- wherein the second control instructions specify for at least a subset of the set of computing systems to perform mining operations for the cryptocurrency when the price of power from the power grid is equal to or less than a revenue obtained by performing the mining operations for the cryptocurrency.
Numbered Paragraph 16. The system of Numbered Paragraph 1, wherein the control system is further configured to: receive the second power option data during the first time interval.
Numbered Paragraph 17. A method comprising: - monitoring, at a computing system, a set of conditions;
- receiving first power option data specifying a first minimum power usage threshold associated with a first time interval;
- responsive to receiving the first power option data, providing first control instructions for a set of computing systems based on a combination of at least: (i) a first power consumption target for the set of computing systems for the first time interval, wherein the first power consumption target is equal to or greater than the first minimum power usage threshold associated with the first time interval, and (ii) at least one condition of the set of conditions, wherein the first control instructions comprises a directive to operate a computing system of the set of computing systems during the first time interval;
- receiving second power option data specifying a second minimum usage power threshold associated with a second time interval; and
- responsive to receiving the second power option data, providing second control instructions for the set of computing systems based on a combination of at least (i) a second power consumption target for the set of computing systems for the second time interval, wherein the second power consumption target is equal to or greater than the second minimum power usage threshold associated with the second time interval, and (ii) at least one condition of the set of conditions.
Numbered Paragraph 18. The method of Numbered Paragraph 17, wherein the second control instructions comprise a directive to stop operating the computing system of the set of computing systems during the second time interval.
Numbered Paragraph 19. The method of Numbered Paragraph 17, wherein the second control instructions comprise a directive to operate a second computing system of the set of computing systems during the second time interval.
Numbered Paragraph 20. The method of Numbered Paragraph 17, wherein monitoring the set of conditions comprises monitoring a price of power from a power grid.
Numbered Paragraph 21, The method of Numbered Paragraph 17, wherein monitoring the set of conditions comprises monitoring: (i) a price of power from a power grid, and (ii) a plurality of parameters associated with one or more computational operations to be performed at the set of computing systems.
Numbered Paragraph 22. The method of Numbered Paragraph 17, wherein providing first control instructions for the set of computing systems based on the combination of at least the portion of the first power option data and at least one condition of the set of conditions comprises specifying one or more operating modes of the set of computing systems.
Numbered Paragraph 23. The method of Numbered Paragraph 17, wherein providing the first control instructions comprises specifying power on/off and/or standby states of the set of computing systems.
Numbered Paragraph 24. The method of Numbered Paragraph 17, wherein the directive of the first control instructions specifies an order for the set of computing systems to follow when performing the one or more computational operations, wherein the order is based on respective priorities associated with the one or more computational operations.
Numbered Paragraph 25. The method of Numbered Paragraph 17, wherein receiving the second power option data comprises: - receiving the second power option data during the first time interval; and
- wherein providing second control instructions for the set of computing systems comprises providing the second control instructions for the set of computing systems prior to an end of the first time interval.
Numbered Paragraph 26. A non-transitory computer readable medium having stored therein instructions executable by one or more processors to cause a computing system to perform functions comprising: - monitoring, at a computing system, a set of conditions;
- receiving first power option data specifying a first minimum power usage threshold associated with a first time interval;
- responsive to receiving the first power option data, providing first control instructions for a set of computing systems based on a combination of at least: (i) a first power consumption target for the set of computing systems for the first time interval, wherein the first power consumption target is equal to or greater than the first minimum power usage threshold associated with the first time interval, and (ii) at least one condition of the set of conditions, wherein the first control instructions comprises a directive to operate a computing system of the set of computing systems during the first time interval;
- receiving second power option data specifying a second minimum usage power threshold associated with a second time interval; and
- responsive to receiving the second power option data, providing second control instructions for the set of computing systems based on a combination of at least (i) a second power consumption target for the set of computing systems for the second time interval, wherein the second power consumption target is equal to or greater than the second minimum power usage threshold associated with the second time interval, and (ii) at least one condition of the set of conditions.
Claims
1. A system comprising:
- a set of computing systems, wherein the set of computing systems is configured to perform computational operations using power from a power grid; and
- a control system configured to:
- monitor a set of conditions;
- receive first power option data specifying a first minimum power usage threshold associated with a first time interval;
- responsive to receiving the first power option data, provide first control instructions for the set of computing systems based on a combination of at least: (i) a first power consumption target for the set of computing systems for the first time interval, wherein the first power consumption target is equal to or greater than the first minimum power usage threshold associated with the first time interval, and (ii) at least one condition of the set of conditions, wherein the first control instructions comprises a directive to operate a computing system of the set of computing systems during the first time interval;
- receive second power option data specifying a second minimum power usage threshold associated with a second time interval; and
- responsive to receiving the second power option data, provide second control instructions for the set of computing systems based on a combination of at least: (i) a second power consumption target for the set of computing systems for the second time interval, wherein the second power consumption target is equal to or greater than the second minimum power usage threshold associated with the second time interval, and (ii) at least one condition of the set of conditions.
2. The system of claim 1, wherein the second control instructions comprise a directive to stop operating the computing system of the set of computing systems during the second time interval.
3. The system of claim 1, wherein the second control instructions comprise a directive to operate a second computing system of the set of computing systems during the second time interval.
4. The system of claim 1, wherein the control system is configured to:
- receive the second power option data subsequent to receiving the first power option data.
5. The system of claim 4, wherein the second time interval is subsequent to the first interval.
6. The system of claim 1 wherein the set of conditions comprises a price of power from the power grid.
7. The system of claim 1, wherein the set of conditions comprises:
- a price of power from the power grid; and
- a plurality of parameters associated with one or more computational operations to be performed at the set of computing systems.
8. The system of claim 7, wherein the control system is configured to determine the first control instructions for the set of computing systems based on a combination of at least the portion of the first power option data, the price of power from the power grid, and the plurality of parameters associated with the one or more computational operations.
9. The system of claim 8, wherein the first control instructions specify an order for the set of computing systems to follow when performing the one or more computational operations, wherein the order is based on respective priorities associated with the one or more computational operations.
10. The system of claim 1, wherein the first control instructions specify an assignment and/or transfer of computational operations among the set of computing systems.
11. The system of claim 1, wherein the first power consumption target is greater than the first minimum power threshold when a cost of power from the power grid is below a threshold price during the first time interval.
12. The system of claim 1, wherein the first power consumption target is equal to the first minimum power threshold when a cost of power from the power grid is above a threshold price during the first time interval.
13. The system of claim 1, wherein the control system is a remote master control system positioned remotely from the set of computing systems.
14. The system of claim 1, wherein the control system is further configured to:
- provide a request to a qualified scheduling entity (QSE); and
- receive the first power option data in response to providing the request to the QSE.
15. The system of claim 1, wherein the set of conditions monitored by the control system further comprises:
- a price of power from the power grid; and
- a global mining hash rate and a price for a cryptocurrency; and
- wherein the control system is further configured to:
- determine the second control instructions for the set of computing systems based on a combination of the first power consumption target for the set of computing systems for the first time interval and at least one of: the price of power from the power grid, the global mining hash rate, and the price for the cryptocurrency,
- wherein the second control instructions specify for at least a subset of the set of computing systems to perform mining operations for the cryptocurrency when the price of power from the power grid is equal to or less than a revenue obtained by performing the mining operations for the cryptocurrency.
16. The system of claim 1, wherein the control system is further configured to: receive the second power option data during the first time interval.
17. A method comprising:
- monitoring, at a computing system, a set of conditions;
- receiving first power option data specifying a first minimum power usage threshold associated with a first time interval;
- responsive to receiving the first power option data, providing first control instructions for a set of computing systems based on a combination of at least: (i) a first power consumption target for the set of computing systems for the first time interval, wherein the first power consumption target is equal to or greater than the first minimum power usage threshold associated with the first time interval, and (ii) at least one condition of the set of conditions, wherein the first control instructions comprises a directive to operate a computing system of the set of computing systems during the first time interval;
- receiving second power option data specifying a second minimum usage power threshold associated with a second time interval; and
- responsive to receiving the second power option data, providing second control instructions for the set of computing systems based on a combination of at least (i) a second power consumption target for the set of computing systems for the second time interval, wherein the second power consumption target is equal to or greater than the second minimum power usage threshold associated with the second time interval, and (ii) at least one condition of the set of conditions.
18. The method of claim 17, wherein the second control instructions comprise a directive to stop operating the computing system of the set of computing systems during the second time interval.
19. The method of claim 17, wherein the second control instructions comprise a directive to operate a second computing system of the set of computing systems during the second time interval.
20. The method of claim 17, wherein monitoring the set of conditions comprises monitoring a price of power from a power grid.
Type: Application
Filed: Feb 6, 2023
Publication Date: Jun 15, 2023
Inventors: Michael T. McNamara (Newport Beach, CA), Raymond E. Cline, JR. (Houston, TX)
Application Number: 18/106,098